IDOT contract 85778 bid tabulation
Rochelle, section 23-00118-00-RP. Let by Illinois DOT on April 25, 2025, Ogle, District 02. 2 bids received; low bid $4,668,879 by McCarthy Improvement Company.
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 54
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | McCarthy Improvement Company | $4,668,879 | Low |
| 2 | Martin & Company Excavating and Sjostrom & Sons, I nc. J.V. | $4,785,544 | +2.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. McCarthy Improvement Company | 2. Martin & Company Excavating and Sjostrom & Sons, I nc. J.V. |
|---|---|---|---|---|---|
| 1 | Railroad track (X0325346) | TRK FT | 1,532 | $98.00 | $105.00 |
| 2 | Base cse remov SPL (X3550103) | SY | 12,074 | $10.00 | $4.10 |
| 3 | Remov EX flar end sec (X5427602) | EACH | 2 | $650.00 | $500.00 |
| 4 | Memb WTRPRF sys B STR (X5810103) | SY | 459 | $49.00 | $26.00 |
| 5 | Manhole special (X6020084) | EACH | 2 | $8,000.00 | $5,200.00 |
| 6 | Traf cont & prot SPL (X7010216) | LS | 1 | $9,500.00 | $4,000.00 |
| 7 | Ballast (Z0002400) | TON | 1,410 | $38.00 | $42.00 |
| 8 | Construction layout (Z0013798) | LS | 1 | $23,400 | $27,500 |
| 9 | RR prot liability ins (Z0048665) | LS | 1 | $5,565.00 | $10,000 |
| 10 | Railroad ties (Z0048700) | EACH | 945 | $92.00 | $98.00 |
| 11 | RR track remov (Z0048900) | LF | 20 | $415.00 | $455.00 |
| 12 | Rock fill - foundatn (Z0054406) | CY | 248.30 | $64.00 | $42.00 |
| 13 | Sub-ballast (Z0069700) | CY | 545 | $50.00 | $38.00 |
| 14 | Railroad trackwork (Z0076302) | LSUM | 1 | $122,000 | $135,000 |
| 15 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 |
| 16 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 |
| 17 | Earth excavation (20200100) | CY | 20,307 | $14.50 | $13.33 |
| 18 | Rem & disp uns matl (20201200) | CY | 100 | $91.00 | $24.00 |
| 19 | Porous gran embank (20700220) | CY | 112 | $148.00 | $32.00 |
| 20 | Geotech fab F/GR stab (21001000) | SY | 300 | $2.50 | $6.00 |
| 21 | Topsoil exc & plac (21101505) | CY | 6,657 | $11.50 | $6.99 |
| 22 | Seeding CL 1A (25000110) | ACRE | 7 | $2,300.00 | $2,200.00 |
| 23 | Nitrogen fert nutr (25000400) | LB | 630 | $3.00 | $2.50 |
| 24 | Phosphorus fert nutr (25000500) | LB | 630 | $3.00 | $2.50 |
| 25 | Potassium fert nutr (25000600) | LB | 630 | $3.00 | $2.50 |
| 26 | Mulch method 2 (25100115) | ACRE | 7 | $2,800.00 | $2,200.00 |
| 27 | Erosion contr blanket (25100630) | SY | 2,200 | $1.00 | $1.65 |
| 28 | Perimeter eros bar (28000400) | LF | 2,200 | $2.75 | $2.50 |
| 29 | Inlet & pipe protect (28000500) | EACH | 2 | $400.00 | $220.00 |
| 30 | Inlet filters (28000510) | EACH | 9 | $250.00 | $150.00 |
| 31 | Stone riprap CL A3 (28100105) | SY | 100 | $25.50 | $44.00 |
| 32 | Filter fabric (28200200) | SY | 100 | $2.50 | $5.00 |
| 33 | Sub gran mat B (31101100) | CY | 100 | $63.50 | $36.00 |
| 34 | Agg base cse B 12 (35102400) | SY | 9,246 | $11.50 | $11.70 |
| 35 | HMA BC IL-9.5 N70 (40602985) | TON | 18 | $500.00 | $150.00 |
| 36 | HMA SC IL-9.5 C N70 (40604052) | TON | 18 | $500.00 | $150.00 |
| 37 | Welded wire reinf (42000060) | SY | 21,320 | $9.35 | $10.00 |
| 38 | PCC PVT 10 jointed (42000501) | SY | 12,074 | $91.75 | $109.00 |
| 39 | PCC PVT 14 jointed (42000564) | SY | 9,246 | $123.50 | $129.00 |
| 40 | Protective coat (42001300) | SY | 21,320 | $0.25 | $1.50 |
| 41 | Pavement rem (44000100) | SY | 280 | $17.75 | $12.30 |
| 42 | Rem/disp uns matl-STR (50200450) | CY | 325 | $55.00 | $48.00 |
| 43 | Box cul end sec C1 (54001001) | EACH | 2 | $29,750 | $33,000 |
| 44 | PCBC 6X3 (54010603) | LF | 513 | $910.00 | $844.00 |
| 45 | PRC flar end sec 12 (54213657) | EACH | 1 | $1,380.00 | $1,000.00 |
| 46 | PRC flar end sec 24 (54213669) | EACH | 4 | $1,105.00 | $1,350.00 |
| 47 | Storm sew CL B 1 12 (550B0050) | LF | 129 | $79.00 | $64.00 |
| 48 | Storm sew CL B 1 24 (550B0120) | LF | 1,039 | $76.00 | $94.00 |
| 49 | Storm sewer rem 12 (55100500) | LF | 14 | $18.00 | $15.00 |
| 50 | Storm sewer rem 18 (55100900) | LF | 11 | $18.00 | $22.00 |
| 51 | Pipe underdr T 1 8 (60108108) | LF | 667 | $20.25 | $28.00 |
| 52 | Man TA 4 dia T1F OL (60218300) | EACH | 5 | $4,875.00 | $2,400.00 |
| 53 | Man TA 5 dia T1F OL (60221000) | EACH | 2 | $6,250.00 | $3,200.00 |
| 54 | Mobilization (67100100) | LS | 1 | $265,000 | $260,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.