IDOT contract 89844 bid tabulation
Project Number: Ykq5-440 / /, section 21-00112-00-BR. Let by Illinois DOT on April 24, 2026, Mcdonough, District 04. 3 bids received; low bid $2,420,262 by County Contractors, Inc..
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 60
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | County Contractors, Inc. | $2,420,262 | Low |
| 2 | Brandt Construction Co. | $2,859,093 | +18% |
| 3 | Otto Baum Company, Inc. | $3,143,400 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. County Contractors, Inc. | 2. Brandt Construction Co. | 3. Otto Baum Company, Inc. |
|---|---|---|---|---|---|---|
| 1 | Bar terminators (X5080530) | EACH | 556 | $28.00 | $38.00 | $23.19 |
| 2 | Fence rem & reinstall (X6640108) | LF | 953 | $5.00 | $30.00 | $48.68 |
| 3 | Traf cont & prot SPL (X7010216) | LS | 1 | $2,650.00 | $2,800.00 | $1,500.00 |
| 4 | Detour signing (X7200203) | LS | 1 | $12,750 | $14,000 | $23,211 |
| 5 | Construction layout (Z0013798) | LS | 1 | $20,000 | $25,000 | $20,000 |
| 6 | Trainees (Z0076600) | HR | 1,000 | $0.80 | $0.80 | $0.80 |
| 7 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 | $15.00 | $15.00 |
| 8 | Tree remov acres (20100500) | ACRE | 0.75 | $36,500 | $11,200 | $10,721 |
| 9 | Earth excavation (20200100) | CY | 1,285 | $18.00 | $25.00 | $35.00 |
| 10 | Channel excavation (20300100) | CY | 314 | $21.00 | $35.00 | $22.48 |
| 11 | Furnished excavation (20400800) | CY | 5,035 | $38.00 | $40.00 | $60.00 |
| 12 | Topsoil F & P 4 (21101615) | SY | 6,160 | $6.25 | $10.00 | $9.00 |
| 13 | Seeding CL 2A (25000210) | ACRE | 1.50 | $4,960.00 | $4,400.00 | $4,181.29 |
| 14 | Nitrogen fert nutr (25000400) | LB | 120 | $2.10 | $4.50 | $4.29 |
| 15 | Phosphorus fert nutr (25000500) | LB | 120 | $2.10 | $4.50 | $4.29 |
| 16 | Potassium fert nutr (25000600) | LB | 120 | $2.10 | $4.50 | $4.29 |
| 17 | Mulch method 3A (25100127) | ACRE | 1.50 | $4,960.00 | $4,250.00 | $4,074.07 |
| 18 | Temp eros contr seed (28000250) | LB | 120 | $10.00 | $4.00 | $4.02 |
| 19 | Temp ditch checks (28000305) | LF | 270 | $10.00 | $7.00 | $6.97 |
| 20 | Perimeter eros bar (28000400) | LF | 1,984 | $4.00 | $6.00 | $5.36 |
| 21 | Temp eros contr blank (28001100) | SY | 266 | $5.00 | $8.00 | $7.50 |
| 22 | Stone riprap CL B5 (28100229) | TON | 888 | $110.00 | $120.00 | $90.47 |
| 23 | Filter fabric (28200200) | SY | 1,077 | $4.50 | $2.50 | $3.46 |
| 24 | Sub gran mat A (31100100) | TON | 1,175 | $35.00 | $45.00 | $47.68 |
| 25 | Bit matls PR CT (40600275) | LB | 4,045 | $1.60 | $1.00 | $1.62 |
| 26 | Bit matls tack CT (40600290) | LB | 1,618 | $4.70 | $1.00 | $4.78 |
| 27 | HMA BC IL-19.0 N50 (40603080) | TON | 453 | $334.00 | $225.00 | $339.33 |
| 28 | HMA SC IL-9.5 C N50 (40604050) | TON | 151 | $402.00 | $335.00 | $409.19 |
| 29 | PVT con HMA BR app SL (42000070) | SY | 93 | $400.00 | $435.00 | $406.79 |
| 30 | Pavement rem (44000100) | SY | 2,010 | $16.00 | $18.00 | $23.93 |
| 31 | Aggregate SHLDS B (48101200) | TON | 192 | $65.00 | $75.00 | $52.84 |
| 32 | Rem exist struct (50100100) | EACH | 1 | $56,000 | $265,000 | $250,000 |
| 33 | Structure excavation (50200100) | CY | 283 | $10.00 | $25.00 | $39.92 |
| 34 | Conc struct (50300225) | CY | 71.90 | $935.00 | $1,500.00 | $889.35 |
| 35 | Conc sup-STR (50300255) | CY | 205.10 | $2,150.00 | $1,810.00 | $2,462.74 |
| 36 | BR deck grooving (50300260) | SY | 648 | $12.00 | $11.00 | $20.32 |
| 37 | Protective coat (50300300) | SY | 848 | $6.00 | $7.00 | $4.32 |
| 38 | Conc supstr app slab (50301350) | CY | 94.30 | $775.00 | $645.00 | $1,194.10 |
| 39 | F & E struct steel (50500105) | LS | 1 | $530,000 | $600,000 | $600,000 |
| 40 | Stud shear connectors (50500505) | EACH | 1,155 | $9.00 | $8.50 | $5.63 |
| 41 | Reinf bars, epoxy CTD (50800205) | LB | 94,340 | $2.20 | $2.50 | $1.88 |
| 42 | Fur STL pile HP14X89 (51201900) | LF | 196 | $155.00 | $140.00 | $97.31 |
| 43 | Driving piles (51202305) | LF | 196 | $0.10 | $1.00 | $0.01 |
| 44 | Test pile ST HP14X89 (51203900) | EACH | 2 | $6,235.00 | $20,700 | $38,656 |
| 45 | Pile shoes (51204650) | EACH | 10 | $255.00 | $250.00 | $217.00 |
| 46 | Name plates (51500100) | EACH | 1 | $1,300.00 | $1,600.00 | $1,160.29 |
| 47 | Anchor bolts 1 (52100520) | EACH | 20 | $100.00 | $70.00 | $201.23 |
| 48 | Granular backfill STR (58600101) | CY | 175 | $85.00 | $140.00 | $138.28 |
| 49 | Geocomposite wall DR (59100100) | SY | 92 | $35.00 | $25.00 | $34.38 |
| 50 | Conc HDWL for P drain (60100060) | EACH | 4 | $550.00 | $855.00 | $750.32 |
| 51 | P undr for struct 4 (60146304) | LF | 118 | $36.00 | $45.00 | $21.28 |
| 52 | SPBGR TY A 6FT posts (63000001) | LF | 238 | $35.00 | $37.00 | $35.49 |
| 53 | Traf bar term T2 (63100045) | EACH | 2 | $2,170.00 | $2,300.00 | $2,203.22 |
| 54 | Traf bar term T6 (63100085) | EACH | 4 | $5,055.00 | $5,400.00 | $5,135.47 |
| 55 | TR bar TRM T1 SPL tan (63100167) | EACH | 2 | $3,915.00 | $4,150.00 | $3,977.58 |
| 56 | Mobilization (67100100) | LS | 1 | $65,250 | $170,000 | $187,979 |
| 57 | Sign panel T1 (72000100) | SF | 6 | $63.00 | $70.00 | $69.69 |
| 58 | Terminal marker - DA (72501000) | EACH | 4 | $52.00 | $55.00 | $53.61 |
| 59 | Teles STL sin support (72800100) | LF | 12 | $48.00 | $5.00 | $63.26 |
| 60 | Grdrail ref type A (78200005) | EACH | 12 | $10.00 | $12.00 | $10.72 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.