IDOT contract 80B31 bid tabulation
Section 2025-2012-RS. Let by Illinois DOT on April 24, 2026, Will, District 01. 4 bids received; low bid $2,127,428 by P. T. Ferro Construction Co..
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 69
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | P. T. Ferro Construction Co. | $2,127,428 | Low |
| 2 | Iroquois Paving Corporation | $2,144,605 | +1.0% |
| 3 | Gallagher Asphalt Corporation | $2,262,111 | +6.0% |
| 4 | Austin Tyler Construction, Inc. | $2,765,709 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. P. T. Ferro Construction Co. | 2. Iroquois Paving Corporation | 3. Gallagher Asphalt Corporation | 4. Austin Tyler Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Rem & rein bric paver (X0327611) | SF | 27 | $35.00 | $38.80 | $100.00 | $113.00 |
| 2 | Grading & shap SHLDRS (X2020110) | UNIT | 69 | $0.01 | $35.50 | $170.00 | $170.00 |
| 3 | Temp access- priv ent (X4021000) | EACH | 3 | $0.01 | $545.00 | $535.00 | $880.00 |
| 4 | Temp access- com ent (X4022000) | EACH | 15 | $0.01 | $545.00 | $950.00 | $1,293.00 |
| 5 | Temporary ramp SPL (X4060995) | SY | 213 | $0.01 | $78.00 | $30.00 | $17.50 |
| 6 | CC&G RMVL repl > 10FT (X4400503) | LF | 85 | $100.00 | $110.00 | $98.00 | $71.50 |
| 7 | Centerln rum strip 16 (X6420114) | LF | 10,265 | $0.60 | $0.63 | $0.55 | $1.15 |
| 8 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $1.00 | $2,950.00 | $500.00 | $3,390.00 |
| 9 | Temp info signing (X7200061) | SF | 565 | $15.00 | $15.10 | $15.00 | $34.00 |
| 10 | HS THPL PM LN 4 (X7800815) | LF | 2,598 | $2.95 | $1.80 | $1.75 | $2.75 |
| 11 | Construction layout (Z0013798) | LS | 1 | $25,000 | $12,450 | $8,600.00 | $11,812 |
| 12 | Earth excavation (20200100) | CY | 7,392 | $0.01 | $0.01 | $0.01 | $48.00 |
| 13 | Rem & disp uns matl (20201200) | CY | 687 | $25.00 | $41.75 | $20.00 | $65.00 |
| 14 | Geotech fab F/GR stab (21001000) | SY | 2,061 | $2.50 | $2.75 | $1.95 | $3.00 |
| 15 | Topsoil F & P 4 (21101615) | SY | 50 | $50.00 | $65.00 | $50.00 | $56.50 |
| 16 | Grading & shap ditch (21400100) | LF | 200 | $25.00 | $57.50 | $10.50 | $23.75 |
| 17 | Agg subgrade improve (30300001) | CY | 687 | $40.00 | $68.00 | $20.00 | $100.00 |
| 18 | Agg subgrade impr 12 (30300112) | SY | 8,245 | $40.00 | $56.00 | $51.30 | $40.00 |
| 19 | Bit matls PR CT (40600275) | LB | 18,551 | $0.01 | $0.01 | $0.01 | $1.40 |
| 20 | Bit matls tack CT (40600290) | LB | 24,221 | $0.01 | $0.01 | $0.01 | $1.40 |
| 21 | Long joint sealant (40600370) | LF | 10,506 | $3.25 | $3.20 | $3.15 | $3.50 |
| 22 | Mix CR JTS flangewys (40600400) | TON | 37 | $0.01 | $0.01 | $0.01 | $355.00 |
| 23 | HMA surf rem butt JT (40600982) | SY | 312 | $0.01 | $13.25 | $0.01 | $23.00 |
| 24 | HMA BC IL-9.5 N70 (40602985) | TON | 2,711 | $87.00 | $85.00 | $86.00 | $82.00 |
| 25 | P HMA BC IL-4.75 N50 (40603200) | TON | 491 | $115.00 | $121.00 | $130.50 | $115.00 |
| 26 | HMA SC IL-9.5 D N70 (40604062) | TON | 3,247 | $87.00 | $80.00 | $97.00 | $82.25 |
| 27 | Protective coat (42001300) | SY | 106 | $0.01 | $0.01 | $1.10 | $3.25 |
| 28 | PC conc sidewalk 5 (42400200) | SF | 784 | $12.50 | $9.75 | $9.10 | $12.00 |
| 29 | Detectable warnings (42400800) | SF | 40 | $26.00 | $24.50 | $20.50 | $28.25 |
| 30 | Pavement rem (44000100) | SY | 1,700 | $15.00 | $0.01 | $18.75 | $29.00 |
| 31 | HMA surf rem 3 3/4 (44000164) | SY | 24,200 | $3.00 | $3.40 | $4.00 | $5.25 |
| 32 | Sidewalk rem (44000600) | SF | 784 | $3.00 | $3.80 | $4.85 | $2.75 |
| 33 | Paved SHLD removal (44004250) | SY | 832 | $15.00 | $0.01 | $20.40 | $25.50 |
| 34 | CL D patch T1 4 (44201690) | SY | 8 | $110.00 | $275.00 | $149.00 | $176.00 |
| 35 | CL D patch T2 4 (44201692) | SY | 10 | $100.00 | $265.00 | $138.00 | $156.00 |
| 36 | CL D patch T1 10 (44201761) | SY | 10 | $175.00 | $175.00 | $109.00 | $309.00 |
| 37 | CL D patch T2 10 (44201765) | SY | 150 | $125.00 | $155.00 | $109.00 | $280.00 |
| 38 | CL D patch T3 10 (44201769) | SY | 250 | $110.00 | $150.00 | $109.00 | $239.00 |
| 39 | CL D patch T4 10 (44201771) | SY | 250 | $100.00 | $141.00 | $109.00 | $121.00 |
| 40 | Agg wedge SHLD type B (48102100) | TON | 452 | $35.00 | $44.00 | $50.00 | $52.75 |
| 41 | HMA shoulders 10 (48203037) | SY | 8,245 | $65.00 | $46.00 | $65.00 | $52.50 |
| 42 | Inlets adjust (60260100) | EACH | 2 | $750.00 | $285.00 | $480.00 | $1,550.00 |
| 43 | SPBGR TY A 6FT posts (63000001) | LF | 120 | $41.00 | $41.25 | $41.00 | $57.50 |
| 44 | TR bar TRM T1 SPL tan (63100167) | EACH | 4 | $4,200.00 | $4,225.00 | $4,200.00 | $4,750.00 |
| 45 | Guardrail remov (63200310) | LF | 120 | $15.00 | $12.85 | $15.00 | $21.00 |
| 46 | Shoulder rum strip 8 (64200108) | LF | 20,488 | $0.40 | $0.53 | $0.33 | $0.75 |
| 47 | Non SPL waste disposl (66900200) | CY | 1,380 | $75.00 | $83.00 | $67.00 | $76.00 |
| 48 | Soil disposal analy (66900530) | EACH | 3 | $1,450.00 | $1,460.00 | $1,450.00 | $904.00 |
| 49 | Reg sub P-const plan (66901001) | LS | 1 | $3,100.00 | $3,115.00 | $3,100.00 | $6,215.00 |
| 50 | Reg sub F con report (66901003) | LS | 1 | $1,200.00 | $1,210.00 | $1,200.00 | $565.00 |
| 51 | Reg sub mon (66901006) | CAL DAY | 15 | $680.00 | $685.00 | $680.00 | $836.00 |
| 52 | Mobilization (67100100) | LS | 1 | $100,000 | $68,000 | $90,500 | $2,193.00 |
| 53 | Traf cont-prot 701201 (70100450) | LS | 1 | $2,072.00 | $2,085.00 | $2,072.00 | $565.00 |
| 54 | Traf cont-prot 701306 (70100460) | LS | 1 | $2,072.00 | $2,085.00 | $2,072.00 | $1,130.00 |
| 55 | Traf cont-prot 701326 (70100500) | LS | 1 | $2,072.00 | $2,085.00 | $2,072.00 | $1,130.00 |
| 56 | Traf cont-prot 701336 (70100600) | LS | 1 | $2,072.00 | $2,085.00 | $2,072.00 | $1,130.00 |
| 57 | TR cont & prot 701501 (70102620) | LS | 1 | $2,072.00 | $2,085.00 | $2,072.00 | $1,695.00 |
| 58 | TR cont & prot 701801 (70102640) | LS | 1 | $2,072.00 | $2,085.00 | $2,072.00 | $2,260.00 |
| 59 | TR cont surveillance (70103815) | CAL DAY | 25 | $200.00 | $200.00 | $8.00 | $1,356.00 |
| 60 | Short term pavt mking (70300100) | LF | 11,998 | $0.01 | $0.01 | $0.01 | $1.35 |
| 61 | SHRT TRM pavt MK rem (70300150) | SF | 19,997 | $0.01 | $0.01 | $0.01 | $2.00 |
| 62 | Temp PVT MK line 4 - paint (70300221) | LF | 65,030 | $0.01 | $0.01 | $0.01 | $0.30 |
| 63 | Temp PVT MK line 24 - paint (70300281) | LF | 102 | $0.01 | $0.01 | $0.01 | $6.00 |
| 64 | Temp PVT MK L4 T4 tape (70307120) | LF | 2,999 | $0.01 | $0.01 | $0.01 | $1.50 |
| 65 | Sign panel T2 (72000200) | SF | 185 | $45.00 | $45.50 | $45.00 | $36.00 |
| 66 | THPL PVT MK line 4 (78000200) | LF | 32,515 | $0.80 | $0.75 | $0.75 | $0.80 |
| 67 | THPL PVT MK line 24 (78000650) | LF | 51 | $16.00 | $6.05 | $6.00 | $11.30 |
| 68 | Raised refl pavt MKR (78100100) | EACH | 194 | $75.00 | $45.25 | $45.00 | $56.00 |
| 69 | Raised ref PVT MK rem (78300200) | EACH | 194 | $0.01 | $0.01 | $0.01 | $30.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.