IDOT contract 68K16 bid tabulation
Section 130RS-8. Let by Illinois DOT on February 27, 2026, Peoria, District 04. 2 bids received; low bid $3,332,964 by R. A. Cullinan and Son, a div of UCM, Inc..
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 56
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | R. A. Cullinan and Son, a div of UCM, Inc. | $3,332,964 | Low |
| 2 | Advanced Asphalt Company | $3,364,295 | +1.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R. A. Cullinan and Son, a div of UCM, Inc. | 2. Advanced Asphalt Company |
|---|---|---|---|---|---|
| 1 | Constr sta layout (XZ013798) | LS | 1 | $2,267.09 | $5,500.00 |
| 2 | HMA surf rem SPL (X4400196) | SY | 2,832 | $0.01 | $18.00 |
| 3 | Conc med TSM4.06 (X6065701) | SF | 459 | $39.00 | $18.00 |
| 4 | Rumble strip (Z0055600) | SY | 67 | $117.39 | $190.00 |
| 5 | Trainees (Z0076600) | HR | 2,000 | $0.80 | $0.80 |
| 6 | Trainees TPG (Z0076604) | HR | 2,000 | $15.00 | $15.00 |
| 7 | Exc & GR EX shoulder (20200600) | UNIT | 328 | $132.31 | $150.00 |
| 8 | Mowing (25000750) | ACRE | 17.25 | $100.00 | $100.00 |
| 9 | P bit matls tack CT (40600295) | LB | 117,495 | $1.02 | $0.78 |
| 10 | Matl transfer device (40600405) | TON | 17,079 | $2.13 | $2.50 |
| 11 | HMA surf rem butt JT (40600982) | SY | 1,507 | $15.22 | $14.00 |
| 12 | Temporary ramp (40600990) | SY | 254 | $41.78 | $28.00 |
| 13 | HMA BC IL-9.5 N50 (40602978) | TON | 1,716 | $111.26 | $105.00 |
| 14 | HMA BC IL-19.0 N50 (40603080) | TON | 2,604 | $111.01 | $98.00 |
| 15 | P HMA BC IL-9.5 N50 (40603205) | TON | 6,106 | $113.52 | $107.00 |
| 16 | HMA SC IL-9.5 D N50 (40604060) | TON | 2,156 | $116.25 | $105.00 |
| 17 | P HMA SC IL-9.5 D N50 (40604160) | TON | 7,101 | $116.25 | $107.00 |
| 18 | Incidental HMA surf (40800050) | TON | 146 | $308.71 | $200.00 |
| 19 | HMA surf rem 1 1/2 (44000155) | SY | 68,093 | $2.65 | $1.76 |
| 20 | HMA surf rem 5 3/4 (44000172) | SY | 5,440 | $7.98 | $7.50 |
| 21 | Comb curb gutter rem (44000500) | LF | 1,236 | $19.50 | $17.00 |
| 22 | Median removal (44003100) | SF | 459 | $10.00 | $5.00 |
| 23 | Welded wire reinf (44200050) | SY | 119 | $13.00 | $0.01 |
| 24 | CL B patch T2 8 (44200934) | SY | 70 | $270.00 | $600.00 |
| 25 | CL B patch T3 8 (44200942) | SY | 45 | $260.00 | $600.00 |
| 26 | CL B patch T4 8 (44200944) | SY | 75 | $250.00 | $600.00 |
| 27 | Dowel bars 1 1/4 (44201298) | EACH | 304 | $39.00 | $0.01 |
| 28 | Saw cuts (44213200) | LF | 720 | $8.00 | $0.01 |
| 29 | Aggregate SHLDS B (48101200) | TON | 2,178 | $36.50 | $43.00 |
| 30 | Comb CC&G TM4.06 (60608552) | LF | 1,236 | $60.00 | $45.00 |
| 31 | Pipe culv cleaned 24 (60920024) | LF | 134 | $39.55 | $100.00 |
| 32 | Shoulder rum strip 8 (64200108) | LF | 39,044 | $0.19 | $0.32 |
| 33 | Sinusoidal rum STP 14 (64200214) | LF | 12,895 | $0.59 | $0.90 |
| 34 | Engr field office A (67000400) | CAL MO | 3 | $0.01 | $2,550.00 |
| 35 | Mobilization (67100100) | LS | 1 | $53,625 | $211,500 |
| 36 | Traf cont-prot 701306 (70100460) | LS | 1 | $17,200 | $50,464 |
| 37 | Traf cont-prot 701326 (70100500) | LS | 1 | $0.01 | $4,750.00 |
| 38 | Traf cont-prot 701336 (70100600) | LS | 1 | $0.02 | $13,100 |
| 39 | Changeable message SN (70107025) | CAL DAY | 28 | $150.00 | $150.00 |
| 40 | Short term pavt mking (70300100) | LF | 6,183 | $2.14 | $1.46 |
| 41 | SHRT TRM pavt MK rem (70300150) | SF | 2,061 | $2.46 | $2.03 |
| 42 | Mod ureth PM LTR-sym (78009000) | SF | 125 | $4.75 | $6.00 |
| 43 | Mod ureth PM line 4 (78009004) | LF | 31,505 | $0.89 | $0.75 |
| 44 | Mod ureth PM line 6 (78009006) | LF | 39,263 | $1.30 | $1.00 |
| 45 | Mod ureth PM line 8 (78009008) | LF | 1,210 | $1.75 | $1.35 |
| 46 | Mod ureth PM line 12 (78009012) | LF | 1,899 | $2.60 | $3.00 |
| 47 | Mod ureth PM line 24 (78009024) | LF | 85 | $5.50 | $6.00 |
| 48 | GRV RCSD PM LTR & sym (78011000) | SF | 175 | $4.50 | $3.00 |
| 49 | GRV RCSD PVT MRKG 5 (78011025) | LF | 31,505 | $0.39 | $0.40 |
| 50 | GRV RCSD PVT MRKG 7 (78011035) | LF | 39,263 | $0.59 | $0.45 |
| 51 | GRV RCSD PVT MRKG 9 (78011045) | LF | 1,210 | $0.80 | $0.75 |
| 52 | GRV RCSD PVT MRKG 13 (78011065) | LF | 1,899 | $2.28 | $2.00 |
| 53 | GRV RCSD PVT MRKG 25 (78011125) | LF | 85 | $5.00 | $3.00 |
| 54 | Raised refl pavt MKR (78100100) | EACH | 461 | $39.00 | $55.00 |
| 55 | Curb reflectors (78200020) | EACH | 45 | $18.00 | $25.00 |
| 56 | Raised ref PVT MK rem (78300200) | EACH | 456 | $16.98 | $31.40 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.