IDOT contract 62X88 bid tabulation

Section 2024-1049-RS. Let by Illinois DOT on February 27, 2026, Cook, District 01. 5 bids received; low bid $2,806,275 by Peter Baker & Son Co..

Owner
Illinois DOT
Letting
27 FEB 2026
Pay items
111
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Peter Baker & Son Co.$2,806,275Low
2K-Five Construction Corporation$2,935,128+5.0%
3Builders Paving, LLC$2,947,527+5.0%
4Plote Construction, Inc.$2,947,685+5.0%
5Schroeder Asphalt Services, Inc.$3,182,144+13%
IDOT contract 62X88: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Peter Baker & Son Co.2. K-Five Construction Corporation3. Builders Paving, LLC4. Plote Construction, Inc.5. Schroeder Asphalt Services, Inc.
1Constructn layout SPL (X0320050)LS1$12,000$5,000.00$19,000$15,500$14,000
2Rem & reinst EX STL bench (X0320066)EACH2$1,000.00$250.00$2,500.00$3,200.00$2,500.00
3Rem & reinst EX trash rec (X0322041)EACH2$1,000.00$250.00$1,500.00$3,200.00$2,000.00
4Rod and clean EX cond (X0324599)LF1,000$2.42$0.01$0.01$0.01$0.02
5Bollard removal (X0350810)EACH2$900.00$500.00$500.00$3,200.00$500.00
6Remove & reinstall EX bollard (X0350812)EACH5$1,500.00$1,000.00$3,500.00$3,800.00$3,500.00
7Ped signal post 10 FT (X1400367)EACH5$1,745.92$1,409.43$1,600.00$1,409.43$1,650.00
8Ped signal post 5 FT (X1400378)EACH3$1,389.73$1,148.36$1,400.00$1,148.36$1,375.00
9Temporary ramp SPL (X4060995)SY177$10.00$47.68$20.00$42.78$20.00
10PC conc sidewalk 5 SP (X4240430)SF87$20.00$25.00$60.00$39.73$29.00
11Brick sidewalk rem (X4400060)SF857$5.00$2.00$10.00$4.00$5.00
12CC&G RMVL repl < = 10 (X4400501)LF62$63.00$50.00$100.00$75.15$57.00
13CC&G RMVL repl > 10FT (X4400503)LF2,521$63.00$43.11$60.00$62.00$48.75
14SS cleaned 12 (X5537800)LF2,025$2.00$2.00$2.00$2.00$18.00
15FR & lids adjust SPL (X6030310)EACH77$1,025.00$1,025.00$1,250.00$1,125.00$1,000.00
16Engrs FLD ofc TY A D1 (X6700407)CAL MO12$2,000.00$3,500.00$4,000.00$4,000.00$4,000.00
17Temp info signing (X7200061)SF752$15.00$14.00$15.00$15.00$22.00
18Accessible ped signal (X8760200)EACH16$2,175.41$2,121.62$2,200.00$2,121.62$2,400.00
19Conc FDN TY A 12D (X8780012)LF32$313.97$317.37$350.00$317.37$370.00
20Vid veh det sys SN AP (X8891009)EACH3$11,810$10,137$11,000$10,137$11,400
21Drainage STR cleaned (Z0018500)EACH135$330.00$315.00$365.00$315.00$59.00
22RE-optimize TR sig sys 1 (Z0033044)EACH3$632.50$792.00$800.00$792.00$950.00
23Earth excavation (20200100)CY75$30.00$50.00$65.00$59.00$80.00
24Topsoil F & P 4 (21101615)SY290$5.00$1.00$1.00$10.00$2.00
25Sodding salt tolerant (25200110)SY290$30.00$38.00$40.00$15.00$44.00
26Supple watering (25200200)UNIT2$115.00$2.00$1.00$75.00$2.00
27HMA base cse 6 (35501308)SY24$75.00$54.30$115.00$140.00$80.00
28HMA base cse 8 (35501316)SY62$100.00$72.40$135.00$205.00$100.00
29Bit matls tack CT (40600290)LB10,771$2.30$0.01$0.01$4.00$0.01
30Long joint sealant (40600370)LF28,905$3.20$2.45$3.00$2.60$3.40
31Mix CR JTS flangewys (40600400)TON159$150.00$50.00$60.00$300.00$300.00
32HMA surf rem butt JT (40600982)SY383$1.00$15.51$20.00$15.45$15.00
33HMA BC IL-9.5 N70 (40602985)TON1,788$104.00$93.78$92.50$100.00$93.00
34P HMA BC IL-4.75 N50 (40603200)TON1,523$112.40$117.08$104.00$130.00$115.00
35HMA SC IL-9.5 D N50 (40604060)TON155$230.00$216.24$75.00$25.00$95.00
36P HMA SC SMA 9.5 F N80 (40605026)TON5,180$125.20$128.15$115.00$130.64$143.00
37Protective coat (42001300)SY1,871$0.10$1.00$0.01$1.00$2.50
38PCC driveway pavt 6 (42300200)SY6$125.00$105.00$72.00$152.00$119.00
39PCC driveway pavt 8 (42300400)SY63$115.00$110.00$81.00$121.00$125.00
40PC conc sidewalk 5 (42400200)SF7,119$9.00$10.13$12.00$11.00$11.75
41Detectable warnings (42400800)SF384$38.00$38.63$40.00$27.00$43.00
42HMA surf rem 2 1/2 (44000159)SY36,901$4.35$4.57$4.25$3.85$2.65
43HMA surf rem 3 3/4 (44000164)SY15,956$7.05$7.48$6.90$5.75$3.80
44Drive pavement rem (44000200)SY155$50.00$29.76$55.00$21.00$11.50
45Sidewalk rem (44000600)SF7,347$3.00$2.25$5.00$2.00$3.00
46Median removal (44003100)SF2,990$3.00$4.00$11.00$2.70$4.50
47CL C patch T4 12 (44201383)SY140$170.00$200.00$135.00$180.00$225.00
48CL D patch T1 12 (44201785)SY133$50.00$45.00$70.00$75.00$128.00
49CL D patch T2 12 (44201789)SY793$50.00$45.00$60.00$70.00$125.00
50CL D patch T3 12 (44201794)SY925$50.00$45.00$30.00$65.00$125.00
51CL D patch T4 12 (44201796)SY793$50.00$45.00$25.00$65.00$125.00
52Saw cuts (44213200)LF970$3.00$4.00$10.00$2.70$5.00
53Tie bars 3/4 (44213204)EACH195$10.00$10.00$20.00$7.50$12.00
54CB reconst (60252800)EACH2$1,000.00$1,000.00$1,350.00$1,150.00$2,077.00
55Man reconst (60257900)EACH1$1,100.00$1,100.00$1,450.00$1,000.00$2,702.00
56Inlets reconst (60262700)EACH1$800.00$800.00$920.00$850.00$1,460.00
57Valve box adj (60266600)EACH5$300.00$300.00$350.00$250.00$630.00
58FR & grates adjust (60300105)EACH3$450.00$450.00$450.00$440.00$640.00
59FR & lids adjust (60300305)EACH10$450.00$450.00$450.00$440.00$535.00
60FR & grates T23 (60404940)EACH1$465.00$465.00$465.00$450.00$425.00
61FR & grates T24 (60404950)EACH1$485.00$465.00$485.00$475.00$425.00
62FR & lids T1 OL (60406000)EACH3$450.00$450.00$460.00$420.00$450.00
63FR & lids T1 ADA compl OL (60406001)EACH1$450.00$450.00$460.00$420.00$530.00
64FR & lids T1 CL (60406100)EACH18$450.00$450.00$460.00$420.00$475.00
65Conc med TSB6.06 (60619200)SF1,896$19.00$18.00$22.00$24.00$20.00
66Non SPL waste disposl (66900200)CY75$70.00$107.33$200.00$100.00$105.00
67Soil disposal analy (66900530)EACH2$1,450.00$1,450.00$865.00$1,450.00$950.00
68Reg sub P-const plan (66901001)LS1$3,100.00$3,100.00$5,200.00$3,100.00$5,200.00
69Reg sub F con report (66901003)LS1$1,200.00$1,200.00$500.00$1,200.00$600.00
70Reg sub mon (66901006)CAL DAY20$680.00$680.00$750.00$680.00$850.00
71Mobilization (67100100)LS1$237,200$155,000$170,000$178,000$35,000
72TR cont & prot 701606 (70102625)LS1$1.00$1.00$1.00$1.00$1.00
73TR cont & prot 701601 (70102630)LS1$1.00$1.00$1.00$1.00$75,000
74TR cont & prot 701602 (70102632)LS1$1.00$332,962$240,000$81,700$1.00
75TR cont & prot 701611 (70102634)LS1$1.00$1.00$1.00$1.00$1.00
76TR cont & prot 701701 (70102635)LS1$1.00$1.00$1.00$1.00$1.00
77TR cont & prot 701801 (70102640)LS1$12,300$1.00$7,500.00$1.00$10,000
78Short term pavt mking (70300100)LF56,993$0.01$0.01$0.01$0.01$3.00
79SHRT TRM pavt MK rem (70300150)SF4,750$1.00$0.01$0.01$0.01$4.00
80Temp PVT MK LTR & sym paint (70300211)SF2,736$0.01$0.01$0.01$1.30$1.35
81Temp PVT MK line 4 - paint (70300221)LF43,362$0.01$0.01$0.01$0.32$0.35
82Temp PVT MK line 6 - paint (70300241)LF12,537$0.01$0.01$0.01$0.46$0.55
83Temp PVT MK line 12 - paint (70300261)LF4,899$0.01$0.01$0.01$1.00$1.15
84Temp PVT MK line 24 - paint (70300281)LF1,319$0.01$0.01$0.01$2.00$1.40
85Temp PVT MK L4 T4 tape (70307120)LF14,202$0.01$1.00$0.01$0.01$3.00
86THPL PVT MK LTR & sym (78000100)SF1,368$5.50$5.50$5.75$5.50$6.60
87THPL PVT MK line 4 (78000200)LF18,160$0.78$0.78$0.80$0.78$0.90
88THPL PVT MK line 6 (78000400)LF6,269$0.96$0.96$1.00$0.96$1.65
89THPL PVT MK line 12 (78000600)LF2,450$2.40$2.40$4.00$2.40$3.45
90THPL PVT MK line 24 (78000650)LF660$5.50$5.50$5.75$5.50$6.75
91Pref PL PM TD STD L4 (78004620)LF3,521$5.00$5.00$7.80$5.00$5.25
92Mod ureth PM line 6 (78009006)LF167$21.00$21.00$28.70$21.00$18.00
93GRV RCSD PVT MRKG 5 (78011025)LF3,521$0.65$0.65$0.70$0.65$0.90
94Raised refl pavt MKR (78100100)EACH674$37.50$37.50$38.50$37.50$52.50
95Raised ref PVT MK rem (78300200)EACH539$14.00$6.41$10.00$14.00$18.00
96Undrgrd C galvs 2 (81028200)LF190$55.48$91.69$92.00$91.69$105.00
97HD handhole (81400200)EACH1$4,809.62$6,128.16$6,250.00$6,128.16$6,800.00
98Main EX TR sig instal (85000200)EACH4$4,771.56$2,008.07$2,200.00$2,008.07$2,350.00
99Elcbl C signal 14 2C (87301215)LF1,883$2.92$3.11$3.25$3.11$3.45
100Elcbl C signal 14 3C (87301225)LF1,464$3.10$3.32$3.50$3.32$3.70
101Elcbl C lead 14 1PR (87301305)LF2,765$3.09$3.32$3.50$3.32$3.75
102Elcbl C egrdc 6 1C (87301900)LF277$4.68$3.93$4.00$3.93$4.40
103Drill EX handhole (87900200)EACH9$997.89$461.35$475.00$461.35$510.00
104Inductive loop detect (88500100)EACH7$187.20$245.13$250.00$245.13$290.00
105Det loop T1 (88600100)LF2,146$33.82$30.70$32.00$30.70$35.00
106Reloc EX ped sig head (89500200)EACH6$755.92$331.40$350.00$331.40$370.00
107Rem elcbl FR con (89502300)LF1,148$2.42$2.54$3.00$2.54$3.00
108Remov EX TS equip (89502375)EACH3$967.89$332.32$350.00$332.32$375.00
109Rebuild EX handhole (89502376)EACH1$3,803.67$4,385.32$5,000.00$4,385.32$5,000.00
110Remov EX handhole (89502380)EACH1$1,511.84$1,396.58$1,500.00$1,396.58$4,900.00
111Remov EX conc FDN (89502385)EACH1$1,269.86$481.33$500.00$481.33$530.00
IDOT contract 62X88: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way