IDOT contract 78495 bid tabulation

Section 11CR-1;12CR-1. Let by Illinois DOT on April 24, 2026, Jefferson, District 09. 4 bids received; low bid $663,975 by Samron Midwest Contracting, Inc..

Owner
Illinois DOT
Letting
24 APR 2026
Pay items
47
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Samron Midwest Contracting, Inc.$663,975Low
2E. T. Simonds Construction Company$739,217+11%
3Sierra Bravo Contractors, LLC$875,923+32%
4Brewster Companies, Inc.$1,191,402+79%
IDOT contract 78495: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Samron Midwest Contracting, Inc.2. E. T. Simonds Construction Company3. Sierra Bravo Contractors, LLC4. Brewster Companies, Inc.
1RRPM protection (X3000001)EACH14$2.00$32.14$10.06$150.00
2Memb WTRPRF sys B STR (X5810103)SY70$21.00$43.79$47.10$95.00
3TC-prot 701316 SPL (X7010200)EACH1$23,250$25,885$22,419$17,520
4Traf cont-prot BLR 21 (X7011800)LS1$1,800.00$4,272.21$6,747.86$1,800.00
5Detour signing (X7200203)LS1$14,000$21,058$20,852$16,100
6Construction layout (Z0013798)LS1$7,500.00$25,115$20,265$9,000.00
7Rock fill - foundatn (Z0054517)TON444$40.00$41.60$60.82$85.00
8Tree remov over 15 (20100210)UNIT30$30.00$61.24$111.68$800.00
9Earth excavation (20200100)CY1,146$20.00$35.07$40.60$45.00
10Furnished excavation (20400800)CY51$35.00$79.71$102.48$90.00
11Porous gran embank (20700220)CY945$70.00$92.75$97.46$140.00
12Seeding CL 2A (25000210)ACRE0.38$9,000.00$9,405.00$8,977.50$4,900.00
13Seeding CL 7 (25000350)ACRE0.38$0.01$2,695.00$2,572.50$3,900.00
14Nitrogen fert nutr (25000400)LB34$2.00$1.87$1.79$0.90
15Phosphorus fert nutr (25000500)LB34$2.00$1.87$1.79$0.90
16Potassium fert nutr (25000600)LB34$2.00$1.87$1.79$0.90
17Agr ground limestone (25000700)TON1$700.00$396.00$378.00$400.00
18Erosion contr blanket (25100630)SY1,833$2.00$2.37$2.26$1.50
19Temp eros contr seed (28000250)LB76$4.00$7.49$6.21$20.00
20Temp ditch checks (28000305)LF127$11.00$11.06$2.59$14.00
21Perimeter eros bar (28000400)LF518$7.00$8.53$5.39$3.00
22Stone riprap CL A4 (28100107)SY118$85.00$54.22$65.56$125.00
23Filter fabric (28200200)SY118$7.00$9.41$6.80$1.00
24Welded wire reinf (42000060)SY291$8.00$15.75$16.92$10.00
25PCC PVT 10 (42000500)SY291$140.00$212.42$291.90$360.00
26Pavement rem (44000100)SY291$10.00$24.98$58.64$50.00
27Paved SHLD removal (44004250)SY61$8.00$46.77$69.93$50.00
28PCC shoulders 10 (48300500)SY106$75.00$175.68$437.95$330.00
29Rem exist struct N1 (50100300)EACH1$4,000.00$9,290.50$15,837$30,000
30Rem exist struct N2 (50100400)EACH1$5,000.00$9,290.50$15,837$30,000
31Rem/disp uns matl-STR (50200450)CY247$30.00$21.78$31.57$110.00
32Reinf bars, epoxy CTD (50800205)LB3,810$3.00$2.30$1.81$3.00
33Conc box cul (54003000)CY46.70$2,100.00$2,448.71$2,685.43$1,980.00
34PCBC 7X6 (54010706)LF170$1,300.00$837.30$965.80$2,090.00
35Geocomposite wall DR (59100100)SY70$10.00$19.70$25.68$20.00
36Fur erect row markers (66600105)EACH16$350.00$407.06$243.87$85.00
37Engr field office A (67000400)CAL MO6$0.01$2,000.00$3,150.00$5,000.00
38Mobilization (67100100)LS1$39,000$33,953$52,555$70,000
39Temp BR traf signals (70106500)EACH1$14,000$17,791$10,500$10,000
40Temp rumble strips (70106700)EACH6$1,000.00$1,664.01$840.00$900.00
41Pavt MK blkout tape 5 (70107005)LF1,918$3.00$3.69$2.63$4.00
42Changeable message SN (70107025)CAL DAY68$100.00$74.66$90.03$120.00
43Short term pavt mking (70300100)LF24$3.00$0.99$5.87$30.00
44SHRT TRM pavt MK rem (70300150)SF807$1.50$4.19$2.62$1.20
45Temp PVT MK line 4 - paint (70300221)LF443$0.01$0.01$7.98$5.00
46Paint PVT MK line 4 (78001110)LF443$4.00$4.48$7.98$5.00
47Uninter power sup ext (86200300)EACH1$0.01$0.01$0.01$15,000
IDOT contract 78495: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy