IDOT contract 70H45 bid tabulation
Section (57-8,57-22,57-23)BR-1. Let by Illinois DOT on March 7, 2025, Mclean, District 05. 1 bid received; low bid $958,366 by Stark Excavating, Inc..
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 19
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stark Excavating, Inc. | $958,366 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stark Excavating, Inc. |
|---|---|---|---|---|
| 1 | Rem EX protec shield (X5017311) | SY | 53 | $35.00 |
| 2 | HMA surface RM (deck) (Z0004556) | SY | 1,351.30 | $5.15 |
| 3 | BRD flyash/slag 2 3/4 (Z0012112) | SY | 1,351.30 | $138.00 |
| 4 | BR deck scar 3/4 (Z0012130) | SY | 1,351.30 | $55.00 |
| 5 | Construction layout (Z0013798) | LS | 1 | $5,575.00 |
| 6 | Deck slab rep (FD-T1) (Z0016001) | SY | 4 | $3,825.00 |
| 7 | Deck slab rep (FD-T2) (Z0016002) | SY | 273.30 | $1,290.00 |
| 8 | Conc rem (50102400) | CY | 5.40 | $3,875.00 |
| 9 | Protective shield (50157300) | SY | 1,365 | $78.00 |
| 10 | Floor drains (50300100) | EACH | 8 | $825.00 |
| 11 | Conc sup-STR (50300255) | CY | 5.40 | $3,250.00 |
| 12 | BR deck grooving (50300260) | SY | 1,232 | $9.00 |
| 13 | Protective coat (50300300) | SY | 1,392.40 | $3.85 |
| 14 | Engr field office B (67000500) | CAL MO | 3 | $1,550.00 |
| 15 | Mobilization (67100100) | LS | 1 | $57,475 |
| 16 | Traf cont-prot 701411 (70100420) | EACH | 6 | $500.00 |
| 17 | Traf cont-prot 701406 (70100700) | LS | 1 | $76,000 |
| 18 | Traf cont-prot 701401 (70100800) | LS | 1 | $0.01 |
| 19 | Changeable message SN (70107025) | CAL DAY | 40 | $155.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way