IDOT contract 91644 bid tabulation

Project Number: Uin2-240 / /, section 22-00046-15-RS. Let by Illinois DOT on March 7, 2025, Mclean, District 05. 2 bids received; low bid $3,188,964 by Rowe Construction, a div of UCM, Inc..

Owner
Illinois DOT
Letting
07 MAR 2025
Pay items
28
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Rowe Construction, a div of UCM, Inc.$3,188,964Low
2H. J. Eppel & Co.$3,600,079+13%
IDOT contract 91644: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Rowe Construction, a div of UCM, Inc.2. H. J. Eppel & Co.
1HMA surf rem var DP (X4401198)SY3,990$12.09$14.02
2Traf cont & prot SPL (X7010216)LS1$60,000$168,000
3Construction layout (Z0013798)LS1$10,000$4,200.00
4Rumble strip (Z0055300)EACH8$1,014.70$1,045.00
5Earth exc wid (20200500)CY3,720$45.00$40.41
6HMA base cse 7 (35501312)SY154$110.00$76.25
7HMA BC wid 4 (35600650)SY17,254$26.00$28.25
8Agg surf course TY B (40200800)TON50$206.81$47.50
9Bit matls tack CT (40600290)LB54,474$1.47$1.35
10Long joint sealant (40600370)LF26,073$2.48$2.90
11Temporary ramp (40600990)SY127$35.75$24.95
12HMA BC IL-9.5FG N50 (40602965)TON5,675$109.00$118.00
13HMA SC IL-9.5 D N70 (40604062)TON6,875$112.00$124.00
14Bit matls tack CT (40800029)LB1,760$0.59$1.70
15Incidental HMA surf (40800050)TON500$255.50$255.00
16HMA surf rem 2 (44000157)SY63,905$3.13$3.85
17HMA shoulders (48203100)TON1,702$125.00$128.00
18Comb CC&G TM6.18 (60609800)LF358$103.48$85.00
19SPBGR TY A 6FT posts (63000001)LF4,662.50$27.82$33.30
20SPGR att to culvert (63000030)LF50$78.75$94.30
21Traf bar term T5A (63100075)EACH2$1,575.00$1,887.00
22TR bar TRM T1 SPL tan (63100167)EACH14$3,018.75$3,617.00
23TR bar TRM T1 SPL FLR (63100169)EACH14$2,362.50$2,830.00
24Guardrail remov (63200310)LF5,736$4.20$5.00
25Shoulder rum strip 8 (64200108)LF62,900$0.23$0.37
26Mobilization (67100100)LS1$25,000$75,000
27Paint PVT MK line 5 (78001120)LF86,870$0.17$0.19
28Raised refl pavt MKR (78100100)EACH330$37.58$45.34
IDOT contract 91644: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy