IDOT contract 64T43 bid tabulation
Section (37-(3-1,4,5,6))BRR. Let by Illinois DOT on September 18, 2026, Henry, District 02. 4 bids received; low bid $8,698,583 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 18 SEP 2026
- Pay items
- 90
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $8,698,583 | Low |
| 2 | Civil Constructors, Inc. d/b/a/ Helm Civil | $9,250,034 | +6.0% |
| 3 | Brandt Construction Co. | $11,518,484 | +32% |
| 4 | Gensini Excavating, Inc. | $11,957,571 | +37% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Civil Constructors, Inc. d/b/a/ Helm Civil | 3. Brandt Construction Co. | 4. Gensini Excavating, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Acrylic coating (X0325748) | SY | 1,586 | $35.00 | $42.00 | $54.00 | $44.80 |
| 2 | Pref PL PM TD L 6 IO (X2700028) | LF | 460 | $9.90 | $3.39 | $3.80 | $23.87 |
| 3 | Pref PL PM TD L 9 IO (X2700029) | LF | 689 | $14.85 | $4.53 | $5.10 | $47.73 |
| 4 | BR deck grooving long (X5030250) | SY | 6,708 | $9.50 | $13.00 | $10.00 | $13.43 |
| 5 | Floor drain extension (X5030530) | EACH | 68 | $350.00 | $715.00 | $570.00 | $994.75 |
| 6 | CLN & PT exp RE-bar (X5060704) | SF | 444 | $60.00 | $124.75 | $140.00 | $87.14 |
| 7 | Bar terminators (X5080530) | EACH | 340 | $40.00 | $25.00 | $50.00 | $53.50 |
| 8 | Slope wall breaking (X5110306) | SY | 25 | $250.00 | $200.00 | $200.00 | $319.99 |
| 9 | Slope wall crack seal (X5110308) | LF | 626 | $60.00 | $38.00 | $17.00 | $50.06 |
| 10 | Slope wall repair (X5110310) | SY | 11 | $1,000.00 | $1,600.00 | $950.00 | $1,944.88 |
| 11 | Slopewall slur pumpng (X5110312) | CY | 12.50 | $1,600.00 | $650.00 | $1,165.00 | $862.05 |
| 12 | Drainage scuppers adj (X5230172) | EACH | 40 | $900.00 | $605.00 | $2,000.00 | $1,307.16 |
| 13 | Rem & rein C HWL P DR (X6015012) | EACH | 5 | $1,000.00 | $440.00 | $1,200.00 | $1,350.51 |
| 14 | Jack & rem EX bearing (Z0001899) | EACH | 36 | $5,000.00 | $3,330.00 | $2,910.00 | $2,788.42 |
| 15 | Approach slab rem (Z0004552) | SY | 571 | $40.00 | $112.00 | $70.00 | $171.62 |
| 16 | Construction layout (Z0013798) | LS | 1 | $65,000 | $27,000 | $45,000 | $146,445 |
| 17 | Diamond grind BR sec (Z0029090) | SY | 11,118 | $9.60 | $14.00 | $10.00 | $11.20 |
| 18 | Pref joint filler (Z0043900) | LF | 319 | $40.00 | $15.00 | $25.00 | $114.90 |
| 19 | RR prot liability ins (Z0048665) | LS | 1 | $5,000.00 | $8,800.00 | $25,000 | $10,848 |
| 20 | Reloc name plates (Z0049790) | EACH | 8 | $1,200.00 | $350.00 | $650.00 | $587.61 |
| 21 | Trainees (Z0076600) | HR | 2,000 | $0.80 | $0.80 | $0.80 | $0.80 |
| 22 | Trainees TPG (Z0076604) | HR | 2,000 | $15.00 | $15.00 | $15.00 | $15.00 |
| 23 | Stone riprap CL A5 (28100109) | SY | 25 | $250.00 | $315.00 | $315.00 | $272.77 |
| 24 | Stone dump rip CL A2 (28100703) | SY | 130 | $225.00 | $150.00 | $58.00 | $81.00 |
| 25 | P bit matls tack CT (40600295) | LB | 3,764 | $0.01 | $5.50 | $1.00 | $5.97 |
| 26 | HMA surf rem butt JT (40600982) | SY | 8,376 | $20.00 | $25.00 | $20.00 | $27.12 |
| 27 | Temporary ramp (40600990) | SY | 592 | $30.00 | $20.00 | $20.00 | $21.70 |
| 28 | P HMA SC IL-9.5 D N90 (40604164) | TON | 716 | $175.00 | $390.00 | $295.00 | $423.06 |
| 29 | Welded wire reinf (42000060) | SY | 536 | $25.00 | $24.00 | $28.00 | $18.62 |
| 30 | PVT con PCC BR app SL (42000080) | SY | 536 | $325.00 | $275.00 | $210.00 | $494.10 |
| 31 | Pavement rem (44000100) | SY | 320 | $30.00 | $70.00 | $115.00 | $171.62 |
| 32 | Paved SHLD removal (44004250) | SY | 216 | $30.00 | $60.00 | $42.00 | $171.63 |
| 33 | Welded wire reinf (44200050) | SY | 36 | $25.00 | $16.00 | $48.00 | $12.71 |
| 34 | CL B patch T2 12 (44200994) | SY | 18 | $450.00 | $225.00 | $535.00 | $744.81 |
| 35 | CL B patch T3 12 (44200998) | SY | 36 | $450.00 | $250.00 | $535.00 | $744.81 |
| 36 | Dowel bars 1 1/2 (44201299) | EACH | 110 | $20.00 | $26.00 | $35.00 | $35.94 |
| 37 | Saw cuts (44213200) | LF | 190 | $10.00 | $6.00 | $1.00 | $3.80 |
| 38 | Conc rem (50102400) | CY | 437.90 | $1,500.00 | $1,380.00 | $2,100.00 | $2,444.46 |
| 39 | Protective shield (50157300) | SY | 1,308 | $95.00 | $82.00 | $135.00 | $123.57 |
| 40 | Structure excavation (50200100) | CY | 334 | $55.00 | $70.00 | $55.00 | $91.22 |
| 41 | Conc struct (50300225) | CY | 133 | $1,200.00 | $916.00 | $890.00 | $2,244.24 |
| 42 | Conc sup-STR (50300255) | CY | 189.50 | $3,000.00 | $3,035.00 | $4,400.00 | $5,412.23 |
| 43 | Protective coat (50300300) | SY | 10,236 | $1.00 | $1.00 | $6.50 | $3.16 |
| 44 | Conc supstr app slab (50301350) | CY | 481.90 | $600.00 | $750.00 | $600.00 | $1,521.66 |
| 45 | F & E struct steel (50500405) | LB | 3,850 | $15.00 | $13.00 | $24.00 | $8.75 |
| 46 | Reinf bars, epoxy CTD (50800205) | LB | 217,670 | $2.50 | $2.00 | $2.55 | $1.98 |
| 47 | Bar splicers (50800515) | EACH | 1,328 | $75.00 | $70.00 | $65.00 | $61.41 |
| 48 | Pref JT strip seal (52000110) | LF | 618 | $290.00 | $300.00 | $320.00 | $299.66 |
| 49 | Elast bearing assy T1 (52100010) | EACH | 36 | $2,500.00 | $1,995.00 | $1,785.00 | $2,174.98 |
| 50 | Anchor bolts 1 (52100520) | EACH | 72 | $180.00 | $150.00 | $80.00 | $204.00 |
| 51 | Temp soil reten systm (52200020) | SF | 240 | $55.00 | $250.00 | $240.00 | $232.61 |
| 52 | Deck slab rep (part) (53016000) | SY | 10 | $1,000.00 | $1.00 | $875.00 | $1,046.53 |
| 53 | Deck slab rep (FD-T1) (53016001) | SY | 15 | $2,000.00 | $1,250.00 | $2,800.00 | $1,346.83 |
| 54 | BR deck scar 3/4 (53101002) | SY | 10,879 | $55.00 | $75.00 | $60.00 | $60.75 |
| 55 | BR DK LTX C oly 2 1/2 (53101409) | SY | 10,942 | $140.00 | $160.00 | $230.00 | $189.62 |
| 56 | STR rep con DP = < 5 (53212754) | SF | 466 | $250.00 | $250.00 | $415.00 | $548.23 |
| 57 | STR rep con DP over 5 (53212755) | SF | 3 | $800.00 | $280.00 | $985.00 | $2,342.04 |
| 58 | Granular backfill STR (58600101) | CY | 246 | $60.00 | $125.00 | $130.00 | $116.30 |
| 59 | Concrete sealer (58700300) | SF | 14,161 | $2.00 | $8.00 | $4.00 | $2.31 |
| 60 | Epoxy crack injection (59000200) | LF | 804 | $90.00 | $98.00 | $75.00 | $48.59 |
| 61 | Geocomposite wall DR (59100100) | SY | 132 | $40.00 | $33.00 | $27.00 | $38.14 |
| 62 | Conc HDWL for P drain (60100060) | EACH | 8 | $500.00 | $500.00 | $700.00 | $1,892.90 |
| 63 | P undr for struct 4 (60146304) | LF | 192 | $30.00 | $56.00 | $50.00 | $75.00 |
| 64 | FR & grates adjust (60300105) | EACH | 4 | $2,000.00 | $2,000.00 | $2,100.00 | $2,000.00 |
| 65 | Rem RE-E SPBGR TY A (63301210) | LF | 75 | $30.98 | $28.16 | $31.00 | $56.41 |
| 66 | Rem RE-E T B term T6 (63302700) | EACH | 5 | $3,238.40 | $2,944.00 | $3,300.00 | $4,230.62 |
| 67 | Mod glar SCR sys temp (63800920) | LF | 10,075 | $11.50 | $7.00 | $7.80 | $7.60 |
| 68 | Shoulder rum strip 16 (64200116) | LF | 3,680 | $5.00 | $3.00 | $3.00 | $4.19 |
| 69 | Engr field office A (67000400) | CAL MO | 8 | $5,000.00 | $4,000.00 | $3,100.00 | $4,881.50 |
| 70 | Mobilization (67100100) | LS | 1 | $492,000 | $555,002 | $700,000 | $754,355 |
| 71 | Traf cont-prot 701402 (70100207) | EACH | 10 | $0.01 | $19,800 | $22,500 | $21,479 |
| 72 | Traf cont-prot 701411 (70100420) | EACH | 2 | $0.01 | $1,500.00 | $1,700.00 | $1,627.17 |
| 73 | Traf cont-prot 701406 (70100700) | LS | 1 | $0.01 | $10,000 | $11,250 | $10,848 |
| 74 | Traf cont-prot 701401 (70100800) | LS | 1 | $200,000 | $20,000 | $22,500 | $21,696 |
| 75 | Pavt MK blkout tape 4 (70107004) | LF | 53,095 | $2.00 | $1.80 | $2.05 | $2.00 |
| 76 | Pavt MK blkout tape 8 (70107008) | LF | 2,035 | $4.00 | $2.40 | $2.70 | $2.60 |
| 77 | Pavt MK blkout tpe 12 (70107012) | LF | 465 | $8.00 | $3.60 | $4.00 | $4.00 |
| 78 | Changeable message SN (70107025) | CAL DAY | 480 | $42.50 | $40.00 | $45.00 | $44.00 |
| 79 | Temp PVT MK L4 T4 tape (70307120) | LF | 140,843 | $1.75 | $1.25 | $1.40 | $1.50 |
| 80 | Temp conc barrier (70400100) | LF | 16,750 | $30.00 | $36.00 | $76.00 | $39.05 |
| 81 | Pin temp conc barrier (70400125) | EACH | 5,736 | $15.00 | $15.00 | $30.00 | $16.27 |
| 82 | Rel temp conc barrier (70400200) | LF | 7,100 | $15.00 | $10.00 | $12.00 | $11.00 |
| 83 | Imp attn temp NRD TL3 (70600250) | EACH | 10 | $7,000.00 | $2,500.00 | $2,800.00 | $2,750.00 |
| 84 | Imp attn rel NRD TL3 (70600350) | EACH | 10 | $2,500.00 | $500.00 | $565.00 | $542.39 |
| 85 | Mod ureth PM line 4 (78009004) | LF | 10,046 | $2.75 | $1.85 | $2.10 | $4.35 |
| 86 | GRV RCSD PVT MRKG 5 (78011025) | LF | 10,046 | $2.20 | $1.83 | $2.05 | $3.50 |
| 87 | GRV RCSD PVT MRKG 7 (78011035) | LF | 460 | $3.30 | $2.75 | $3.00 | $18.50 |
| 88 | GRV RCSD PVT MRKG 10 (78011050) | LF | 689 | $4.40 | $3.65 | $4.00 | $21.25 |
| 89 | Raised refl pavt MKR (78100100) | EACH | 64 | $88.00 | $139.00 | $155.00 | $662.00 |
| 90 | Raised ref PVT MK rem (78300200) | EACH | 64 | $15.00 | $90.00 | $50.00 | $550.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of September 18, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way