IDOT contract 70G85 bid tabulation
Section D5. Let by Illinois DOT on January 17, 2025, Mclean, District 05. 3 bids received; low bid $2,995,164 by Bodine Electric of Decatur.
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 43
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Bodine Electric of Decatur | $2,995,164 | Low |
| 2 | John Burns Construction Company | $3,144,875 | +5.0% |
| 3 | Champaign Signal and Lighting Co. A Division of Champaign Asphalt Company LLC | $3,407,913 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bodine Electric of Decatur | 2. John Burns Construction Company | 3. Champaign Signal and Lighting Co. A Division of Champaign Asphalt Company LLC |
|---|---|---|---|---|---|---|
| 1 | Pole MT equip cab TB (X0323920) | EACH | 5 | $9,434.05 | $17,500 | $10,000 |
| 2 | Support equip & maint (X0323923) | LS | 1 | $15,828 | $13,210 | $30,000 |
| 3 | TR MTD LED dyn MSG SN (X0325485) | EACH | 5 | $112,919 | $178,425 | $150,000 |
| 4 | CCTV dome cam IP base (X0326905) | EACH | 5 | $8,517.18 | $17,302 | $10,000 |
| 5 | DMS removal - IDOT (X1400459) | EACH | 5 | $9,289.28 | $9,161.00 | $50,000 |
| 6 | Rem imp atten no salv (X6430120) | EACH | 6 | $6,997.12 | $8,502.00 | $5,000.00 |
| 7 | Conduit splice (X8100105) | EACH | 1 | $2,931.55 | $1,216.00 | $500.00 |
| 8 | Wood pole 35 CL 4 (X8302135) | EACH | 5 | $2,774.72 | $7,204.00 | $5,000.00 |
| 9 | Fib opt CBL 12F SM (X8710036) | LF | 4,120 | $23.22 | $12.00 | $18.00 |
| 10 | Fib opt fusion splice (X8710071) | EACH | 10 | $2,171.52 | $1,478.00 | $2,000.00 |
| 11 | Ethernet switch (X8710103) | EACH | 5 | $2,485.18 | $3,467.00 | $4,000.00 |
| 12 | Construction layout (Z0013798) | LS | 1 | $12,064 | $15,000 | $30,000 |
| 13 | Furnished excavation (20400800) | CY | 75 | $603.20 | $625.00 | $400.00 |
| 14 | Seeding CL 2A (25000210) | ACRE | 0.50 | $16,166 | $5,000.00 | $15,000 |
| 15 | Nitrogen fert nutr (25000400) | LB | 47 | $84.45 | $5.00 | $250.00 |
| 16 | Phosphorus fert nutr (25000500) | LB | 47 | $84.45 | $5.00 | $250.00 |
| 17 | Potassium fert nutr (25000600) | LB | 47 | $84.45 | $5.00 | $250.00 |
| 18 | Mulch method 2 (25100115) | ACRE | 0.50 | $18,579 | $5,000.00 | $15,000 |
| 19 | SPBGR TY A 6FT posts (63000001) | LF | 2,325 | $38.60 | $30.00 | $40.00 |
| 20 | Traf bar term T2 (63100045) | EACH | 13 | $2,050.88 | $1,600.00 | $2,500.00 |
| 21 | TR bar TRM T1 SPL tan (63100167) | EACH | 13 | $4,463.68 | $3,620.00 | $5,000.00 |
| 22 | Guardrail remov (63200310) | LF | 697 | $9.65 | $6.00 | $10.00 |
| 23 | Mobilization (67100100) | LS | 1 | $115,573 | $188,000 | $200,000 |
| 24 | Traf cont-prot 701411 (70100420) | EACH | 2 | $9,687.39 | $1.00 | $50,000 |
| 25 | Traf cont-prot 701401 (70100800) | LS | 1 | $272,936 | $90,000 | $200,000 |
| 26 | Changeable message SN (70107025) | CAL DAY | 35 | $1,737.22 | $50.00 | $500.00 |
| 27 | Night work zone light (70200100) | LS | 1 | $12,305 | $11,000 | $5,000.00 |
| 28 | Terminal marker - DA (72501000) | EACH | 13 | $60.32 | $50.00 | $100.00 |
| 29 | Ovhd sin STR-span T3A (73300300) | LF | 313 | $2,066.56 | $1,874.00 | $1,800.00 |
| 30 | Oss walkway TY A (73301810) | LF | 100 | $784.16 | $504.00 | $1,000.00 |
| 31 | Drill shaft conc FDN (73400200) | CY | 110.30 | $2,433.31 | $2,615.00 | $2,250.00 |
| 32 | Remov OH sin STR-span (73600100) | EACH | 5 | $18,096 | $6,921.00 | $18,000 |
| 33 | Rem conc FDN-ovhd (73700300) | EACH | 20 | $2,955.68 | $2,815.00 | $3,500.00 |
| 34 | Grdrail ref type A (78200005) | EACH | 49 | $18.10 | $10.00 | $20.00 |
| 35 | Serv install TY A (80500100) | EACH | 5 | $8,034.62 | $14,544 | $12,500 |
| 36 | Undrgrd C PVC 2 (81028350) | LF | 1,734 | $36.19 | $95.00 | $30.00 |
| 37 | Con at ST 2 galvs (81100600) | LF | 90 | $91.08 | $125.00 | $130.00 |
| 38 | Handhole (81400100) | EACH | 2 | $5,018.62 | $11,857 | $6,000.00 |
| 39 | Remov elect serv inst (84500120) | EACH | 5 | $1,857.86 | $8,502.00 | $5,000.00 |
| 40 | Elcbl C tracer 12 1C (87300901) | LF | 394 | $3.26 | $0.50 | $5.00 |
| 41 | Elcbl C serv 6 3C (87301815) | LF | 1,451 | $36.19 | $7.00 | $8.00 |
| 42 | Elcbl C egrdc 6 1C (87301900) | LF | 1,476 | $5.55 | $1.50 | $5.00 |
| 43 | Drill EX handhole (87900200) | EACH | 4 | $965.12 | $1,216.00 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.