IDOT contract 62X60 bid tabulation
Section 2024-1020-RS. Let by Illinois DOT on June 13, 2025, Dupage, District 01. 3 bids received; low bid $842,712 by R. W. Dunteman Company.
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 73
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | R. W. Dunteman Company | $842,712 | Low |
| 2 | Plote Construction, Inc. | $851,000 | +1.0% |
| 3 | A Lamp Concrete Contractors, Inc. | $868,956 | +3.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R. W. Dunteman Company | 2. Plote Construction, Inc. | 3. A Lamp Concrete Contractors, Inc. |
|---|---|---|---|---|---|---|
| 1 | Constructn layout SPL (X0320050) | LS | 1 | $3,000.00 | $1,500.00 | $8,900.00 |
| 2 | Tree limb rem 4-10 (X2010100) | EACH | 2 | $150.00 | $150.00 | $150.00 |
| 3 | Tree rem<6 unit flush (X2010108) | UNIT | 10 | $25.00 | $25.00 | $25.00 |
| 4 | Tree limb rem over 10 (X2010200) | EACH | 3 | $150.00 | $150.00 | $150.00 |
| 5 | Selective clearing (X2010516) | UNIT | 9 | $325.00 | $325.00 | $325.00 |
| 6 | Grading & shap SHLDRS (X2020110) | UNIT | 14 | $250.17 | $356.05 | $550.00 |
| 7 | Prun safety/equip CLR (X2100002) | UNIT | 4 | $600.00 | $600.00 | $600.00 |
| 8 | Eros cont blanket SPL (X2511630) | SY | 3,200 | $1.00 | $2.05 | $2.05 |
| 9 | Temporary ramp SPL (X4060995) | SY | 186 | $13.86 | $20.00 | $25.00 |
| 10 | CC&G RMVL repl < = 10 (X4400501) | LF | 235 | $139.22 | $85.00 | $91.00 |
| 11 | CC&G RMVL repl > 10FT (X4400503) | LF | 50 | $130.84 | $105.00 | $81.00 |
| 12 | SS cleaned 12 (X5537800) | LF | 150 | $10.00 | $10.00 | $10.00 |
| 13 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 6 | $3,500.00 | $4,000.00 | $1,500.00 |
| 14 | Temp info signing (X7200061) | SF | 51.40 | $15.00 | $16.00 | $25.00 |
| 15 | Drainage STR cleaned (Z0018500) | EACH | 10 | $500.00 | $500.00 | $500.00 |
| 16 | Tree remov 6-15 (20100110) | UNIT | 210 | $34.00 | $34.00 | $34.00 |
| 17 | Earth excavation (20200100) | CY | 430 | $38.50 | $65.00 | $35.00 |
| 18 | Topsoil F & P 2 (21101605) | SY | 1,000 | $5.00 | $3.50 | $3.50 |
| 19 | Topsoil F & P 4 (21101615) | SY | 2,285 | $0.10 | $6.75 | $6.75 |
| 20 | Grading & shap ditch (21400100) | LF | 3,300 | $4.03 | $7.00 | $6.85 |
| 21 | Seeding CL 2A (25000210) | ACRE | 0.67 | $29,040 | $5,000.00 | $5,000.00 |
| 22 | Nitrogen fert nutr (25000400) | LB | 45 | $1.00 | $2.00 | $2.00 |
| 23 | Potassium fert nutr (25000600) | LB | 45 | $1.00 | $2.00 | $2.00 |
| 24 | Sodding salt tolerant (25200110) | SY | 85 | $1.00 | $22.00 | $22.00 |
| 25 | Supple watering (25200200) | UNIT | 10 | $0.10 | $1.00 | $1.00 |
| 26 | Perimeter eros bar (28000400) | LF | 925 | $4.00 | $3.50 | $3.50 |
| 27 | HMA base cse 6 (35501308) | SY | 250 | $58.61 | $130.00 | $42.00 |
| 28 | Bit matls tack CT (40600290) | LB | 6,800 | $0.99 | $0.01 | $0.01 |
| 29 | Long joint sealant (40600370) | LF | 3,475 | $5.81 | $6.00 | $5.50 |
| 30 | Mix CR JTS flangewys (40600400) | TON | 20 | $417.59 | $250.00 | $100.00 |
| 31 | HMA surf rem butt JT (40600982) | SY | 120 | $31.15 | $5.00 | $34.00 |
| 32 | HMA BC IL-9.5 N70 (40602985) | TON | 1,129 | $98.60 | $95.00 | $99.00 |
| 33 | HMA SC IL-9.5 D N50 (40604060) | TON | 35 | $188.75 | $290.00 | $134.00 |
| 34 | HMA SC IL-9.5 D N70 (40604062) | TON | 988 | $98.60 | $88.00 | $98.00 |
| 35 | Protective coat (42001300) | SY | 376 | $1.00 | $5.00 | $1.00 |
| 36 | PC conc sidewalk 5 (42400200) | SF | 2,000 | $14.50 | $15.00 | $9.50 |
| 37 | Detectable warnings (42400800) | SF | 66 | $39.00 | $65.00 | $25.00 |
| 38 | HMA surf rem 3 3/4 (44000164) | SY | 10,075 | $5.04 | $5.00 | $4.50 |
| 39 | Sidewalk rem (44000600) | SF | 1,000 | $3.52 | $3.00 | $2.00 |
| 40 | CL D patch T2 12 (44201789) | SY | 302 | $160.68 | $80.00 | $40.00 |
| 41 | CL D patch T3 12 (44201794) | SY | 101 | $144.22 | $80.00 | $40.00 |
| 42 | CL D patch T4 12 (44201796) | SY | 650 | $129.94 | $80.00 | $40.00 |
| 43 | Agg wedge SHLD type B (48102100) | TON | 26 | $78.74 | $90.00 | $148.00 |
| 44 | CB reconst (60252800) | EACH | 1 | $2,350.00 | $2,350.00 | $2,350.00 |
| 45 | Man reconst (60257900) | EACH | 1 | $2,850.00 | $2,850.00 | $2,850.00 |
| 46 | FR & lids adjust (60300305) | EACH | 5 | $1,850.00 | $1,850.00 | $1,850.00 |
| 47 | FR & lids T1 OL (60406000) | EACH | 1 | $880.00 | $880.00 | $880.00 |
| 48 | FR & lids T1 CL (60406100) | EACH | 1 | $880.00 | $880.00 | $880.00 |
| 49 | Pipe culv cleaned 12 (60920012) | LF | 450 | $10.00 | $10.00 | $10.00 |
| 50 | Non SPL waste disposl (66900200) | CY | 430 | $103.23 | $50.00 | $80.00 |
| 51 | Soil disposal analy (66900530) | EACH | 3 | $1,550.00 | $1,550.00 | $1,550.00 |
| 52 | Reg sub P-const plan (66901001) | LS | 1 | $3,400.00 | $3,400.00 | $3,400.00 |
| 53 | Reg sub F con report (66901003) | LS | 1 | $500.00 | $500.00 | $500.00 |
| 54 | Reg sub mon (66901006) | CAL DAY | 3 | $700.00 | $1,000.00 | $700.00 |
| 55 | Mobilization (67100100) | LS | 1 | $49,923 | $50,400 | $52,100 |
| 56 | TR cont & prot 701501 (70102620) | LS | 1 | $24,244 | $119,063 | $202,750 |
| 57 | TR cont & prot 701801 (70102640) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 58 | Short term pavt mking (70300100) | LF | 3,308 | $1.68 | $0.01 | $0.25 |
| 59 | SHRT TRM pavt MK rem (70300150) | SF | 1,103 | $2.45 | $0.01 | $0.50 |
| 60 | Temp PVT MK LTR & sym paint (70300211) | SF | 138 | $1.75 | $0.01 | $5.00 |
| 61 | Temp PVT MK line 4 - paint (70300221) | LF | 6,922 | $0.50 | $0.01 | $0.01 |
| 62 | Temp PVT MK line 6 - paint (70300241) | LF | 161 | $0.75 | $0.01 | $0.50 |
| 63 | Temp PVT MK line 12 - paint (70300261) | LF | 469 | $1.50 | $0.01 | $0.60 |
| 64 | Temp PVT MK line 24 - paint (70300281) | LF | 90 | $3.00 | $0.01 | $2.50 |
| 65 | Temp PVT MK L4 T4 tape (70307120) | LF | 827 | $1.30 | $1.40 | $2.00 |
| 66 | THPL PVT MK LTR & sym (78000100) | SF | 138 | $8.50 | $6.00 | $5.00 |
| 67 | THPL PVT MK line 4 (78000200) | LF | 6,922 | $1.20 | $1.15 | $1.10 |
| 68 | THPL PVT MK line 6 (78000400) | LF | 161 | $2.00 | $1.50 | $1.71 |
| 69 | THPL PVT MK line 12 (78000600) | LF | 470 | $4.25 | $3.00 | $3.40 |
| 70 | THPL PVT MK line 24 (78000650) | LF | 90 | $8.50 | $6.00 | $6.80 |
| 71 | Raised refl pavt MKR (78100100) | EACH | 50 | $85.00 | $100.00 | $145.00 |
| 72 | Raised ref PVT MK rem (78300200) | EACH | 50 | $19.81 | $9.00 | $35.00 |
| 73 | PVT MKG rem WTR blast (78300202) | SF | 3,451 | $1.25 | $1.50 | $3.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.