IDOT contract 76K02 bid tabulation
Section 82-5VB-R-2. Let by Illinois DOT on March 7, 2025, St.Clair, District 08. 2 bids received; low bid $35,988,571 by Keeley & Sons, Inc..
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 110
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Keeley & Sons, Inc. | $35,988,571 | Low |
| 2 | Millstone Weber LLC | $40,594,060 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Keeley & Sons, Inc. | 2. Millstone Weber LLC |
|---|---|---|---|---|---|
| 1 | Conduit support sys (X0321519) | LS | 1 | $121,847 | $40,000 |
| 2 | Bolt replacement (X0322559) | EACH | 307 | $200.40 | $181.47 |
| 3 | Polyurethane sealant (X0327543) | LF | 3,002 | $11.55 | $22.75 |
| 4 | Conc rem spec (X5012502) | CY | 1,030.60 | $2,290.00 | $4,000.00 |
| 5 | Protective coat SPL (X5030550) | SY | 68 | $15.00 | $25.75 |
| 6 | Bridge drain sys RPR (X5230144) | EACH | 1 | $135,000 | $17,700 |
| 7 | Conc bar wall SPL (X6370050) | LF | 99 | $598.45 | $370.00 |
| 8 | Engr FLD off A SPL (X6700410) | CAL MO | 17 | $3,890.00 | $4,500.00 |
| 9 | Traf cont & prot SPL (X7010216) | LS | 1 | $367,890 | $151,800 |
| 10 | Changeable MSG SN SPL (X7010239) | CAL WK | 47 | $306.00 | $525.00 |
| 11 | Alternate rte signing (X7200202) | LS | 1 | $17,111 | $16,400 |
| 12 | Smart traf monit sys (X8570002) | CAL WK | 47 | $765.00 | $375.00 |
| 13 | Smart traf monit dev (X8570004) | CAL WK | 47 | $178.50 | $500.00 |
| 14 | Struct steel repair (Z0001905) | LB | 59,170 | $19.95 | $15.75 |
| 15 | C&D lead PT CL RS N1 (Z0007101) | LS | 1 | $1,077,707 | $376,472 |
| 16 | Clean & PT STL BR N1 (Z0010501) | LS | 1 | $2,001,470 | $1,129,316 |
| 17 | Clean drainage system (Z0010605) | LS | 1 | $47,890 | $4,500.00 |
| 18 | STR rep con DP = < 5 (Z0012754) | SF | 8,161 | $157.85 | $155.00 |
| 19 | STR rep con DP over 5 (Z0012755) | SF | 915 | $159.85 | $310.00 |
| 20 | Construction layout (Z0013798) | LS | 1 | $178,500 | $58,000 |
| 21 | Deck slab rep (FD-T1) (Z0016001) | SY | 52 | $1,980.00 | $2,600.00 |
| 22 | Deck slab rep (FD-T2) (Z0016002) | SY | 52 | $1,190.00 | $2,700.00 |
| 23 | Deck slab rep (part) (Z0016200) | SY | 496 | $449.85 | $1,200.00 |
| 24 | Detour signing (Z0016702) | LS | 1 | $45,645 | $38,600 |
| 25 | Drainage scuppers adj (Z0018051) | EACH | 26 | $1,390.00 | $760.00 |
| 26 | Drainage STR cleaned (Z0018500) | EACH | 1 | $19,800 | $4,500.00 |
| 27 | RR prot liability ins (Z0048665) | LS | 1 | $337,800 | $341,650 |
| 28 | Temp support sys L1 (Z0073410) | EACH | 1 | $945,700 | $2,125,000 |
| 29 | Temp support sys L2 (Z0073420) | EACH | 1 | $1,800,000 | $2,200,000 |
| 30 | Temp support sys L3 (Z0073430) | EACH | 1 | $2,700,000 | $3,000,000 |
| 31 | Temp support sys L4 (Z0073431) | EACH | 1 | $2,100,000 | $1,975,000 |
| 32 | Temp support sys L5 (Z0073432) | EACH | 1 | $2,300,000 | $1,975,000 |
| 33 | Temp support sys L6 (Z0073433) | EACH | 1 | $990,800 | $1,950,000 |
| 34 | Temp support sys L7 (Z0073434) | EACH | 1 | $990,800 | $1,950,000 |
| 35 | Temp support sys L8 (Z0073435) | EACH | 1 | $945,700 | $1,950,000 |
| 36 | Trainees (Z0076600) | HR | 3,000 | $0.80 | $0.80 |
| 37 | Trainees TPG (Z0076604) | HR | 3,000 | $15.00 | $15.00 |
| 38 | Trench backfill (20800150) | CY | 2 | $100.00 | $120.00 |
| 39 | Geotech fab F/GR stab (21001000) | SY | 588 | $8.55 | $6.20 |
| 40 | Perimeter eros bar (28000400) | LF | 331 | $30.00 | $7.50 |
| 41 | Stone riprap CL A3 (28100105) | SY | 6 | $300.00 | $160.00 |
| 42 | Agg base cse A 12 (35101100) | SY | 588 | $32.85 | $42.00 |
| 43 | P bit matls tack CT (40600295) | LB | 1,500 | $0.77 | $0.76 |
| 44 | Long joint sealant (40600370) | LF | 1,792 | $8.16 | $8.08 |
| 45 | HMA surf rem butt JT (40600982) | SY | 2,156 | $16.32 | $16.16 |
| 46 | P SC SMA 9.5 E N80 (40605024) | TON | 2,166 | $245.82 | $245.45 |
| 47 | Welded wire reinf (42000060) | SY | 758 | $19.80 | $19.50 |
| 48 | HMA surf rem 3/4 (44000152) | SY | 1,171 | $16.32 | $16.16 |
| 49 | Paved SHLD removal (44004250) | SY | 973 | $25.50 | $28.75 |
| 50 | Agg wedge SHLD type B (48102100) | TON | 7 | $200.00 | $330.00 |
| 51 | HMA shoulders 10 (48203037) | SY | 886 | $114.24 | $114.14 |
| 52 | PCC shoulders 12 3/4 (48300715) | SY | 39 | $187.85 | $180.00 |
| 53 | Conc rem (50102400) | CY | 267.20 | $2,690.00 | $1,800.00 |
| 54 | Protective shield (50157300) | SY | 1,914 | $58.45 | $120.00 |
| 55 | Conc struct (50300225) | CY | 1,649.80 | $2,495.00 | $2,100.00 |
| 56 | Conc sup-STR (50300255) | CY | 309.20 | $4,190.00 | $3,600.00 |
| 57 | F & E struct steel (50500405) | LB | 12,600 | $22.85 | $56.00 |
| 58 | Reinf bars, epoxy CTD (50800205) | LB | 317,540 | $2.85 | $2.40 |
| 59 | Bar splicers (50800515) | EACH | 544 | $56.78 | $48.27 |
| 60 | Pref joint seal 2 1/4 (52000027) | LF | 1,655 | $28.85 | $50.00 |
| 61 | Pref JT strip seal (52000110) | LF | 1,296 | $381.00 | $450.00 |
| 62 | Elast bearing assy T1 (52100010) | EACH | 192 | $2,390.00 | $3,000.00 |
| 63 | Anchor bolts 1 1/2 (52100540) | EACH | 512 | $157.44 | $145.35 |
| 64 | End sections 12 (54213447) | EACH | 3 | $625.00 | $1,700.00 |
| 65 | Storm sew CL A 2 12 (550A0340) | LF | 134 | $70.00 | $240.00 |
| 66 | FLS waterproof system (58100210) | SY | 19,777 | $29.33 | $30.10 |
| 67 | Concrete sealer (58700300) | SF | 36,774 | $0.70 | $5.50 |
| 68 | Inlets adjust (60260100) | EACH | 1 | $1,145.00 | $1,700.00 |
| 69 | Remov inlets (60500060) | EACH | 3 | $550.00 | $1,300.00 |
| 70 | Conc thrust blocks (61000050) | EACH | 3 | $487.00 | $2,200.00 |
| 71 | TY E inlet box 610001 (61000115) | EACH | 3 | $4,500.00 | $8,900.00 |
| 72 | SPBGR TY A 6FT posts (63000001) | LF | 375 | $29.33 | $27.90 |
| 73 | Traf bar term T2 (63100045) | EACH | 1 | $2,014.50 | $1,701.70 |
| 74 | Traf bar term T5 (63100070) | EACH | 1 | $1,428.00 | $1,590.00 |
| 75 | Traf bar term T6 (63100085) | EACH | 1 | $4,462.50 | $4,011.00 |
| 76 | TR bar TRM T1 SPL tan (63100167) | EACH | 1 | $3,213.00 | $3,242.50 |
| 77 | Guardrail remov (63200310) | LF | 493 | $6.12 | $7.80 |
| 78 | Conc glare screen (63801000) | LF | 356 | $184.83 | $330.00 |
| 79 | Shoulder rum strip 16 (64200116) | LF | 383 | $26.00 | $25.00 |
| 80 | Conc SHLD curb (66201120) | LF | 79 | $100.00 | $200.00 |
| 81 | Fur erect row markers (66600105) | EACH | 5 | $800.00 | $930.00 |
| 82 | Non SPL waste disposl (66900200) | CY | 238 | $235.22 | $69.00 |
| 83 | Soil disposal analy (66900530) | EACH | 1 | $1,428.00 | $1,980.00 |
| 84 | Reg sub P-const plan (66901001) | LS | 1 | $2,244.00 | $2,300.00 |
| 85 | Reg sub F con report (66901003) | LS | 1 | $2,244.00 | $2,100.00 |
| 86 | Reg sub mon (66901006) | CAL DAY | 20 | $1,111.80 | $1,500.00 |
| 87 | Mobilization (67100100) | LS | 1 | $2,160,000 | $2,400,000 |
| 88 | Pavt MK blkout tape 5 (70107005) | LF | 19,301 | $2.25 | $2.30 |
| 89 | Pavt MK blkout tape 7 (70107007) | LF | 1,220 | $3.25 | $3.05 |
| 90 | Pavt MK blkout tape 9 (70107009) | LF | 11,747 | $4.23 | $3.90 |
| 91 | Changeable message SN (70107025) | CAL DAY | 1,428 | $31.62 | $35.00 |
| 92 | Night work zone light (70200100) | LS | 1 | $3,570.00 | $52,000 |
| 93 | Short term pavt mking (70300100) | LF | 1,445 | $1.55 | $3.50 |
| 94 | SHRT TRM pavt MK rem (70300150) | SF | 54,660 | $1.35 | $1.50 |
| 95 | Temp PVT MK L6 T4 tape (70307130) | LF | 73,227 | $1.94 | $2.40 |
| 96 | Temp conc barrier (70400100) | LF | 7,537.50 | $35.80 | $52.00 |
| 97 | Rel temp conc barrier (70400200) | LF | 5,100 | $9.69 | $12.00 |
| 98 | Imp attn temp NRN TL3 (70600251) | EACH | 7 | $3,060.00 | $4,500.00 |
| 99 | Imp attn rel NRN TL3 (70600352) | EACH | 3 | $1,275.00 | $400.00 |
| 100 | Terminal marker - DA (72501000) | EACH | 1 | $42.84 | $25.00 |
| 101 | Pref PL PM TB STNRD LTR-sym (78003101) | SF | 56 | $165.24 | $160.14 |
| 102 | Pref PL PM TB STD L6 (78003131) | LF | 8,112 | $6.79 | $6.26 |
| 103 | Pref PL PM TB STD L8 (78003141) | LF | 1,121 | $10.71 | $11.83 |
| 104 | GRV RCSD PM LTR & sym (78011000) | SF | 56 | $2.55 | $33.51 |
| 105 | GRV RCSD PVT MRKG 7 (78011035) | LF | 8,112 | $0.26 | $0.86 |
| 106 | GRV RCSD PVT MRKG 9 (78011045) | LF | 1,121 | $0.77 | $1.36 |
| 107 | Raised refl pavt MKR (78100100) | EACH | 249 | $65.28 | $51.55 |
| 108 | Grdrail ref type A (78200005) | EACH | 6 | $12.24 | $12.00 |
| 109 | Barr wall ref type C (78200011) | EACH | 29 | $12.24 | $20.75 |
| 110 | Raised ref PVT MK rem (78300200) | EACH | 244 | $20.40 | $79.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.