IDOT contract 80B09 bid tabulation

Section 2025-1097-RS. Let by Illinois DOT on April 24, 2026, Cook, District 01. 3 bids received; low bid $4,440,808 by Builders Paving, LLC.

Owner
Illinois DOT
Letting
24 APR 2026
Pay items
114
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Builders Paving, LLC$4,440,808Low
2R. W. Dunteman Company$4,779,100+8.0%
3Plote Construction, Inc.$4,891,091+10%
IDOT contract 80B09: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Builders Paving, LLC2. R. W. Dunteman Company3. Plote Construction, Inc.
1Constructn layout SPL (X0320050)LS1$8,600.00$8,600.00$10,000
2Rem & rein bric paver (X0327611)SF1,029$18.75$25.00$25.00
3Ped signal post 5 FT (X1400378)EACH7$1,108.10$1,108.10$1,108.10
4Grading & shap SHLDRS (X2020110)UNIT135.10$35.00$75.75$131.00
5Temporary ramp SPL (X4060995)SY226$55.00$15.25$30.00
6PCC surf rem var DP (X4400100)SY3,007$2.75$4.60$9.00
7Curb rem & replacemt < = 10FT (X4400221)LF119$75.00$85.00$51.00
8Curb rem&repl > 10FT (X4400223)LF1,047$56.00$55.35$51.00
9CC&G RMVL repl < = 10 (X4400501)LF64$75.00$101.75$85.00
10CC&G RMVL repl > 10FT (X4400503)LF1,165$61.00$81.00$62.00
11SS cleaned 12 (X5537800)LF870$4.00$2.00$2.00
12FR & lids adjust SPL (X6030310)EACH12$1,100.00$1,150.00$1,150.00
13Engrs FLD ofc TY A D1 (X6700407)CAL MO12$3,250.00$3,500.00$3,900.00
14Temp info signing (X7200061)SF438.90$16.00$20.00$20.00
15Accessible ped signal (X8760200)EACH16$1,700.35$1,700.35$1,700.35
16Conc FDN TY A 12D (X8780012)LF28$346.96$346.96$346.96
17Det loop repl (X8860105)LF152$24.91$24.91$24.91
18Drainage STR cleaned (Z0018500)EACH58$375.00$325.00$325.00
19RE-optimize TR sig sys 1 (Z0033044)EACH2$792.00$792.00$792.00
20RR prot liability ins (Z0048665)LS1$10,000$4,000.00$5,000.00
21Trainees (Z0076600)HR500$0.80$0.80$0.80
22Trainees TPG (Z0076604)HR500$15.00$15.00$15.00
23Earth excavation (20200100)CY80$50.00$75.25$128.00
24Trench backfill (20800150)CY16$59.00$23.00$23.00
25Topsoil F & P 4 (21101615)SY494$0.10$10.00$6.00
26Sodding salt tolerant (25200110)SY494$25.25$23.00$25.00
27Supple watering (25200200)UNIT4.90$30.00$40.00$0.01
28Stone riprap CL A4 (28100107)SY22$99.00$325.00$325.00
29HMA base cse 8 (35501316)SY120$70.00$66.65$140.00
30Bit matls tack CT (40600290)LB74,011$0.01$1.00$0.01
31Long joint sealant (40600370)LF44,728$3.10$3.00$3.00
32Mix CR JTS flangewys (40600400)TON171.10$200.00$363.00$125.00
33Matl transfer device (40600405)TON11,620$0.01$4.35$5.00
34HMA surf rem butt JT (40600982)SY722$5.00$22.50$28.00
35HMA repl over patch (40601005)TON272$10.00$132.00$150.00
36P HMA BC IL-4.75 N50 (40603200)TON5,381$90.00$105.75$125.00
37HMA SC IL-9.5 D N50 (40604060)TON14$300.00$196.65$300.00
38HMA SC IL-9.5 D N70 (40604062)TON1,488$100.00$99.40$110.00
39P SC SMA 12.5 F N80 (40605036)TON11,620$118.00$129.25$142.00
40Welded wire reinf (42000060)SY45$34.00$23.85$36.00
41Protective coat (42001300)SY1,172$1.00$1.15$0.01
42PCC driveway pavt 8 (42300400)SY40$110.00$139.00$135.00
43PC conc sidewalk 5 (42400200)SF4,721$9.50$8.50$10.00
44Detectable warnings (42400800)SF230$38.00$38.40$25.00
45HMA surf rem 2 (44000157)SY13,285$3.25$3.65$4.40
46HMA surf rem 3 (44000161)SY100,788$3.75$4.85$4.90
47Drive pavement rem (44000200)SY160$30.00$31.65$17.00
48Sidewalk rem (44000600)SF4,708$2.50$2.00$2.50
49HMA RM OV patch 2 1/2 (44002210)SY1,937$28.00$8.30$12.00
50CL B patch T4 10 (44200976)SY45$123.00$297.50$227.00
51Dowel bars 1 1/2 (44201299)EACH20$15.00$41.35$25.00
52CL D patch T1 10 (44201761)SY3$233.00$435.00$140.00
53CL D patch T2 10 (44201765)SY1,738$133.00$112.00$130.00
54CL D patch T3 10 (44201769)SY36$132.00$109.00$125.00
55CL D patch T4 10 (44201771)SY160$107.00$98.00$120.00
56Saw cuts (44213200)LF138$4.00$3.21$6.00
57Tie bars 3/4 (44213204)EACH34$10.00$28.25$17.00
58Agg wedge SHLD type B (48102100)TON213.40$45.00$43.00$80.00
59Conc rem (50102400)CY1$500.00$1,110.00$1,400.00
60Pipe culvert remov (50105220)LF80$25.00$10.00$10.00
61P cul CL A 1 15 (542A0220)LF80$115.00$125.00$125.00
62PRC flar end sec 15 (54213660)EACH2$1,950.00$1,650.00$1,650.00
63CB reconst (60252800)EACH1$1,800.00$1,150.00$1,150.00
64Valve box adj (60266600)EACH6$300.00$350.00$350.00
65FR & grates adjust (60300105)EACH7$525.00$450.00$450.00
66FR & lids adjust (60300305)EACH5$525.00$450.00$450.00
67FR & grates T24 (60404950)EACH1$475.00$485.00$485.00
68FR & lids T1 OL (60406000)EACH1$450.00$460.00$460.00
69FR & lids T1 CL (60406100)EACH4$450.00$460.00$460.00
70Class SI conc outlet (60600095)CY1.41$900.00$669.00$1,636.33
71Non SPL waste disposl (66900200)CY80$80.00$101.00$100.00
72Soil disposal analy (66900530)EACH2$1,450.00$1,450.00$1,450.00
73Reg sub P-const plan (66901001)LS1$3,100.00$3,100.00$3,100.00
74Reg sub F con report (66901003)LS1$1,200.00$1,200.00$1,200.00
75Reg sub mon (66901006)CAL DAY16$680.00$680.00$680.00
76Mobilization (67100100)LS1$355,405$278,626$293,600
77TR cont & prot 701601 (70102630)LS1$315,000$53,200$92,000
78TR cont & prot 701701 (70102635)LS1$500.00$120,000$1,000.00
79TR cont & prot 701801 (70102640)LS1$500.00$15,000$1,000.00
80Night work zone light (70200100)LS1$0.01$5,500.00$5,700.00
81Short term pavt mking (70300100)LF78,559$0.01$0.01$0.01
82SHRT TRM pavt MK rem (70300150)SF6,547$0.10$1.50$0.01
83Temp PVT MK LTR & sym paint (70300211)SF4,252$0.01$2.00$0.01
84Temp PVT MK line 4 - paint (70300221)LF85,762$0.01$0.25$0.01
85Temp PVT MK line 6 - paint (70300241)LF13,625$0.01$0.50$0.01
86Temp PVT MK line 8 - paint (70300251)LF800$0.01$1.00$0.01
87Temp PVT MK line 12 - paint (70300261)LF10,166$0.01$1.00$0.01
88Temp PVT MK line 24 - paint (70300281)LF2,236$0.01$2.00$0.01
89Temp PVT MK L4 T4 tape (70307120)LF19,640$0.01$0.01$0.01
90Terminal marker - DA (72501000)EACH2$400.00$100.00$150.00
91THPL PVT MK LTR & sym (78000100)SF2,126$5.15$4.50$4.50
92THPL PVT MK line 4 (78000200)LF33,821$0.72$0.60$0.60
93THPL PVT MK line 6 (78000400)LF6,812$1.32$1.10$1.10
94THPL PVT MK line 8 (78000500)LF400$1.50$2.20$2.20
95THPL PVT MK line 12 (78000600)LF5,083$1.85$2.25$2.25
96THPL PVT MK line 24 (78000650)LF1,118$5.15$4.50$4.50
97Pref PL PM TD STD L4 (78004620)LF9,060$5.00$4.15$4.15
98Mod ureth PM line 12 (78009012)LF718$5.60$4.00$4.00
99Mod ureth PM line 24 (78009024)LF160$10.60$8.00$8.00
100GRV RCSD PVT MRKG 5 (78011025)LF9,060$0.50$0.85$0.85
101Raised refl pavt MKR (78100100)EACH1,065$35.00$37.00$37.00
102Raised ref PVT MK rem (78300200)EACH1,065$10.00$13.85$17.00
103PVT MKG rem WTR blast (78300202)SF437$11.50$2.50$2.50
104Undrgrd C galvs 2 (81028200)LF346$66.96$66.96$66.96
105HD handhole (81400200)EACH3$5,916.10$5,916.10$5,916.10
106Main EX TR sig instal (85000200)EACH4$1,776.52$1,776.52$1,776.52
107Elcbl C signal 14 2C (87301215)LF1,580$4.46$4.46$4.46
108Elcbl C lead 14 1PR (87301305)LF2,707$4.65$4.65$4.65
109Elcbl C egrdc 6 1C (87301900)LF117$5.29$5.29$5.29
110Drill EX handhole (87900200)EACH10$439.14$439.14$439.14
111Det loop T1 (88600100)LF3,105$24.91$24.91$24.91
112Rem elcbl FR con (89502300)LF1,592$0.14$0.14$0.14
113Remov EX TS equip (89502375)EACH2$236.95$236.95$236.95
114Remov EX handhole (89502380)EACH3$1,343.90$1,343.90$1,343.90
IDOT contract 80B09: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy