IDOT contract 66N58 bid tabulation
Section (G-BR)BR-1. Let by Illinois DOT on April 24, 2026, Grundy, District 03. 2 bids received; low bid $1,596,194 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 88
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $1,596,194 | Low |
| 2 | Austin Tyler Construction, Inc. | $1,852,353 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Austin Tyler Construction, Inc. |
|---|---|---|---|---|---|
| 1 | Acrylic coating (X0325748) | SY | 26 | $143.00 | $130.00 |
| 2 | Fiber wrap (X0325749) | SF | 232 | $99.00 | $90.00 |
| 3 | HMA stab 6IN at SPBGR (X4062952) | SY | 306 | $50.00 | $48.00 |
| 4 | Linear delin panels 4 (X6350204) | EACH | 8 | $47.30 | $43.00 |
| 5 | Linear delin panels 6 (X6350206) | EACH | 6 | $75.14 | $68.00 |
| 6 | Furn perm surv MKRS (X6670106) | EACH | 1 | $50.00 | $750.00 |
| 7 | Temp info signing (X7200061) | SF | 42 | $30.00 | $25.00 |
| 8 | Jack & rem EX bearing (Z0001899) | EACH | 8 | $5,000.00 | $5,500.00 |
| 9 | Rem EX conc I-beam (Z0003615) | EACH | 6 | $4,000.00 | $7,600.00 |
| 10 | Construction layout (Z0013798) | LS | 1 | $14,000 | $15,000 |
| 11 | Debris removal (Z0015500) | LS | 1 | $5,000.00 | $5,500.00 |
| 12 | P P conc I-BM repair (Z0043800) | SF | 73 | $300.00 | $540.00 |
| 13 | Reset survey monument (Z0053700) | EACH | 1 | $2,000.00 | $600.00 |
| 14 | Temp pavement (Z0062456) | SY | 141 | $100.00 | $77.00 |
| 15 | Temporary fence (20101000) | LF | 695 | $5.00 | $6.00 |
| 16 | Earth excavation (20200100) | CY | 180 | $50.00 | $70.00 |
| 17 | Rem & disp uns matl (20201200) | CY | 10 | $100.00 | $50.00 |
| 18 | Furnished excavation (20400800) | CY | 30 | $50.00 | $120.00 |
| 19 | Seeding CL 2A (25000210) | ACRE | 0.25 | $1,331.00 | $1,210.00 |
| 20 | Nitrogen fert nutr (25000400) | LB | 23 | $3.30 | $3.00 |
| 21 | Phosphorus fert nutr (25000500) | LB | 23 | $3.30 | $3.00 |
| 22 | Potassium fert nutr (25000600) | LB | 23 | $3.30 | $3.00 |
| 23 | Erosion contr blanket (25100630) | SY | 907 | $3.85 | $3.50 |
| 24 | Temp eros contr seed (28000250) | LB | 57 | $11.00 | $10.00 |
| 25 | Perimeter eros bar (28000400) | LF | 1,653 | $3.30 | $3.00 |
| 26 | Inlet & pipe protect (28000500) | EACH | 1 | $220.00 | $200.00 |
| 27 | Stone riprap CL A4 (28100107) | SY | 463 | $90.00 | $77.00 |
| 28 | Filter fabric (28200200) | SY | 463 | $5.00 | $4.00 |
| 29 | Agg surf course TY B (40200800) | TON | 27 | $60.00 | $55.00 |
| 30 | Bit matls tack CT (40600290) | LB | 4,012 | $0.01 | $0.01 |
| 31 | Long joint sealant (40600370) | LF | 951 | $10.00 | $18.00 |
| 32 | Temporary ramp (40600990) | SY | 84 | $0.01 | $77.00 |
| 33 | P HMA BC IL19.0 N70 (40603235) | TON | 403 | $95.00 | $123.00 |
| 34 | P HMA SC 9.5FG D N70 (40604112) | TON | 334 | $100.00 | $132.00 |
| 35 | HMA surf rem 1 1/2 (44000155) | SY | 161 | $8.00 | $14.00 |
| 36 | HMA surf rem 3 3/4 (44000164) | SY | 2,688 | $4.50 | $7.00 |
| 37 | Paved SHLD removal (44004250) | SY | 36 | $25.00 | $13.00 |
| 38 | Aggregate SHLDS B 6 (48101500) | SY | 113 | $20.00 | $30.00 |
| 39 | Agg wedge SHLD type B (48102100) | TON | 56 | $50.00 | $77.00 |
| 40 | HMA shoulders 8 (48203029) | SY | 492 | $45.00 | $53.00 |
| 41 | Conc rem (50102400) | CY | 123.30 | $823.00 | $1,500.00 |
| 42 | Slope wall remov (50104650) | SY | 444 | $90.00 | $41.00 |
| 43 | Floor drains (50300100) | EACH | 18 | $600.00 | $1,100.00 |
| 44 | Conc sup-STR (50300255) | CY | 138.90 | $1,400.00 | $2,160.00 |
| 45 | Protective coat (50300300) | SY | 185 | $1.00 | $3.00 |
| 46 | F & E P P con I-BM 42 (50400905) | LF | 320 | $640.75 | $786.00 |
| 47 | Reinf bars, epoxy CTD (50800205) | LB | 39,210 | $2.00 | $2.00 |
| 48 | Bar splicers (50800515) | EACH | 26 | $60.00 | $72.00 |
| 49 | Mechanical splicers (50800530) | EACH | 1,018 | $85.00 | $78.00 |
| 50 | Name plates (51500100) | EACH | 1 | $1,200.00 | $750.00 |
| 51 | Pref JT strip seal (52000110) | LF | 92 | $275.00 | $230.00 |
| 52 | Elast bearing assy T2 (52100020) | EACH | 12 | $2,600.00 | $2,625.00 |
| 53 | Anchor bolts 1 (52100520) | EACH | 24 | $100.00 | $230.00 |
| 54 | Deck slab rep (part) (53016000) | SY | 7 | $750.00 | $1,330.00 |
| 55 | Deck slab rep (FD-T1) (53016001) | SY | 50 | $1,200.00 | $1,350.00 |
| 56 | STR rep con DP = < 5 (53212754) | SF | 36 | $300.00 | $440.00 |
| 57 | FLS waterproof system (58100210) | SY | 738 | $80.00 | $58.00 |
| 58 | Epoxy crack injection (59000200) | LF | 80 | $70.00 | $65.00 |
| 59 | SPBGR TY A 6FT posts (63000001) | LF | 250 | $43.02 | $40.00 |
| 60 | Traf bar term T6 (63100085) | EACH | 4 | $5,352.60 | $4,866.00 |
| 61 | TR bar TRM T1 SPL tan (63100167) | EACH | 4 | $4,760.80 | $4,328.00 |
| 62 | Guardrail remov (63200310) | LF | 610 | $8.16 | $7.50 |
| 63 | Delineators (63500105) | EACH | 4 | $60.28 | $55.00 |
| 64 | Engr field office A (67000400) | CAL MO | 6 | $5,000.00 | $2,500.00 |
| 65 | Mobilization (67100100) | LS | 1 | $95,750 | $65,000 |
| 66 | Traf cont-prot 701321 (70100405) | EACH | 1 | $20,000 | $34,000 |
| 67 | Traf cont-prot 701201 (70100450) | LS | 1 | $0.01 | $1,000.00 |
| 68 | Traf cont-prot 701306 (70100460) | LS | 1 | $0.01 | $5,000.00 |
| 69 | Traf cont-prot 701326 (70100500) | LS | 1 | $0.01 | $1,000.00 |
| 70 | TR cont surveillance (70103815) | CAL DAY | 5 | $500.00 | $1,000.00 |
| 71 | Temp BR traf signals (70106500) | EACH | 1 | $35,000 | $14,500 |
| 72 | Temp rumble strips (70106700) | EACH | 6 | $1,200.00 | $1,800.00 |
| 73 | Short term pavt mking (70300100) | LF | 816 | $1.50 | $1.50 |
| 74 | SHRT TRM pavt MK rem (70300150) | SF | 2,264 | $1.50 | $1.50 |
| 75 | Temp PVT MK L4 T4 tape (70307120) | LF | 5,686 | $1.80 | $1.50 |
| 76 | Temp PVT MK L24 T4 tape (70307210) | LF | 48 | $10.00 | $8.25 |
| 77 | Temp conc barrier (70400100) | LF | 450 | $25.00 | $37.00 |
| 78 | Rel temp conc barrier (70400200) | LF | 387.50 | $15.00 | $24.00 |
| 79 | Imp attn temp NRN TL3 (70600251) | EACH | 2 | $7,000.00 | $3,340.00 |
| 80 | Imp attn rel NRN TL3 (70600352) | EACH | 2 | $2,000.00 | $1,720.00 |
| 81 | Terminal marker - DA (72501000) | EACH | 4 | $38.50 | $35.00 |
| 82 | Mod ureth PM line 4 (78009004) | LF | 3,804 | $1.98 | $1.80 |
| 83 | Mod ureth PM line 6 (78009006) | LF | 480 | $7.04 | $6.40 |
| 84 | Raised refl pavt MKR (78100100) | EACH | 12 | $495.00 | $450.00 |
| 85 | Grdrail ref type A (78200005) | EACH | 16 | $11.00 | $10.00 |
| 86 | Barr wall ref type C (78200011) | EACH | 12 | $25.00 | $15.00 |
| 87 | Raised ref PVT MK rem (78300200) | EACH | 12 | $10.00 | $72.00 |
| 88 | PVT MKG rem WTR blast (78300202) | SF | 754 | $4.40 | $6.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.