IDOT contract 80B09 bid tabulation
Section 2025-1097-RS. Let by Illinois DOT on April 24, 2026, Cook, District 01. 3 bids received; low bid $4,440,808 by Builders Paving, LLC.
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 114
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Builders Paving, LLC | $4,440,808 | Low |
| 2 | R. W. Dunteman Company | $4,779,100 | +8.0% |
| 3 | Plote Construction, Inc. | $4,891,091 | +10% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Builders Paving, LLC | 2. R. W. Dunteman Company | 3. Plote Construction, Inc. |
|---|---|---|---|---|---|---|
| 1 | Constructn layout SPL (X0320050) | LS | 1 | $8,600.00 | $8,600.00 | $10,000 |
| 2 | Rem & rein bric paver (X0327611) | SF | 1,029 | $18.75 | $25.00 | $25.00 |
| 3 | Ped signal post 5 FT (X1400378) | EACH | 7 | $1,108.10 | $1,108.10 | $1,108.10 |
| 4 | Grading & shap SHLDRS (X2020110) | UNIT | 135.10 | $35.00 | $75.75 | $131.00 |
| 5 | Temporary ramp SPL (X4060995) | SY | 226 | $55.00 | $15.25 | $30.00 |
| 6 | PCC surf rem var DP (X4400100) | SY | 3,007 | $2.75 | $4.60 | $9.00 |
| 7 | Curb rem & replacemt < = 10FT (X4400221) | LF | 119 | $75.00 | $85.00 | $51.00 |
| 8 | Curb rem&repl > 10FT (X4400223) | LF | 1,047 | $56.00 | $55.35 | $51.00 |
| 9 | CC&G RMVL repl < = 10 (X4400501) | LF | 64 | $75.00 | $101.75 | $85.00 |
| 10 | CC&G RMVL repl > 10FT (X4400503) | LF | 1,165 | $61.00 | $81.00 | $62.00 |
| 11 | SS cleaned 12 (X5537800) | LF | 870 | $4.00 | $2.00 | $2.00 |
| 12 | FR & lids adjust SPL (X6030310) | EACH | 12 | $1,100.00 | $1,150.00 | $1,150.00 |
| 13 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $3,250.00 | $3,500.00 | $3,900.00 |
| 14 | Temp info signing (X7200061) | SF | 438.90 | $16.00 | $20.00 | $20.00 |
| 15 | Accessible ped signal (X8760200) | EACH | 16 | $1,700.35 | $1,700.35 | $1,700.35 |
| 16 | Conc FDN TY A 12D (X8780012) | LF | 28 | $346.96 | $346.96 | $346.96 |
| 17 | Det loop repl (X8860105) | LF | 152 | $24.91 | $24.91 | $24.91 |
| 18 | Drainage STR cleaned (Z0018500) | EACH | 58 | $375.00 | $325.00 | $325.00 |
| 19 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 2 | $792.00 | $792.00 | $792.00 |
| 20 | RR prot liability ins (Z0048665) | LS | 1 | $10,000 | $4,000.00 | $5,000.00 |
| 21 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 |
| 22 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 |
| 23 | Earth excavation (20200100) | CY | 80 | $50.00 | $75.25 | $128.00 |
| 24 | Trench backfill (20800150) | CY | 16 | $59.00 | $23.00 | $23.00 |
| 25 | Topsoil F & P 4 (21101615) | SY | 494 | $0.10 | $10.00 | $6.00 |
| 26 | Sodding salt tolerant (25200110) | SY | 494 | $25.25 | $23.00 | $25.00 |
| 27 | Supple watering (25200200) | UNIT | 4.90 | $30.00 | $40.00 | $0.01 |
| 28 | Stone riprap CL A4 (28100107) | SY | 22 | $99.00 | $325.00 | $325.00 |
| 29 | HMA base cse 8 (35501316) | SY | 120 | $70.00 | $66.65 | $140.00 |
| 30 | Bit matls tack CT (40600290) | LB | 74,011 | $0.01 | $1.00 | $0.01 |
| 31 | Long joint sealant (40600370) | LF | 44,728 | $3.10 | $3.00 | $3.00 |
| 32 | Mix CR JTS flangewys (40600400) | TON | 171.10 | $200.00 | $363.00 | $125.00 |
| 33 | Matl transfer device (40600405) | TON | 11,620 | $0.01 | $4.35 | $5.00 |
| 34 | HMA surf rem butt JT (40600982) | SY | 722 | $5.00 | $22.50 | $28.00 |
| 35 | HMA repl over patch (40601005) | TON | 272 | $10.00 | $132.00 | $150.00 |
| 36 | P HMA BC IL-4.75 N50 (40603200) | TON | 5,381 | $90.00 | $105.75 | $125.00 |
| 37 | HMA SC IL-9.5 D N50 (40604060) | TON | 14 | $300.00 | $196.65 | $300.00 |
| 38 | HMA SC IL-9.5 D N70 (40604062) | TON | 1,488 | $100.00 | $99.40 | $110.00 |
| 39 | P SC SMA 12.5 F N80 (40605036) | TON | 11,620 | $118.00 | $129.25 | $142.00 |
| 40 | Welded wire reinf (42000060) | SY | 45 | $34.00 | $23.85 | $36.00 |
| 41 | Protective coat (42001300) | SY | 1,172 | $1.00 | $1.15 | $0.01 |
| 42 | PCC driveway pavt 8 (42300400) | SY | 40 | $110.00 | $139.00 | $135.00 |
| 43 | PC conc sidewalk 5 (42400200) | SF | 4,721 | $9.50 | $8.50 | $10.00 |
| 44 | Detectable warnings (42400800) | SF | 230 | $38.00 | $38.40 | $25.00 |
| 45 | HMA surf rem 2 (44000157) | SY | 13,285 | $3.25 | $3.65 | $4.40 |
| 46 | HMA surf rem 3 (44000161) | SY | 100,788 | $3.75 | $4.85 | $4.90 |
| 47 | Drive pavement rem (44000200) | SY | 160 | $30.00 | $31.65 | $17.00 |
| 48 | Sidewalk rem (44000600) | SF | 4,708 | $2.50 | $2.00 | $2.50 |
| 49 | HMA RM OV patch 2 1/2 (44002210) | SY | 1,937 | $28.00 | $8.30 | $12.00 |
| 50 | CL B patch T4 10 (44200976) | SY | 45 | $123.00 | $297.50 | $227.00 |
| 51 | Dowel bars 1 1/2 (44201299) | EACH | 20 | $15.00 | $41.35 | $25.00 |
| 52 | CL D patch T1 10 (44201761) | SY | 3 | $233.00 | $435.00 | $140.00 |
| 53 | CL D patch T2 10 (44201765) | SY | 1,738 | $133.00 | $112.00 | $130.00 |
| 54 | CL D patch T3 10 (44201769) | SY | 36 | $132.00 | $109.00 | $125.00 |
| 55 | CL D patch T4 10 (44201771) | SY | 160 | $107.00 | $98.00 | $120.00 |
| 56 | Saw cuts (44213200) | LF | 138 | $4.00 | $3.21 | $6.00 |
| 57 | Tie bars 3/4 (44213204) | EACH | 34 | $10.00 | $28.25 | $17.00 |
| 58 | Agg wedge SHLD type B (48102100) | TON | 213.40 | $45.00 | $43.00 | $80.00 |
| 59 | Conc rem (50102400) | CY | 1 | $500.00 | $1,110.00 | $1,400.00 |
| 60 | Pipe culvert remov (50105220) | LF | 80 | $25.00 | $10.00 | $10.00 |
| 61 | P cul CL A 1 15 (542A0220) | LF | 80 | $115.00 | $125.00 | $125.00 |
| 62 | PRC flar end sec 15 (54213660) | EACH | 2 | $1,950.00 | $1,650.00 | $1,650.00 |
| 63 | CB reconst (60252800) | EACH | 1 | $1,800.00 | $1,150.00 | $1,150.00 |
| 64 | Valve box adj (60266600) | EACH | 6 | $300.00 | $350.00 | $350.00 |
| 65 | FR & grates adjust (60300105) | EACH | 7 | $525.00 | $450.00 | $450.00 |
| 66 | FR & lids adjust (60300305) | EACH | 5 | $525.00 | $450.00 | $450.00 |
| 67 | FR & grates T24 (60404950) | EACH | 1 | $475.00 | $485.00 | $485.00 |
| 68 | FR & lids T1 OL (60406000) | EACH | 1 | $450.00 | $460.00 | $460.00 |
| 69 | FR & lids T1 CL (60406100) | EACH | 4 | $450.00 | $460.00 | $460.00 |
| 70 | Class SI conc outlet (60600095) | CY | 1.41 | $900.00 | $669.00 | $1,636.33 |
| 71 | Non SPL waste disposl (66900200) | CY | 80 | $80.00 | $101.00 | $100.00 |
| 72 | Soil disposal analy (66900530) | EACH | 2 | $1,450.00 | $1,450.00 | $1,450.00 |
| 73 | Reg sub P-const plan (66901001) | LS | 1 | $3,100.00 | $3,100.00 | $3,100.00 |
| 74 | Reg sub F con report (66901003) | LS | 1 | $1,200.00 | $1,200.00 | $1,200.00 |
| 75 | Reg sub mon (66901006) | CAL DAY | 16 | $680.00 | $680.00 | $680.00 |
| 76 | Mobilization (67100100) | LS | 1 | $355,405 | $278,626 | $293,600 |
| 77 | TR cont & prot 701601 (70102630) | LS | 1 | $315,000 | $53,200 | $92,000 |
| 78 | TR cont & prot 701701 (70102635) | LS | 1 | $500.00 | $120,000 | $1,000.00 |
| 79 | TR cont & prot 701801 (70102640) | LS | 1 | $500.00 | $15,000 | $1,000.00 |
| 80 | Night work zone light (70200100) | LS | 1 | $0.01 | $5,500.00 | $5,700.00 |
| 81 | Short term pavt mking (70300100) | LF | 78,559 | $0.01 | $0.01 | $0.01 |
| 82 | SHRT TRM pavt MK rem (70300150) | SF | 6,547 | $0.10 | $1.50 | $0.01 |
| 83 | Temp PVT MK LTR & sym paint (70300211) | SF | 4,252 | $0.01 | $2.00 | $0.01 |
| 84 | Temp PVT MK line 4 - paint (70300221) | LF | 85,762 | $0.01 | $0.25 | $0.01 |
| 85 | Temp PVT MK line 6 - paint (70300241) | LF | 13,625 | $0.01 | $0.50 | $0.01 |
| 86 | Temp PVT MK line 8 - paint (70300251) | LF | 800 | $0.01 | $1.00 | $0.01 |
| 87 | Temp PVT MK line 12 - paint (70300261) | LF | 10,166 | $0.01 | $1.00 | $0.01 |
| 88 | Temp PVT MK line 24 - paint (70300281) | LF | 2,236 | $0.01 | $2.00 | $0.01 |
| 89 | Temp PVT MK L4 T4 tape (70307120) | LF | 19,640 | $0.01 | $0.01 | $0.01 |
| 90 | Terminal marker - DA (72501000) | EACH | 2 | $400.00 | $100.00 | $150.00 |
| 91 | THPL PVT MK LTR & sym (78000100) | SF | 2,126 | $5.15 | $4.50 | $4.50 |
| 92 | THPL PVT MK line 4 (78000200) | LF | 33,821 | $0.72 | $0.60 | $0.60 |
| 93 | THPL PVT MK line 6 (78000400) | LF | 6,812 | $1.32 | $1.10 | $1.10 |
| 94 | THPL PVT MK line 8 (78000500) | LF | 400 | $1.50 | $2.20 | $2.20 |
| 95 | THPL PVT MK line 12 (78000600) | LF | 5,083 | $1.85 | $2.25 | $2.25 |
| 96 | THPL PVT MK line 24 (78000650) | LF | 1,118 | $5.15 | $4.50 | $4.50 |
| 97 | Pref PL PM TD STD L4 (78004620) | LF | 9,060 | $5.00 | $4.15 | $4.15 |
| 98 | Mod ureth PM line 12 (78009012) | LF | 718 | $5.60 | $4.00 | $4.00 |
| 99 | Mod ureth PM line 24 (78009024) | LF | 160 | $10.60 | $8.00 | $8.00 |
| 100 | GRV RCSD PVT MRKG 5 (78011025) | LF | 9,060 | $0.50 | $0.85 | $0.85 |
| 101 | Raised refl pavt MKR (78100100) | EACH | 1,065 | $35.00 | $37.00 | $37.00 |
| 102 | Raised ref PVT MK rem (78300200) | EACH | 1,065 | $10.00 | $13.85 | $17.00 |
| 103 | PVT MKG rem WTR blast (78300202) | SF | 437 | $11.50 | $2.50 | $2.50 |
| 104 | Undrgrd C galvs 2 (81028200) | LF | 346 | $66.96 | $66.96 | $66.96 |
| 105 | HD handhole (81400200) | EACH | 3 | $5,916.10 | $5,916.10 | $5,916.10 |
| 106 | Main EX TR sig instal (85000200) | EACH | 4 | $1,776.52 | $1,776.52 | $1,776.52 |
| 107 | Elcbl C signal 14 2C (87301215) | LF | 1,580 | $4.46 | $4.46 | $4.46 |
| 108 | Elcbl C lead 14 1PR (87301305) | LF | 2,707 | $4.65 | $4.65 | $4.65 |
| 109 | Elcbl C egrdc 6 1C (87301900) | LF | 117 | $5.29 | $5.29 | $5.29 |
| 110 | Drill EX handhole (87900200) | EACH | 10 | $439.14 | $439.14 | $439.14 |
| 111 | Det loop T1 (88600100) | LF | 3,105 | $24.91 | $24.91 | $24.91 |
| 112 | Rem elcbl FR con (89502300) | LF | 1,592 | $0.14 | $0.14 | $0.14 |
| 113 | Remov EX TS equip (89502375) | EACH | 2 | $236.95 | $236.95 | $236.95 |
| 114 | Remov EX handhole (89502380) | EACH | 3 | $1,343.90 | $1,343.90 | $1,343.90 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.