IDOT contract 78A80 bid tabulation
Section 77(1,1-1,1-2,1-3,2,2-1,3)RS-3;BRREP. Let by Illinois DOT on April 25, 2025, Pulaski, District 09. 2 bids received; low bid $12,722,436 by E. T. Simonds Construction Company.
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 92
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E. T. Simonds Construction Company | $12,722,436 | Low |
| 2 | Samron Midwest Contracting, Inc. | $14,272,978 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E. T. Simonds Construction Company | 2. Samron Midwest Contracting, Inc. |
|---|---|---|---|---|---|
| 1 | Rodent shields (X0322278) | EACH | 462 | $141.78 | $185.00 |
| 2 | BR deck grooving long (X5030250) | SY | 1,960 | $13.79 | $12.00 |
| 3 | Conc wearing surf rem (X5030275) | SY | 2,246 | $38.81 | $27.00 |
| 4 | Conc wearing surf VD (X5030301) | SY | 2,184 | $97.05 | $95.00 |
| 5 | Structural STL removl (X5051204) | LB | 4,720 | $3.30 | $5.00 |
| 6 | Struct steel repair (X5051206) | LB | 1,212 | $40.44 | $22.50 |
| 7 | Bar terminators (X5080530) | EACH | 552 | $25.33 | $28.00 |
| 8 | Jack & rem EX bearing (Z0001899) | EACH | 28 | $1,406.98 | $1,500.00 |
| 9 | Approach slab rem (Z0004552) | SY | 529 | $36.58 | $65.00 |
| 10 | C&D lead PT CL RS N1 (Z0007101) | LS | 1 | $35,700 | $40,000 |
| 11 | C&D lead PT CL RS N2 (Z0007102) | LS | 1 | $35,700 | $40,000 |
| 12 | Clean & PT STL BR N1 (Z0010501) | LS | 1 | $132,600 | $140,000 |
| 13 | Clean & PT STL BR N2 (Z0010502) | LS | 1 | $132,600 | $140,000 |
| 14 | BR deck scar 1/2 (Z0012157) | SY | 2,184 | $40.97 | $48.00 |
| 15 | STR rep con DP = < 5 (Z0012754) | SF | 42 | $243.14 | $225.00 |
| 16 | Deck slab rep (FD-T1) (Z0016001) | SY | 1 | $2,090.06 | $1,800.00 |
| 17 | Deck slab rep (FD-T2) (Z0016002) | SY | 19 | $1,480.28 | $1,900.00 |
| 18 | Diamond grind BR sec (Z0029090) | SY | 2,464 | $11.81 | $13.00 |
| 19 | Pavt fabric epoxy CTD (Z0037100) | SY | 547 | $34.56 | $0.01 |
| 20 | Trainees (Z0076600) | HR | 1,000 | $0.80 | $0.80 |
| 21 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 | $15.00 |
| 22 | Earth excavation (20200100) | CY | 5 | $130.95 | $100.00 |
| 23 | Furnished excavation (20400800) | CY | 20 | $120.83 | $250.00 |
| 24 | Bit matls tack CT (40600290) | LB | 260,515 | $0.01 | $0.01 |
| 25 | Long joint sealant (40600370) | LF | 101,866 | $2.67 | $3.00 |
| 26 | Matl transfer device (40600405) | TON | 59,533 | $2.20 | $1.50 |
| 27 | HMA surf rem butt JT (40600982) | SY | 1,341 | $6.61 | $10.00 |
| 28 | Temporary ramp (40600990) | SY | 738 | $37.30 | $0.01 |
| 29 | P HMA BC IL-9.5FG N90 (40603219) | TON | 92 | $92.42 | $92.00 |
| 30 | P HMA BC IL19.0 N90 (40603240) | TON | 34,937 | $75.92 | $95.50 |
| 31 | P HMA SC IL-9.5 D N90 (40604164) | TON | 23,433 | $97.43 | $103.00 |
| 32 | Welded wire reinf (42000060) | SY | 238 | $17.95 | $25.00 |
| 33 | PVT con PCC BR app SL (42000080) | SY | 238 | $259.49 | $250.00 |
| 34 | HMA surf rem 1 1/2 (44000155) | SY | 435,071 | $1.41 | $1.95 |
| 35 | HMA surf rem 2 (44000157) | SY | 916 | $8.09 | $10.50 |
| 36 | HMA surf rem 3 1/4 (44000162) | SY | 5,546 | $3.91 | $2.75 |
| 37 | HMA surf rem 3 3/4 (44000164) | SY | 11,156 | $2.78 | $3.00 |
| 38 | Paved SHLD removal (44004250) | SY | 104 | $62.00 | $35.00 |
| 39 | CL A patch T2 14 (44200620) | SY | 125 | $275.00 | $385.00 |
| 40 | CL A patch T3 14 (44200624) | SY | 16 | $270.00 | $375.00 |
| 41 | CL B patch T2 16 (44201043) | SY | 499 | $210.00 | $220.00 |
| 42 | CL B patch T3 16 (44201047) | SY | 200 | $200.00 | $215.00 |
| 43 | CL B patch T4 16 (44201048) | SY | 347 | $193.36 | $210.00 |
| 44 | Dowel bars 1 (44201297) | EACH | 1,680 | $20.20 | $20.00 |
| 45 | Patch reinforcement (44213000) | SY | 141 | $48.38 | $40.00 |
| 46 | Saw cuts (44213200) | LF | 5,308 | $7.60 | $10.00 |
| 47 | Tie bars 3/4 (44213204) | EACH | 33 | $22.21 | $20.00 |
| 48 | Agg wedge SHLD type B (48102100) | TON | 3,075 | $35.95 | $55.00 |
| 49 | HMA shoulders 2 (48203005) | SY | 103 | $65.75 | $325.00 |
| 50 | HMA shoulders 10 (48203037) | SY | 104 | $152.34 | $320.00 |
| 51 | HMA shoulders (48203100) | TON | 33,771 | $74.70 | $89.00 |
| 52 | Conc rem (50102400) | CY | 56.60 | $2,324.87 | $1,500.00 |
| 53 | Structure excavation (50200100) | CY | 140 | $40.69 | $52.00 |
| 54 | Conc struct (50300225) | CY | 48 | $1,092.36 | $850.00 |
| 55 | Conc sup-STR (50300255) | CY | 74.40 | $1,870.17 | $1,750.00 |
| 56 | Protective coat (50300300) | SY | 2,802 | $1.59 | $3.00 |
| 57 | Conc supstr app slab (50301350) | CY | 129.40 | $456.88 | $775.00 |
| 58 | F & E struct steel (50500405) | LB | 4,610 | $6.70 | $7.50 |
| 59 | Reinf bars, epoxy CTD (50800205) | LB | 88,540 | $1.52 | $1.75 |
| 60 | Bar splicers (50800515) | EACH | 1,138 | $39.76 | $45.00 |
| 61 | Elast bearing assy T1 (52100010) | EACH | 28 | $976.55 | $1,250.00 |
| 62 | Anchor bolts 1 (52100520) | EACH | 56 | $116.18 | $125.00 |
| 63 | Temp soil reten systm (52200020) | SF | 112 | $363.57 | $600.00 |
| 64 | Granular backfill STR (58600101) | CY | 120 | $75.77 | $95.00 |
| 65 | Geocomposite wall DR (59100100) | SY | 40 | $28.27 | $20.00 |
| 66 | Conc HDWL for P drain (60100060) | EACH | 4 | $353.61 | $500.00 |
| 67 | P undr for struct 4 (60146304) | LF | 308 | $59.58 | $30.00 |
| 68 | Shoulder rum strip 16 (64200116) | LF | 202,307 | $0.27 | $0.20 |
| 69 | Mobilization (67100100) | LS | 1 | $819,865 | $850,000 |
| 70 | Traf cont-prot 701402 (70100207) | EACH | 2 | $34,219 | $48,000 |
| 71 | Traf cont-prot 701411 (70100420) | EACH | 4 | $8,186.65 | $5,000.00 |
| 72 | Traf cont-prot 701401 (70100800) | LS | 1 | $330,991 | $135,000 |
| 73 | Traf cont-prot 701456 (70100825) | LS | 1 | $25,061 | $0.01 |
| 74 | Changeable message SN (70107025) | CAL DAY | 28 | $76.80 | $150.00 |
| 75 | Short term pavt mking (70300100) | LF | 37,341 | $1.37 | $0.01 |
| 76 | SHRT TRM pavt MK rem (70300150) | SF | 18,594 | $0.01 | $0.01 |
| 77 | Temp PVT MK line 6 - paint (70300241) | LF | 230,055 | $0.01 | $0.01 |
| 78 | Temp PVT MK line 8 - paint (70300251) | LF | 1,782 | $0.01 | $0.01 |
| 79 | Temp conc barrier (70400100) | LF | 1,175 | $22.86 | $36.00 |
| 80 | Pin temp conc barrier (70400125) | EACH | 66 | $25.31 | $9.00 |
| 81 | Rel temp conc barrier (70400200) | LF | 1,150 | $5.68 | $4.00 |
| 82 | Imp attn temp NRN TL3 (70600251) | EACH | 2 | $4,172.68 | $7,500.00 |
| 83 | Imp attn rel NRN TL3 (70600352) | EACH | 2 | $1,998.91 | $1,200.00 |
| 84 | THPL PVT MK LTR & sym (78000100) | SF | 924 | $12.41 | $13.75 |
| 85 | THPL PVT MK line 6 (78000400) | LF | 230,055 | $0.81 | $0.90 |
| 86 | THPL PVT MK line 8 (78000500) | LF | 1,782 | $1.03 | $1.10 |
| 87 | GRV RCSD PM LTR & sym (78011000) | SF | 2,005 | $4.65 | $5.00 |
| 88 | GRV RCSD PVT MRKG 7 (78011035) | LF | 230,055 | $0.52 | $0.65 |
| 89 | GRV RCSD PVT MRKG 9 (78011045) | LF | 1,782 | $0.67 | $0.70 |
| 90 | Raised refl pavt MKR (78100100) | EACH | 1,405 | $40.19 | $46.00 |
| 91 | Raised ref PVT MK rem (78300200) | EACH | 1,405 | $6.92 | $15.00 |
| 92 | PVT MKG rem grinding (78300201) | SF | 119,686 | $0.01 | $0.01 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.