IDOT contract 78A97 bid tabulation
Section (1R)SLP-1. Let by Illinois DOT on June 13, 2025, Jackson, District 09. 3 bids received; low bid $170,723 by Sierra Bravo Contractors, LLC.
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 28
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Sierra Bravo Contractors, LLC | $170,723 | Low |
| 2 | Samron Midwest Contracting, Inc. | $176,115 | +3.0% |
| 3 | May Excavating, Inc. | $233,557 | +37% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sierra Bravo Contractors, LLC | 2. Samron Midwest Contracting, Inc. | 3. May Excavating, Inc. |
|---|---|---|---|---|---|---|
| 1 | Clearing & grubbing (X2010510) | LS | 1 | $12,327 | $20,000 | $5,000.00 |
| 2 | Rem & disp uns matl (20201200) | CY | 850 | $23.76 | $35.00 | $30.00 |
| 3 | Furnished excavation (20400800) | CY | 561 | $34.32 | $60.00 | $120.00 |
| 4 | Geotech fab F/GR stab (21001000) | SY | 41 | $6.41 | $30.00 | $10.00 |
| 5 | Seeding CL 2 (25000200) | ACRE | 0.10 | $30,313 | $25,000 | $10,000 |
| 6 | Seeding CL 7 (25000350) | ACRE | 0.10 | $2,156.30 | $0.01 | $10,000 |
| 7 | Nitrogen fert nutr (25000400) | LB | 9 | $2.06 | $10.00 | $10.00 |
| 8 | Phosphorus fert nutr (25000500) | LB | 9 | $2.06 | $10.00 | $10.00 |
| 9 | Potassium fert nutr (25000600) | LB | 9 | $2.06 | $10.00 | $10.00 |
| 10 | Agr ground limestone (25000700) | TON | 0.20 | $446.25 | $500.00 | $2,500.00 |
| 11 | Mulch method 2 (25100115) | ACRE | 0.10 | $21,688 | $0.01 | $10,000 |
| 12 | Erosion contr blanket (25100630) | SY | 488 | $2.31 | $2.50 | $10.00 |
| 13 | Temp eros contr seed (28000250) | LB | 15 | $7.10 | $0.01 | $10.00 |
| 14 | Perimeter eros bar (28000400) | LF | 150 | $11.21 | $8.00 | $15.00 |
| 15 | Stone riprap CL A4 (28100107) | SY | 379 | $58.94 | $40.00 | $115.00 |
| 16 | Filter fabric (28200200) | SY | 379 | $4.06 | $5.00 | $18.00 |
| 17 | Lime (30201500) | TON | 34 | $368.87 | $250.00 | $65.00 |
| 18 | Aggregate SHLDS A (48100100) | TON | 22 | $50.42 | $60.00 | $65.00 |
| 19 | Conc HDWL for P drain (60100060) | EACH | 4 | $879.31 | $1,000.00 | $2,000.00 |
| 20 | Pipe underdrain 4 SP (60108100) | LF | 170 | $71.51 | $3.00 | $35.00 |
| 21 | Backslope drain T3 4 (60109640) | LF | 80 | $111.30 | $40.00 | $35.00 |
| 22 | Mobilization (67100100) | LS | 1 | $10,198 | $9,500.00 | $9,000.00 |
| 23 | Traf cont-prot 701316 (70100100) | EACH | 1 | $21,025 | $28,000 | $5,000.00 |
| 24 | Traf cont-prot 701306 (70100460) | LS | 1 | $562.50 | $0.01 | $5,000.00 |
| 25 | Temp BR traf signals (70106500) | EACH | 1 | $7,812.50 | $6,000.00 | $1,500.00 |
| 26 | Temp rumble strips (70106700) | EACH | 6 | $937.50 | $1,000.00 | $1,000.00 |
| 27 | Changeable message SN (70107025) | CAL DAY | 28 | $102.80 | $75.00 | $785.00 |
| 28 | Uninter power sup ext (86200300) | EACH | 1 | $0.01 | $0.01 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.