IDOT contract 80B08 bid tabulation
Section 2025-1096-RS. Let by Illinois DOT on February 27, 2026, Dupage, District 01. 4 bids received; low bid $2,172,384 by Builders Paving, LLC.
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 90
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Builders Paving, LLC | $2,172,384 | Low |
| 2 | K-Five Construction Corporation | $2,269,967 | +4.0% |
| 3 | R. W. Dunteman Company | $2,391,900 | +10% |
| 4 | Plote Construction, Inc. | $2,487,725 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Builders Paving, LLC | 2. K-Five Construction Corporation | 3. R. W. Dunteman Company | 4. Plote Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Ped signal post 10 FT (X1400367) | EACH | 1 | $1,500.00 | $1,423.00 | $1,422.31 | $1,422.31 |
| 2 | Ped signal post 5 FT (X1400378) | EACH | 3 | $1,200.00 | $1,162.00 | $1,161.18 | $1,161.18 |
| 3 | Grading & shap SHLDRS (X2020110) | UNIT | 10 | $600.00 | $400.00 | $196.06 | $250.00 |
| 4 | PC conc sidewalk 5 SP (X4240430) | SF | 13 | $82.00 | $100.00 | $137.18 | $115.00 |
| 5 | CC&G RMVL repl < = 10 (X4400501) | LF | 100 | $100.00 | $60.00 | $116.72 | $90.00 |
| 6 | CC&G RMVL repl > 10FT (X4400503) | LF | 350 | $85.00 | $60.00 | $85.39 | $67.00 |
| 7 | SS cleaned 12 (X5537800) | LF | 341 | $2.00 | $1.00 | $1.00 | $1.00 |
| 8 | SS cleaned 36 (X5538600) | LF | 585 | $3.00 | $3.00 | $3.00 | $3.00 |
| 9 | FR & lids adjust SPL (X6030310) | EACH | 13 | $1,200.00 | $1,150.00 | $1,150.00 | $1,150.00 |
| 10 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $3,700.00 | $3,500.00 | $3,500.00 | $4,000.00 |
| 11 | Temp info signing (X7200061) | SF | 77 | $18.00 | $18.00 | $18.00 | $17.00 |
| 12 | Accessible ped signal (X8760200) | EACH | 6 | $3,050.00 | $3,043.00 | $3,043.01 | $3,043.01 |
| 13 | Conc FDN TY A 12D (X8780012) | LF | 16 | $400.00 | $385.00 | $384.54 | $384.54 |
| 14 | Construction layout (Z0013798) | LS | 1 | $1,600.00 | $10,000 | $1,500.00 | $1,500.00 |
| 15 | Drainage STR cleaned (Z0018500) | EACH | 15 | $350.00 | $330.00 | $330.00 | $330.00 |
| 16 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 2 | $750.00 | $720.00 | $720.00 | $720.00 |
| 17 | Earth excavation (20200100) | CY | 10 | $105.00 | $100.00 | $108.45 | $50.00 |
| 18 | Topsoil F & P 4 (21101615) | SY | 22 | $2.00 | $68.00 | $1.00 | $1.00 |
| 19 | Sodding salt tolerant (25200110) | SY | 22 | $75.00 | $202.00 | $65.00 | $65.00 |
| 20 | Supple watering (25200200) | UNIT | 1 | $1.00 | $50.00 | $1.00 | $1.00 |
| 21 | Bit matls tack CT (40600290) | LB | 33,063 | $0.01 | $0.01 | $0.65 | $0.01 |
| 22 | Long joint sealant (40600370) | LF | 29,120 | $2.70 | $2.50 | $2.58 | $2.60 |
| 23 | Mix CR JTS flangewys (40600400) | TON | 111 | $310.00 | $50.00 | $401.50 | $250.00 |
| 24 | Matl transfer device (40600405) | TON | 6,950 | $1.50 | $17.00 | $4.23 | $4.50 |
| 25 | HMA surf rem butt JT (40600982) | SY | 330 | $15.00 | $0.01 | $30.78 | $23.00 |
| 26 | HMA repl over patch (40601005) | TON | 321 | $98.00 | $50.00 | $194.96 | $250.00 |
| 27 | HMA SC IL-9.5 D N70 (40604062) | TON | 1,279 | $91.50 | $100.00 | $99.46 | $92.00 |
| 28 | P SC SMA 12.5 F N80 (40605036) | TON | 6,950 | $126.00 | $130.00 | $124.39 | $125.00 |
| 29 | Protective coat (42001300) | SY | 165 | $1.10 | $10.00 | $1.00 | $0.95 |
| 30 | PC conc sidewalk 5 (42400200) | SF | 280 | $28.00 | $15.00 | $10.93 | $10.37 |
| 31 | Detectable warnings (42400800) | SF | 80 | $50.00 | $60.00 | $38.41 | $26.00 |
| 32 | HMA surf rem 2 (44000157) | SY | 73,472 | $4.10 | $3.85 | $2.73 | $4.00 |
| 33 | Sidewalk rem (44000600) | SF | 294 | $8.00 | $5.00 | $4.11 | $1.75 |
| 34 | HMA RM OV patch 3 (44002212) | SY | 3,146 | $1.00 | $0.01 | $0.01 | $0.50 |
| 35 | CL D patch T1 9 (44201749) | SY | 184 | $30.00 | $25.00 | $126.53 | $105.00 |
| 36 | CL D patch T2 9 (44201753) | SY | 654 | $30.00 | $25.00 | $109.00 | $100.00 |
| 37 | CL D patch T3 9 (44201757) | SY | 1,103 | $30.00 | $25.00 | $95.66 | $95.00 |
| 38 | CL D patch T4 9 (44201759) | SY | 919 | $30.00 | $25.00 | $92.42 | $95.00 |
| 39 | Agg wedge SHLD type B (48102100) | TON | 981 | $36.00 | $10.00 | $48.69 | $25.00 |
| 40 | Man reconst (60257900) | EACH | 1 | $1,300.00 | $1,225.00 | $1,225.00 | $1,225.00 |
| 41 | FR & lids adjust (60300305) | EACH | 3 | $500.00 | $460.00 | $460.00 | $460.00 |
| 42 | Box cul to BE cleaned (60905305) | LF | 125 | $75.00 | $65.00 | $65.00 | $65.00 |
| 43 | Non SPL waste disposl (66900200) | CY | 10 | $125.00 | $100.00 | $106.51 | $97.00 |
| 44 | Soil disposal analy (66900530) | EACH | 2 | $1,450.00 | $1,450.00 | $865.00 | $1,450.00 |
| 45 | Reg sub P-const plan (66901001) | LS | 1 | $3,100.00 | $3,100.00 | $5,200.00 | $3,100.00 |
| 46 | Reg sub F con report (66901003) | LS | 1 | $1,200.00 | $1,200.00 | $500.00 | $1,200.00 |
| 47 | Reg sub mon (66901006) | CAL DAY | 2 | $680.00 | $680.00 | $715.00 | $680.00 |
| 48 | Mobilization (67100100) | LS | 1 | $130,000 | $136,000 | $143,500 | $149,000 |
| 49 | Traf cont-prot 701421 (70100310) | LS | 1 | $500.00 | $1.00 | $16,839 | $1.00 |
| 50 | Traf cont-prot 701422 (70100320) | LS | 1 | $500.00 | $1.00 | $1.00 | $1.00 |
| 51 | TR cont & prot 701601 (70102630) | LS | 1 | $30,000 | $76,900 | $8,000.00 | $121,000 |
| 52 | TR cont & prot 701701 (70102635) | LS | 1 | $500.00 | $1.00 | $1.00 | $1.00 |
| 53 | TR cont & prot 701801 (70102640) | LS | 1 | $500.00 | $1.00 | $9,850.00 | $1.00 |
| 54 | Night work zone light (70200100) | LS | 1 | $2,200.00 | $100.00 | $1,000.00 | $3,000.00 |
| 55 | Short term pavt mking (70300100) | LF | 13,581 | $0.80 | $0.01 | $1.28 | $0.01 |
| 56 | SHRT TRM pavt MK rem (70300150) | SF | 2,264 | $0.01 | $14.00 | $1.70 | $0.01 |
| 57 | Temp PVT MK LTR & sym paint (70300211) | SF | 535 | $0.01 | $1.30 | $1.50 | $1.30 |
| 58 | Temp PVT MK line 4 - paint (70300221) | LF | 33,671 | $0.01 | $0.01 | $0.27 | $0.30 |
| 59 | Temp PVT MK line 6 - paint (70300241) | LF | 2,942 | $0.01 | $0.50 | $0.40 | $0.50 |
| 60 | Temp PVT MK line 8 - paint (70300251) | LF | 793 | $0.01 | $0.80 | $0.55 | $0.80 |
| 61 | Temp PVT MK line 12 - paint (70300261) | LF | 2,046 | $0.01 | $1.00 | $0.85 | $1.00 |
| 62 | Temp PVT MK line 24 - paint (70300281) | LF | 459 | $0.01 | $2.00 | $1.50 | $2.00 |
| 63 | Temp PVT MK L4 T4 tape (70307120) | LF | 6,791 | $0.01 | $1.30 | $1.00 | $0.01 |
| 64 | THPL PVT MK LTR & sym (78000100) | SF | 535 | $5.25 | $5.25 | $5.25 | $5.25 |
| 65 | THPL PVT MK line 4 (78000200) | LF | 27,047 | $0.82 | $0.82 | $0.76 | $0.82 |
| 66 | THPL PVT MK line 6 (78000400) | LF | 2,942 | $1.25 | $1.25 | $1.20 | $1.25 |
| 67 | THPL PVT MK line 8 (78000500) | LF | 793 | $1.75 | $1.75 | $1.65 | $1.75 |
| 68 | THPL PVT MK line 12 (78000600) | LF | 2,046 | $2.25 | $3.75 | $2.45 | $2.25 |
| 69 | THPL PVT MK line 24 (78000650) | LF | 459 | $5.25 | $7.50 | $5.25 | $5.25 |
| 70 | Pref PL PM TD STD L4 (78004620) | LF | 6,624 | $5.00 | $5.00 | $4.55 | $5.00 |
| 71 | GRV RCSD PVT MRKG 5 (78011025) | LF | 6,624 | $0.50 | $0.50 | $0.75 | $0.50 |
| 72 | Raised refl pavt MKR (78100100) | EACH | 669 | $35.00 | $34.00 | $47.00 | $34.00 |
| 73 | Raised ref PVT MK rem (78300200) | EACH | 699 | $20.00 | $10.00 | $14.30 | $17.00 |
| 74 | Undrgrd C galvs 2 (81028200) | LF | 193 | $82.00 | $81.80 | $81.80 | $81.80 |
| 75 | HD handhole (81400200) | EACH | 2 | $6,400.00 | $6,300.00 | $6,295.81 | $6,295.81 |
| 76 | Main EX TR sig instal (85000200) | EACH | 2 | $2,200.00 | $2,142.00 | $2,142.13 | $2,142.13 |
| 77 | Elcbl C signal 14 2C (87301215) | LF | 843 | $2.30 | $2.27 | $2.27 | $2.27 |
| 78 | Elcbl C signal 14 3C (87301225) | LF | 351 | $2.60 | $2.48 | $2.48 | $2.48 |
| 79 | Elcbl C lead 14 1PR (87301305) | LF | 4,040 | $2.60 | $2.48 | $2.48 | $2.48 |
| 80 | Elcbl C egrdc 6 1C (87301900) | LF | 111 | $3.20 | $3.10 | $3.10 | $3.10 |
| 81 | Drill EX foundation (87900100) | EACH | 3 | $500.00 | $483.00 | $482.24 | $482.24 |
| 82 | Drill EX HD handhole (87900205) | EACH | 3 | $500.00 | $483.00 | $482.24 | $482.24 |
| 83 | Inductive loop detect (88500100) | EACH | 8 | $230.00 | $221.00 | $220.94 | $220.94 |
| 84 | Det loop T1 (88600100) | LF | 2,195 | $28.00 | $27.27 | $27.27 | $27.27 |
| 85 | Reloc EX ped sig head (89500200) | EACH | 1 | $400.00 | $350.00 | $346.51 | $346.51 |
| 86 | Rem elcbl FR con (89502300) | LF | 1,267 | $1.80 | $1.70 | $1.70 | $1.70 |
| 87 | Rem & RE elcbl FR con (89502350) | LF | 21 | $1.80 | $1.70 | $1.70 | $1.70 |
| 88 | Remov EX TS equip (89502375) | EACH | 2 | $150.00 | $144.35 | $144.35 | $144.35 |
| 89 | Remov EX handhole (89502380) | EACH | 2 | $1,500.00 | $1,425.00 | $1,424.60 | $1,424.60 |
| 90 | Remov EX conc FDN (89502385) | EACH | 1 | $560.00 | $503.00 | $502.22 | $502.22 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.