IDOT contract 68J18 bid tabulation
Section 45RS-8;(46-1)RS-10. Let by Illinois DOT on April 25, 2025, Peoria, District 04. 2 bids received; low bid $9,772,668 by Advanced Asphalt Company.
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 75
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Advanced Asphalt Company | $9,772,668 | Low |
| 2 | R. A. Cullinan and Son, a div of UCM, Inc. | $9,969,644 | +2.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Advanced Asphalt Company | 2. R. A. Cullinan and Son, a div of UCM, Inc. |
|---|---|---|---|---|---|
| 1 | Constr sta layout (XZ013798) | LS | 1 | $5,000.00 | $5,753.71 |
| 2 | CCTV dome camera HD (X0320023) | EACH | 1 | $7,350.00 | $7,350.00 |
| 3 | HMA surf rem SPL (X4400196) | SY | 4,224 | $12.00 | $0.01 |
| 4 | SHLDR rem SPL (X4404262) | SY | 45 | $35.00 | $63.52 |
| 5 | Delineator removal (X6350120) | EACH | 29 | $20.00 | $60.85 |
| 6 | Linear delin panels 4 (X6350204) | EACH | 167 | $75.00 | $62.50 |
| 7 | Rem imp atten no salv (X6430120) | EACH | 12 | $800.00 | $1,500.00 |
| 8 | GDRL agg eros cont (Z0001002) | TON | 706 | $70.00 | $120.09 |
| 9 | Conc curb repair (Z0012500) | LF | 705 | $50.00 | $150.23 |
| 10 | Erosion cont curb rem (Z0020805) | LF | 350 | $10.00 | $4.26 |
| 11 | Trainees (Z0076600) | HR | 2,000 | $0.80 | $0.80 |
| 12 | Trainees TPG (Z0076604) | HR | 2,000 | $15.00 | $15.00 |
| 13 | Mowing (25000750) | ACRE | 57 | $95.00 | $95.00 |
| 14 | Stone riprap CL B3 (28100225) | TON | 756 | $80.00 | $83.57 |
| 15 | Agg surf cse A (40200100) | TON | 13 | $100.00 | $244.43 |
| 16 | P bit matls tack CT (40600295) | LB | 388,725 | $0.71 | $0.91 |
| 17 | Matl transfer device (40600405) | TON | 43,871 | $2.00 | $2.48 |
| 18 | HMA surf rem butt JT (40600982) | SY | 6,590 | $8.00 | $8.26 |
| 19 | Temporary ramp (40600990) | SY | 1,582 | $15.00 | $0.01 |
| 20 | P HMA BC IL-4.75 N50 (40603200) | TON | 10,089 | $115.00 | $122.02 |
| 21 | P HMA SC IL-9.5 D N70 (40604162) | TON | 17,608 | $100.00 | $107.45 |
| 22 | Incidental HMA surf (40800050) | TON | 1,276 | $135.00 | $182.07 |
| 23 | HMA surf rem 2 1/2 (44000159) | SY | 276,276 | $1.75 | $2.74 |
| 24 | Median removal (44003100) | SF | 6,784 | $5.00 | $6.12 |
| 25 | Welded wire reinf (44200050) | SY | 1,259 | $15.00 | $15.00 |
| 26 | CL B patch T2 14 (44201019) | SY | 4,239 | $280.00 | $280.00 |
| 27 | CL B patch T3 14 (44201023) | SY | 516 | $275.00 | $275.00 |
| 28 | CL B patch T4 14 (44201025) | SY | 744 | $275.00 | $275.00 |
| 29 | Dowel bars 1 1/2 (44201299) | EACH | 10,902 | $15.00 | $15.00 |
| 30 | Saw cuts (44213200) | LF | 27,869 | $0.01 | $0.01 |
| 31 | Tie bars 3/4 (44213204) | EACH | 117 | $7.50 | $7.50 |
| 32 | HMA shoulders (48203100) | TON | 16,174 | $95.00 | $102.40 |
| 33 | Inlets adjust (60260100) | EACH | 1 | $1,200.00 | $1,508.76 |
| 34 | Conc med TSB6.06 (60619200) | SF | 6,784 | $22.00 | $19.98 |
| 35 | SPBGR TY A 6FT posts (63000001) | LF | 275 | $33.50 | $33.50 |
| 36 | SPBGR TY A 9FT posts (63000003) | LF | 1,500 | $38.75 | $36.75 |
| 37 | SPBGR TY D 6FT posts (63000017) | LF | 5,319 | $44.00 | $38.25 |
| 38 | Traf bar term T2 (63100045) | EACH | 3 | $3,250.00 | $2,150.00 |
| 39 | TR bar TRM T1 SPL tan (63100167) | EACH | 6 | $3,450.00 | $3,275.00 |
| 40 | Guardrail remov (63200310) | LF | 7,414 | $4.00 | $6.75 |
| 41 | Shoulder rum strip 16 (64200116) | LF | 95,939 | $0.25 | $0.34 |
| 42 | Imp atten FRD nar TL3 (64300260) | EACH | 12 | $28,000 | $23,850 |
| 43 | Engr field office A (67000400) | CAL MO | 12 | $2,000.00 | $3,125.42 |
| 44 | Mobilization (67100100) | LS | 1 | $585,000 | $235,415 |
| 45 | Traf cont-prot 701201 (70100450) | LS | 1 | $8,000.00 | $8,000.00 |
| 46 | Traf cont-prot 701406 (70100700) | LS | 1 | $1,000.00 | $1,000.00 |
| 47 | Traf cont-prot 701401 (70100800) | LS | 1 | $220,000 | $79,800 |
| 48 | TR cont surveillance (70103815) | CAL DAY | 10 | $0.01 | $1,410.00 |
| 49 | Changeable message SN (70107025) | CAL DAY | 14 | $125.00 | $100.00 |
| 50 | Short term pavt mking (70300100) | LF | 25,380 | $1.00 | $0.01 |
| 51 | SHRT TRM pavt MK rem (70300150) | SF | 2,820 | $0.90 | $3.82 |
| 52 | Temp PVT MK LTR & sym paint (70300211) | SF | 687 | $0.01 | $0.01 |
| 53 | Temp PVT MK line 4 - paint (70300221) | LF | 2,026 | $0.01 | $0.01 |
| 54 | Temp PVT MK line 6 - paint (70300241) | LF | 134,640 | $0.01 | $0.01 |
| 55 | Temp PVT MK line 8 - paint (70300251) | LF | 13,071 | $0.01 | $0.01 |
| 56 | Temp PVT MK line 12 - paint (70300261) | LF | 1,469 | $0.01 | $0.01 |
| 57 | Temp PVT MK line 24 - paint (70300281) | LF | 287 | $0.01 | $0.01 |
| 58 | Terminal marker - DA (72501000) | EACH | 6 | $50.00 | $42.00 |
| 59 | Mod ureth PM LTR-sym (78009000) | SF | 687 | $9.00 | $4.80 |
| 60 | Mod ureth PM line 4 (78009004) | LF | 2,026 | $1.00 | $0.82 |
| 61 | Mod ureth PM line 6 (78009006) | LF | 134,640 | $1.20 | $0.83 |
| 62 | Mod ureth PM line 8 (78009008) | LF | 13,071 | $2.50 | $1.60 |
| 63 | Mod ureth PM line 12 (78009012) | LF | 1,469 | $5.00 | $4.80 |
| 64 | Mod ureth PM line 24 (78009024) | LF | 287 | $12.00 | $9.60 |
| 65 | GRV RCSD PM LTR & sym (78011000) | SF | 687 | $5.00 | $4.00 |
| 66 | GRV RCSD PVT MRKG 5 (78011025) | LF | 2,026 | $0.36 | $0.64 |
| 67 | GRV RCSD PVT MRKG 7 (78011035) | LF | 134,640 | $0.50 | $0.65 |
| 68 | GRV RCSD PVT MRKG 9 (78011045) | LF | 13,071 | $0.85 | $1.35 |
| 69 | GRV RCSD PVT MRKG 13 (78011065) | LF | 1,469 | $2.50 | $4.00 |
| 70 | GRV RCSD PVT MRKG 25 (78011125) | LF | 287 | $5.00 | $8.00 |
| 71 | Raised refl pavt MKR (78100100) | EACH | 1,030 | $59.00 | $33.67 |
| 72 | Curb reflectors (78200020) | EACH | 84 | $8.50 | $5.00 |
| 73 | Raised ref PVT MK rem (78300200) | EACH | 1,030 | $7.94 | $11.75 |
| 74 | Cont cab type IV (86300400) | EACH | 1 | $25,665 | $25,665 |
| 75 | Det loop T1 (88600100) | LF | 1,224 | $46.00 | $46.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.