IDOT contract 72263 bid tabulation
Section (115BDR,116SR)RS-5,124RS-8. Let by Illinois DOT on June 13, 2025, Morgan, District 06. 2 bids received; low bid $9,038,193 by Illinois Valley Paving, a div of UCM, Inc..
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 82
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Illinois Valley Paving, a div of UCM, Inc. | $9,038,193 | Low |
| 2 | K. E. Vas Company | $9,156,240 | +1.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Illinois Valley Paving, a div of UCM, Inc. | 2. K. E. Vas Company |
|---|---|---|---|---|---|
| 1 | Acrylic coating (X0325748) | SY | 68 | $169.94 | $100.00 |
| 2 | Fiber wrap (X0325749) | SF | 304 | $139.22 | $125.00 |
| 3 | Exc & GR EX SHLD SPL (X2020060) | UNIT | 299 | $1,054.97 | $400.00 |
| 4 | Grading & shap SHLDRS (X2020110) | UNIT | 299 | $110.21 | $180.00 |
| 5 | Conc median surf rem (X4402020) | SF | 26,600 | $2.74 | $3.30 |
| 6 | Corrugated med rem (X6060500) | SF | 2,297 | $14.81 | $16.00 |
| 7 | Traf bar term T6 SPL (X6310214) | EACH | 2 | $4,911.50 | $4,465.00 |
| 8 | Guardrail remov SPL (X6320100) | LF | 164 | $27.56 | $26.00 |
| 9 | SPBGR (short radius) (X6330725) | LF | 50 | $55.66 | $51.00 |
| 10 | Rem/rep SPBGR RL elem (X6331007) | LF | 54 | $36.69 | $34.00 |
| 11 | Width restrict sign (X7200201) | LS | 1 | $3,107.50 | $3,500.00 |
| 12 | Appr slab repair (PD) (Z0001800) | SY | 10 | $1,634.18 | $650.00 |
| 13 | BR deck scar 3/4 (Z0012130) | SY | 570 | $166.05 | $200.00 |
| 14 | BR DK mic C ovl 2 1/2 (Z0012164) | SY | 570 | $210.40 | $210.00 |
| 15 | STR rep con DP = < 5 (Z0012754) | SF | 10 | $344.21 | $550.00 |
| 16 | Construction layout (Z0013798) | LS | 1 | $17,908 | $30,000 |
| 17 | Deck slab rep (FD-T1) (Z0016001) | SY | 5 | $1,675.28 | $1,500.00 |
| 18 | Polymer concrete (Z0041895) | CF | 3 | $2,130.56 | $2,800.00 |
| 19 | P P conc I-BM repair (Z0043800) | SF | 38 | $568.37 | $275.00 |
| 20 | Trainees (Z0076600) | HR | 2,500 | $0.80 | $0.80 |
| 21 | Trainees TPG (Z0076604) | HR | 2,500 | $15.00 | $15.00 |
| 22 | Seeding CL 2 (25000200) | ACRE | 7 | $1,265.00 | $1,500.00 |
| 23 | Nitrogen fert nutr (25000400) | LB | 617 | $1.10 | $5.00 |
| 24 | Phosphorus fert nutr (25000500) | LB | 617 | $1.10 | $5.00 |
| 25 | Potassium fert nutr (25000600) | LB | 617 | $1.10 | $5.00 |
| 26 | Mulch method 2 (25100115) | ACRE | 7 | $1,265.00 | $1,500.00 |
| 27 | Temp ditch checks (28000305) | LF | 60 | $33.44 | $20.00 |
| 28 | Inlet & pipe protect (28000500) | EACH | 21 | $356.82 | $200.00 |
| 29 | Sub gran mat B (31101000) | TON | 4,729 | $41.54 | $51.00 |
| 30 | Preparation of base (35800100) | SY | 247 | $25.15 | $30.00 |
| 31 | Agg base repair (35800200) | TON | 20 | $58.00 | $200.00 |
| 32 | Agg surf course TY B (40200800) | TON | 29 | $356.21 | $200.00 |
| 33 | Bit matls tack CT (40600290) | LB | 97,182 | $1.04 | $3.00 |
| 34 | Long joint sealant (40600370) | LF | 37,215 | $3.01 | $5.00 |
| 35 | Matl transfer device (40600405) | TON | 10,689 | $4.65 | $5.00 |
| 36 | HMA surf rem butt JT (40600982) | SY | 4,310 | $6.59 | $25.00 |
| 37 | HMA BC IL-19.0 N50 (40603080) | TON | 14,249 | $130.79 | $135.00 |
| 38 | P HMA SC IL-9.5 C N50 (40604150) | TON | 10,678 | $150.87 | $150.00 |
| 39 | Bit matls tack CT (40800029) | LB | 798 | $1.04 | $5.00 |
| 40 | Incidental HMA surf (40800050) | TON | 305 | $296.44 | $300.00 |
| 41 | HMA surf rem 1 1/2 (44000155) | SY | 135,732 | $2.85 | $4.00 |
| 42 | Comb curb gutter rem (44000500) | LF | 5,353 | $23.52 | $14.00 |
| 43 | Agg wedge SHLD type B (48102100) | TON | 1,234 | $41.67 | $60.00 |
| 44 | HMA shoulders 6 1/2 (48203023) | SY | 13,125 | $58.48 | $48.00 |
| 45 | HMA shoulders (48203100) | TON | 3,661 | $151.74 | $150.00 |
| 46 | PCC shoulders 8 (48300300) | SY | 50 | $186.32 | $125.00 |
| 47 | Concrete sealer (58700300) | SF | 10 | $15.73 | $125.00 |
| 48 | Inlets adjust (60260100) | EACH | 8 | $1,541.77 | $870.00 |
| 49 | Comb CC&G TM4.06 (60608552) | LF | 5,353 | $89.11 | $63.00 |
| 50 | Conc median surf 4 (60618300) | SF | 26,600 | $16.52 | $12.28 |
| 51 | Corrugated med (60624600) | SF | 2,297 | $33.96 | $32.60 |
| 52 | SPBGR TY A 6FT posts (63000001) | LF | 69 | $40.92 | $38.00 |
| 53 | Traf bar term T2 (63100045) | EACH | 2 | $2,183.50 | $1,985.00 |
| 54 | TR bar TRM T1 SPL tan (63100167) | EACH | 8 | $4,136.00 | $3,760.00 |
| 55 | Guardrail remov (63200310) | LF | 522 | $14.91 | $14.00 |
| 56 | Shoulder rum strip 8 (64200108) | LF | 30,290 | $0.60 | $1.00 |
| 57 | Imp atten FRD nar TL3 (64300260) | EACH | 2 | $33,094 | $30,085 |
| 58 | Engr field office A (67000400) | CAL MO | 12 | $4,127.90 | $5,000.00 |
| 59 | Mobilization (67100100) | LS | 1 | $634,797 | $350,000 |
| 60 | Traf cont-prot 701316 (70100100) | EACH | 1 | $24,668 | $30,000 |
| 61 | Traf cont-prot 701421 (70100310) | LS | 1 | $15,675 | $145,000 |
| 62 | Traf cont-prot 701201 (70100450) | LS | 1 | $5,132.21 | $25,000 |
| 63 | Traf cont-prot 701306 (70100460) | LS | 1 | $96,882 | $205,000 |
| 64 | Traf cont-prot 701326 (70100500) | LS | 1 | $7,124.61 | $80,000 |
| 65 | TR cont & prot 701701 (70102635) | LS | 1 | $907.50 | $20,000 |
| 66 | Temp BR traf signals (70106500) | EACH | 1 | $12,384 | $25,000 |
| 67 | Temp rumble strips (70106700) | EACH | 6 | $770.00 | $1,250.00 |
| 68 | Changeable message SN (70107025) | CAL DAY | 650 | $46.20 | $75.00 |
| 69 | Short term pavt mking (70300100) | LF | 11,660 | $1.43 | $1.00 |
| 70 | SHRT TRM pavt MK rem (70300150) | SF | 1,296 | $7.93 | $4.00 |
| 71 | Terminal marker - DA (72501000) | EACH | 8 | $55.00 | $50.00 |
| 72 | Mod ureth PM LTR-sym (78009000) | SF | 234 | $4.40 | $4.00 |
| 73 | Mod ureth PM line 5 (78009005) | LF | 111,255 | $0.77 | $0.70 |
| 74 | Mod ureth PM line 6 (78009006) | LF | 1,217 | $0.99 | $0.90 |
| 75 | Mod ureth PM line 8 (78009008) | LF | 698 | $1.32 | $1.20 |
| 76 | Mod ureth PM line 12 (78009012) | LF | 1,717 | $1.98 | $1.80 |
| 77 | Mod ureth PM line 24 (78009024) | LF | 103 | $4.40 | $4.00 |
| 78 | Raised refl pavt MKR (78100100) | EACH | 640 | $43.76 | $40.00 |
| 79 | Grdrail ref type A (78200005) | EACH | 23 | $11.00 | $10.00 |
| 80 | Curb reflectors (78200020) | EACH | 211 | $19.25 | $5.00 |
| 81 | Raised ref PVT MK rem (78300200) | EACH | 632 | $9.49 | $15.00 |
| 82 | PVT MKG rem grinding (78300201) | SF | 871 | $2.51 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.