IDOT contract 72989 bid tabulation
Section (17X)RS-1,SW. Let by Illinois DOT on February 27, 2026, Sangamon, District 06. 3 bids received; low bid $3,597,405 by Illinois Valley Paving, a div of UCM, Inc..
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 64
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Illinois Valley Paving, a div of UCM, Inc. | $3,597,405 | Low |
| 2 | P. H. Broughton & Sons, Inc. | $3,618,306 | +1.0% |
| 3 | Truman L. Flatt & Sons Co., Inc. | $3,665,028 | +2.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Illinois Valley Paving, a div of UCM, Inc. | 2. P. H. Broughton & Sons, Inc. | 3. Truman L. Flatt & Sons Co., Inc. |
|---|---|---|---|---|---|---|
| 1 | PC conc sidewalk 4 SP (X4240420) | SF | 50 | $60.66 | $90.00 | $121.80 |
| 2 | Conc median surf rem (X4402020) | SF | 8 | $74.52 | $77.30 | $75.60 |
| 3 | Conc median remov (X4403300) | SF | 550 | $14.15 | $25.00 | $18.90 |
| 4 | PCC surf rem 3 (X4406824) | SY | 80 | $16.09 | $22.88 | $27.57 |
| 5 | Fac in exist cab (X8570215) | EACH | 1 | $7,153.92 | $7,420.44 | $7,257.60 |
| 6 | Video veh det sys 4 cam (X8891013) | EACH | 1 | $33,385 | $34,629 | $33,869 |
| 7 | Construction layout (Z0013798) | LS | 1 | $11,290 | $16,103 | $4,725.00 |
| 8 | Trainees (Z0076600) | HR | 3,000 | $0.80 | $0.80 | $0.80 |
| 9 | Trainees TPG (Z0076604) | HR | 3,000 | $15.00 | $15.00 | $15.00 |
| 10 | Agg base cse B 4 (35101600) | SY | 40 | $104.81 | $26.84 | $84.00 |
| 11 | PCC bse cse 14 (35300728) | SY | 61 | $162.47 | $300.00 | $385.35 |
| 12 | Bit matls tack CT (40600290) | LB | 59,217 | $0.88 | $0.66 | $0.68 |
| 13 | Long joint sealant (40600370) | LF | 41,662 | $2.65 | $3.12 | $2.83 |
| 14 | Matl transfer device (40600405) | TON | 7,026 | $6.19 | $5.24 | $6.12 |
| 15 | HMA surf rem butt JT (40600982) | SY | 1,222 | $9.05 | $26.88 | $14.87 |
| 16 | Temporary ramp (40600990) | SY | 610 | $5.84 | $12.02 | $17.43 |
| 17 | P HMA BC IL-9.5FG N70 (40603218) | TON | 5,865 | $154.65 | $146.62 | $155.11 |
| 18 | P HMA SC IL-9.5 D N70 (40604162) | TON | 7,038 | $152.24 | $151.66 | $152.99 |
| 19 | Bit matls tack CT (40800029) | LB | 550 | $0.85 | $1.00 | $0.69 |
| 20 | Incidental HMA surf (40800050) | TON | 94 | $368.71 | $470.80 | $366.08 |
| 21 | Detectable warnings (42400800) | SF | 20 | $51.76 | $75.00 | $63.00 |
| 22 | HMA surf rem 1 1/4 (44000154) | SY | 7,257 | $3.62 | $10.21 | $4.01 |
| 23 | HMA surf rem 2 1/2 (44000159) | SY | 83,640 | $4.50 | $4.21 | $4.78 |
| 24 | Comb curb gutter rem (44000500) | LF | 60 | $14.48 | $33.56 | $30.09 |
| 25 | Sidewalk rem (44000600) | SF | 50 | $17.37 | $22.54 | $10.91 |
| 26 | CL A patch T2 10 (44200553) | SY | 73 | $501.98 | $483.10 | $509.25 |
| 27 | CL A patch T3 10 (44200557) | SY | 35 | $497.84 | $483.10 | $505.05 |
| 28 | CL A patch T4 10 (44200559) | SY | 73 | $493.70 | $483.10 | $500.85 |
| 29 | Patch reinforcement (44213000) | SY | 182 | $80.73 | $161.03 | $81.90 |
| 30 | Saw cuts (44213200) | LF | 808 | $11.39 | $13.42 | $11.55 |
| 31 | Tie bars 3/4 (44213204) | EACH | 30 | $21.74 | $37.57 | $22.05 |
| 32 | HMA shoulders (48203100) | TON | 610 | $132.41 | $172.82 | $166.86 |
| 33 | Man adjust (60255500) | EACH | 5 | $1,206.66 | $4,152.55 | $1,026.10 |
| 34 | Inlets adjust (60260100) | EACH | 7 | $2,233.07 | $2,275.00 | $1,179.84 |
| 35 | VV adjust (60265700) | EACH | 8 | $768.46 | $1,000.00 | $815.31 |
| 36 | Comb CC&G TY B-6.24 (60605000) | LF | 60 | $108.23 | $120.00 | $204.75 |
| 37 | Conc median surf 4 (60618300) | SF | 8 | $149.04 | $154.59 | $151.20 |
| 38 | Engr field office A (67000400) | CAL MO | 12 | $3,526.05 | $3,723.39 | $3,076.51 |
| 39 | Mobilization (67100100) | LS | 1 | $131,188 | $98,318 | $70,180 |
| 40 | TR cont & prot 701601 (70102630) | LS | 1 | $26,550 | $26,839 | $36,039 |
| 41 | TR cont & prot 701602 (70102632) | LS | 1 | $36,689 | $19,968 | $40,087 |
| 42 | TR cont & prot 701701 (70102635) | LS | 1 | $1,399.86 | $107.36 | $7,052.09 |
| 43 | TR cont & prot 701801 (70102640) | LS | 1 | $103.50 | $107.36 | $99.53 |
| 44 | Changeable message SN (70107025) | CAL DAY | 360 | $65.21 | $67.63 | $105.00 |
| 45 | Night work zone light (70200100) | LS | 1 | $86,064 | $50,457 | $91,465 |
| 46 | Short term pavt mking (70300100) | LF | 6,843 | $0.01 | $1.61 | $1.27 |
| 47 | SHRT TRM pavt MK rem (70300150) | SF | 753 | $1.25 | $12.29 | $3.53 |
| 48 | Mod ureth PM LTR-sym (78009000) | SF | 2,069 | $19.67 | $9.13 | $8.93 |
| 49 | Mod ureth PM line 5 (78009005) | LF | 46,903 | $0.75 | $0.94 | $0.92 |
| 50 | Mod ureth PM line 6 (78009006) | LF | 8,147 | $2.07 | $1.13 | $1.10 |
| 51 | Mod ureth PM line 8 (78009008) | LF | 3,067 | $5.18 | $1.93 | $1.89 |
| 52 | Mod ureth PM line 12 (78009012) | LF | 1,341 | $9.32 | $4.03 | $3.94 |
| 53 | Mod ureth PM line 24 (78009024) | LF | 739 | $19.67 | $8.59 | $8.40 |
| 54 | GRV RCSD PM LTR & sym (78011000) | SF | 2,069 | $3.36 | $9.13 | $8.93 |
| 55 | GRV RCSD PVT MRKG 6 (78011030) | LF | 46,903 | $0.37 | $0.70 | $0.68 |
| 56 | GRV RCSD PVT MRKG 7 (78011035) | LF | 8,147 | $1.04 | $0.82 | $0.80 |
| 57 | GRV RCSD PVT MRKG 9 (78011045) | LF | 3,067 | $2.59 | $3.01 | $2.94 |
| 58 | GRV RCSD PVT MRKG 13 (78011065) | LF | 1,341 | $4.66 | $4.56 | $4.46 |
| 59 | GRV RCSD PVT MRKG 25 (78011125) | LF | 739 | $9.32 | $9.13 | $8.93 |
| 60 | Raised refl pavt MKR (78100100) | EACH | 980 | $39.81 | $56.90 | $55.65 |
| 61 | Raised ref PVT MK rem (78300200) | EACH | 980 | $7.96 | $9.11 | $23.06 |
| 62 | Undrgrd C PVC 2 (81028350) | LF | 239 | $40.99 | $42.51 | $41.58 |
| 63 | Intersec monitor unit (85706000) | EACH | 1 | $2,285.28 | $2,370.42 | $2,318.40 |
| 64 | Drill EX handhole (87900200) | EACH | 4 | $894.24 | $927.56 | $907.20 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.