IDOT contract 72220 bid tabulation
Section (54-4HB)D. Let by Illinois DOT on April 25, 2025, Logan, District 06. 3 bids received; low bid $4,994,242 by Sangamo Construction Company.
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 103
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Sangamo Construction Company | $4,994,242 | Low |
| 2 | William Charles Construction Company, LLC | $5,453,298 | +9.0% |
| 3 | Freesen, a div of UCM, Inc. | $7,040,990 | +41% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sangamo Construction Company | 2. William Charles Construction Company, LLC | 3. Freesen, a div of UCM, Inc. |
|---|---|---|---|---|---|---|
| 1 | Maintenance mowing (X2503000) | ACRE | 5.20 | $613.44 | $580.00 | $609.00 |
| 2 | CL C patch T2 13 SPL (X4421389) | SY | 100 | $396.62 | $385.00 | $519.75 |
| 3 | CL C patch T3 13 SPL (X4421394) | SY | 100 | $386.05 | $360.00 | $519.75 |
| 4 | Rem conc end sec (X5010523) | EACH | 3 | $553.25 | $650.00 | $1,340.63 |
| 5 | BR deck grooving long (X5030250) | SY | 1,065 | $10.65 | $12.50 | $11.72 |
| 6 | Bar terminators (X5080530) | EACH | 183 | $28.50 | $32.75 | $25.17 |
| 7 | HLMRB disc fixed 200K (X5211410) | EACH | 6 | $4,305.48 | $5,700.00 | $4,777.76 |
| 8 | HLMRB disc G exp 200K (X5211610) | EACH | 14 | $5,216.21 | $6,600.00 | $5,782.27 |
| 9 | Pipe drain removal (X6010003) | LF | 226 | $20.67 | $49.00 | $87.26 |
| 10 | TC-prot 701402 SPL (X7010208) | EACH | 1 | $214,116 | $59,650 | $126,666 |
| 11 | Width restrict sign (X7200201) | LS | 1 | $4,759.46 | $5,875.00 | $10,151 |
| 12 | Jack & rem EX bearing (Z0001899) | EACH | 20 | $2,804.62 | $4,800.00 | $3,403.66 |
| 13 | Struct steel repair (Z0001905) | LB | 12,090 | $9.59 | $15.00 | $14.64 |
| 14 | Rem EX conc I-beam (Z0003615) | EACH | 8 | $948.82 | $3,500.00 | $2,513.03 |
| 15 | Approach slab rem (Z0004552) | SY | 303 | $66.05 | $135.00 | $139.09 |
| 16 | C&D lead PT CL RS N1 (Z0007101) | LS | 1 | $10,577 | $15,000 | $99,430 |
| 17 | C&D lead PT CL RS N2 (Z0007102) | LS | 1 | $8,461.26 | $10,000 | $42,613 |
| 18 | Clean & PT STL BR N1 (Z0010501) | LS | 1 | $41,249 | $60,000 | $9,998.10 |
| 19 | Clean & PT STL BR N2 (Z0010502) | LS | 1 | $30,672 | $50,000 | $5,784.45 |
| 20 | STR rep con DP = < 5 (Z0012754) | SF | 152 | $228.19 | $150.00 | $337.03 |
| 21 | Construction layout (Z0013798) | LS | 1 | $36,433 | $35,000 | $32,061 |
| 22 | Detour signing (Z0016702) | LS | 1 | $36,399 | $10,980 | $13,482 |
| 23 | Diamond grind BR sec (Z0029090) | SY | 1,769 | $14.14 | $22.50 | $21.17 |
| 24 | Jack exist sup-STR (Z0032300) | LS | 1 | $8,203.68 | $1.00 | $49,357 |
| 25 | Slope wall repair (Z0065700) | SY | 15.30 | $388.47 | $1,200.00 | $2,593.80 |
| 26 | Slopewall slur pumpng (Z0065730) | CY | 3.40 | $478.09 | $2,200.00 | $5,220.70 |
| 27 | Trainees (Z0076600) | HR | 2,500 | $0.80 | $0.80 | $0.80 |
| 28 | Trainees TPG (Z0076604) | HR | 2,500 | $15.00 | $15.00 | $15.00 |
| 29 | Earth excavation (20200100) | CY | 50 | $157.79 | $95.00 | $214.60 |
| 30 | Grading & shap ditch (21400100) | LF | 400 | $7.53 | $18.50 | $58.77 |
| 31 | Seeding CL 2 (25000200) | ACRE | 0.25 | $6,620.92 | $6,260.00 | $6,573.00 |
| 32 | Nitrogen fert nutr (25000400) | LB | 24 | $10.58 | $10.00 | $10.50 |
| 33 | Phosphorus fert nutr (25000500) | LB | 24 | $10.58 | $10.00 | $10.50 |
| 34 | Potassium fert nutr (25000600) | LB | 24 | $10.58 | $10.00 | $10.50 |
| 35 | Agr ground limestone (25000700) | TON | 0.80 | $105.76 | $100.00 | $105.00 |
| 36 | Mulch method 2 (25100115) | ACRE | 0.25 | $6,620.92 | $6,260.00 | $6,573.00 |
| 37 | Temp eros contr seed (28000250) | LB | 40 | $4.15 | $8.00 | $7.23 |
| 38 | Agg base cse B 4 (35101600) | SY | 355 | $17.31 | $32.00 | $65.11 |
| 39 | Bit matls tack CT (40600290) | LB | 1,709 | $8.18 | $7.45 | $7.45 |
| 40 | LNG JNT SLNT half WD (40600372) | LF | 1,564 | $15.86 | $15.00 | $15.75 |
| 41 | Temporary ramp (40600990) | SY | 92 | $67.29 | $18.00 | $24.36 |
| 42 | P HMA SC IL-9.5 D N70 (40604162) | TON | 157 | $737.05 | $671.47 | $671.47 |
| 43 | Welded wire reinf (42000060) | SY | 242 | $18.09 | $40.00 | $94.03 |
| 44 | PVT con PCC BR app SL (42000080) | SY | 406 | $249.31 | $220.00 | $237.49 |
| 45 | Protective coat (42001300) | SY | 406 | $3.32 | $5.00 | $7.32 |
| 46 | Pavement rem (44000100) | SY | 242 | $62.69 | $70.00 | $114.31 |
| 47 | HMA surf rem 1 1/2 (44000155) | SY | 3,138 | $28.52 | $25.98 | $25.98 |
| 48 | Paved SHLD removal (44004250) | SY | 1,727 | $61.57 | $56.00 | $62.10 |
| 49 | Agg wedge SHLD type B (48102100) | TON | 130 | $93.85 | $120.00 | $182.58 |
| 50 | HMA shoulders 10 1/2 (48203039) | SY | 1,422 | $170.81 | $155.61 | $155.61 |
| 51 | HMA shoulders (48203100) | TON | 226 | $583.08 | $531.20 | $531.20 |
| 52 | PCC shoulders 10 (48300500) | SY | 28 | $337.63 | $210.00 | $354.96 |
| 53 | Conc rem (50102400) | CY | 78.40 | $1,222.29 | $2,100.00 | $1,129.22 |
| 54 | Rem EX conc deck N1 (50104701) | EACH | 1 | $134,022 | $170,000 | $254,535 |
| 55 | Rem EX conc deck N2 (50104702) | EACH | 1 | $232,310 | $122,000 | $234,667 |
| 56 | Protective shield (50157300) | SY | 587 | $1.00 | $100.00 | $174.01 |
| 57 | Structure excavation (50200100) | CY | 131 | $55.79 | $100.00 | $135.70 |
| 58 | Floor drains (50300100) | EACH | 6 | $558.83 | $785.00 | $889.02 |
| 59 | Conc struct (50300225) | CY | 56.40 | $1,017.19 | $1,800.00 | $1,905.18 |
| 60 | Conc sup-STR (50300255) | CY | 576.90 | $1,795.96 | $2,035.00 | $3,562.73 |
| 61 | Protective coat (50300300) | SY | 2,196 | $3.33 | $3.00 | $5.77 |
| 62 | Conc supstr app slab (50301350) | CY | 199.90 | $767.72 | $950.00 | $1,039.48 |
| 63 | F & E P P con I-BM 36 (50400805) | LF | 288 | $888.67 | $895.00 | $864.36 |
| 64 | Stud shear connectors (50500505) | EACH | 2,580 | $12.85 | $6.50 | $5.57 |
| 65 | Reinf bars, epoxy CTD (50800205) | LB | 230,480 | $1.55 | $1.75 | $1.75 |
| 66 | Bar splicers (50800515) | EACH | 953 | $47.46 | $55.00 | $60.32 |
| 67 | Name plates (51500100) | EACH | 2 | $731.10 | $1,200.00 | $1,168.78 |
| 68 | Pref JT strip seal (52000110) | LF | 172 | $315.10 | $370.00 | $497.29 |
| 69 | Anchor bolts 1 (52100520) | EACH | 80 | $178.17 | $175.00 | $203.64 |
| 70 | Temp SHT piling (52200010) | SF | 133 | $164.87 | $240.00 | $148.15 |
| 71 | End sections 12 (54213447) | EACH | 3 | $361.23 | $975.00 | $607.04 |
| 72 | Granular backfill STR (58600101) | CY | 109 | $88.95 | $125.00 | $318.08 |
| 73 | Concrete sealer (58700300) | SF | 700 | $2.52 | $4.00 | $9.24 |
| 74 | Pipe drains 12 (60100945) | LF | 252 | $35.52 | $71.00 | $79.11 |
| 75 | Remov inlets (60500060) | EACH | 3 | $759.15 | $825.00 | $1,340.63 |
| 76 | TY G inlet box 610001 (61000335) | EACH | 3 | $3,690.49 | $7,200.00 | $4,089.78 |
| 77 | SPBGR TY A 6FT posts (63000001) | LF | 2,675 | $31.89 | $33.00 | $31.66 |
| 78 | Traf bar term T2 (63100045) | EACH | 2 | $2,067.72 | $2,625.00 | $2,052.75 |
| 79 | Traf bar term T5 (63100070) | EACH | 2 | $1,581.20 | $1,200.00 | $1,569.75 |
| 80 | Traf bar term T6 (63100085) | EACH | 4 | $5,433.58 | $6,250.00 | $5,040.00 |
| 81 | TR bar TRM T1 SPL tan (63100167) | EACH | 4 | $4,019.10 | $3,650.00 | $3,990.00 |
| 82 | Guardrail remov (63200310) | LF | 3,147 | $5.79 | $6.45 | $10.08 |
| 83 | Shoulder rum strip 16 (64200116) | LF | 3,236 | $4.06 | $3.50 | $3.85 |
| 84 | Conc SHLD curb (66201120) | LF | 43 | $50.07 | $55.00 | $201.82 |
| 85 | Engr field office A (67000400) | CAL MO | 18 | $3,280.97 | $2,800.00 | $4,463.94 |
| 86 | Mobilization (67100100) | LS | 1 | $294,660 | $327,000 | $338,846 |
| 87 | Traf cont-prot 701401 (70100800) | LS | 1 | $30,720 | $45,500 | $157,869 |
| 88 | Traf cont-prot 701451 (70100820) | LS | 1 | $2,644.14 | $8,400.00 | $6,090.00 |
| 89 | Changeable message SN (70107025) | CAL DAY | 360 | $31.73 | $100.00 | $78.75 |
| 90 | Night work zone light (70200100) | LS | 1 | $6,558.53 | $35,242 | $80,351 |
| 91 | Short term pavt mking (70300100) | LF | 363 | $1.85 | $2.00 | $2.21 |
| 92 | SHRT TRM pavt MK rem (70300150) | SF | 152 | $3.01 | $3.00 | $4.67 |
| 93 | Temp conc barrier (70400100) | LF | 525 | $62.66 | $56.00 | $68.01 |
| 94 | Rel temp conc barrier (70400200) | LF | 525 | $9.04 | $9.00 | $6.23 |
| 95 | Imp attn temp FRN TL3 (70600260) | EACH | 1 | $8,800.26 | $11,100 | $12,730 |
| 96 | Imp attn rel FRN TL3 (70600332) | EACH | 1 | $5,035.46 | $3,600.00 | $7,993.04 |
| 97 | Terminal marker - DA (72501000) | EACH | 4 | $52.88 | $50.00 | $52.50 |
| 98 | Mod ureth PM line 5 (78009005) | LF | 3,240 | $4.27 | $5.00 | $4.24 |
| 99 | Raised refl pavt MKR (78100100) | EACH | 46 | $122.69 | $155.00 | $121.80 |
| 100 | Grdrail ref type A (78200005) | EACH | 34 | $10.58 | $11.00 | $10.50 |
| 101 | Barr wall ref type C (78200011) | EACH | 16 | $16.68 | $10.00 | $100.96 |
| 102 | Raised ref PVT MK rem (78300200) | EACH | 46 | $11.84 | $80.00 | $56.90 |
| 103 | PVT MKG rem grinding (78300201) | SF | 758 | $11.98 | $10.00 | $11.90 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.