Bodine Electric of Decatur submitted 64 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 12 JUN 2026, and was the low bidder on 30 of them (47%). When it was not low, its total sat a median +26% above the low bid.
- Owner
- Illinois DOT
- Low bid volume
- $19,689,380
- Latest bid
- 12 JUN 2026
- Data through
- 18 SEP 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2021 | 20 | 6 | 30% |
| 2022 | 12 | 8 | 67% |
| 2023 | 10 | 4 | 40% |
| 2024 | 10 | 5 | 50% |
| 2025 | 8 | 5 | 63% |
| 2026 | 4 | 2 | 50% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 06 | 21 | 8 | 38% |
| District 07 | 15 | 13 | 87% |
| District 05 | 12 | 6 | 50% |
| District 04 | 9 | 2 | 22% |
| District 03 | 3 | 0 | 0% |
| District 08 | 3 | 0 | 0% |
| District 09 | 1 | 1 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Elect serv install | 80400100 | EACH | 16 | 12 (75%) | $4,433.52 | $4,720.33 |
| Bkwy dev cou SS SCRN | 83800650 | EACH | 14 | 8 (57%) | $166.45 | $225.56 |
| Journey electrician | XP000001 | HR | 9 | 7 (78%) | $135.00 | $137.00 |
| Luminaire MT BRKT SPL | X8210402 | EACH | 13 | 5 (38%) | $431.18 | $410.00 |
| Remov elect serv inst | 84500120 | EACH | 12 | 5 (42%) | $1,467.69 | $936.00 |
| Ethernet switch | X0326266 | EACH | 8 | 5 (63%) | $1,906.49 | $2,101.38 |
| LT P A 45MH 15DA | 83003600 | EACH | 7 | 5 (71%) | $6,082.73 | $6,604.50 |
| Traf cont-prot 701411 | 70100420 | EACH | 5 | 5 (100%) | $3,173.39 | $750.00 |
| Lum LED rdwy G | 82110007 | EACH | 17 | 4 (24%) | $850.00 | $907.50 |
| Drill EX handhole | 87900200 | EACH | 15 | 4 (27%) | $871.01 | $465.00 |
| LT P GS 45MH ten MT | 83060830 | EACH | 14 | 4 (29%) | $5,710.90 | $5,347.98 |
| Undrgrd C PVC 2 | 81028350 | LF | 11 | 4 (36%) | $22.26 | $27.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Capitol Construction Group, LLC d/b/a Egizii Electric | 21 | 14 of 21 |
| Laser Electric, Inc. | 12 | 7 of 12 |
| Gerstner Electric, Inc. | 11 | 5 of 11 |
| Champaign Signal and Lighting Co. A Division of Champaign Asphalt Company LLC | 11 | 4 of 11 |
| Oberlander Electric Co. | 10 | 5 of 10 |
| H & H Electric Co. | 3 | 2 of 3 |
| John Burns Construction Company | 3 | 0 of 3 |
| William Charles Construction Co, LLC (d/b/a) William Charles Electric | 3 | 1 of 3 |
| Wissehr Electric, Inc. | 2 | 2 of 2 |
| Electric Conduit Construction | 2 | 1 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 12 JUN 2026 | 72509 | District 06 | Section (54-1,2)HL-1 | 1 of 2 | $569,259 | Low, 7.0% under the second |
| 24 APR 2026 | 72F52 | District 06 | Section D6 | 2 of 2 | $344,690 | +26% |
| 24 APR 2026 | 74E31 | District 07 | Section D7 | 1 of 1 | $596,150 | Low |
| 16 JAN 2026 | 74D37 | District 07 | Section D7 | 2 of 3 | $455,027 | +37% |
| 19 SEP 2025 | 70H51 | District 05 | Section HMLT2025-1 | 2 of 5 | $909,013 | +5.0% |
| 19 SEP 2025 | 72977 | District 06 | Section (54-1,2)HL | 1 of 2 | $397,966 | Low, 4.0% under the second |
| 13 JUN 2025 | 70H65 | District 05 | Section D5 | 2 of 2 | $424,166 | +20% |
| 13 JUN 2025 | 74C97 | District 07 | Section (58-62)HL | 1 of 2 | $2,670,320 | Low, 36% under the second |
| 25 APR 2025 | 74D44 | District 07 | Section D7 | 1 of 1 | $508,030 | Low |
| 07 MAR 2025 | 72602 | District 06 | Section D6 | 2 of 2 | $565,752 | +6.0% |
| 07 MAR 2025 | 72603 | District 06 | Section D6 | 1 of 1 | $292,133 | Low |
| 17 JAN 2025 | 70G85 | District 05 | Section D5 | 1 of 3 | $2,995,164 | Low, 5.0% under the second |
| 08 NOV 2024 | 74D00 | District 07 | Section D7 | 1 of 2 | $350,973 | Low, 24% under the second |
| 14 JUN 2024 | 70G90 | District 05 | Section (23)N | 1 of 2 | $489,967 | Low, 2.0% under the second |
| 14 JUN 2024 | 72733 | District 06 | Section D6 | 2 of 2 | $728,751 | +13% |
| 14 JUN 2024 | 72734 | District 06 | Section D6 | 2 of 2 | $1,623,418 | +37% |
| 26 APR 2024 | 72735 | District 06 | Section D6 | 2 of 2 | $435,750 | +44% |
| 26 APR 2024 | 72E35 | District 06 | Section D6 | 1 of 1 | $394,130 | Low |
| 26 APR 2024 | 72E36 | District 06 | Section D6 | 2 of 2 | $617,900 | +21% |
| 26 APR 2024 | 74C82 | District 07 | Section D7 | 1 of 2 | $544,837 | Low, 23% under the second |
| 26 APR 2024 | 74C88 | District 07 | Section D7 | 1 of 1 | $467,940 | Low |
| 26 APR 2024 | 76M86 | District 08 | Section 82-3, | 4 of 4 | $19,870,226 | +124% |
| 22 SEP 2023 | 70G26 | District 05 | Section HSIP | 3 of 3 | $2,507,991 | +84% |
| 04 AUG 2023 | 76P67 | District 08 | Section 82-8SG-1, | 2 of 2 | $5,207,039 | +54% |
| 04 AUG 2023 | 76R27 | District 08 | Section 60-(1,2)HL-1 | 2 of 2 | $928,466 | +61% |
How this record was read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.