IDOT contract 97863 bid tabulation
Mascoutah, section 21-00028-00-BT. Let by Illinois DOT on August 1, 2025, St. Clair, District 08. 2 bids received; low bid $1,251,808 by Baxmeyer Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 01 AUG 2025
- Pay items
- 67
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Baxmeyer Construction, Inc. | $1,251,808 | Low |
| 2 | DMS Contracting, Inc. | $1,458,183 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Baxmeyer Construction, Inc. | 2. DMS Contracting, Inc. |
|---|---|---|---|---|---|
| 1 | Ballast removal (XX009715) | CY | 27 | $90.00 | $100.00 |
| 2 | Bioretension system (XX009716) | SF | 1,194 | $28.00 | $27.00 |
| 3 | FL beacon P MTD SP in (X0325714) | EACH | 2 | $9,150.00 | $26,437 |
| 4 | Fold down bollards (X0350805) | EACH | 5 | $2,010.00 | $8,620.00 |
| 5 | Remov EX flar end sec (X5427602) | EACH | 2 | $195.00 | $670.00 |
| 6 | SS cleaned 18 (X5538000) | LF | 35 | $190.00 | $75.00 |
| 7 | Inlets SPL (X6024240) | EACH | 1 | $2,800.00 | $3,200.00 |
| 8 | WD post & rail fence (X6640628) | LF | 162 | $65.00 | $485.00 |
| 9 | Traf cont & prot SPL (X7010216) | LS | 1 | $8,000.00 | $30,000 |
| 10 | Bollards (Z0004002) | EACH | 10 | $950.00 | $2,000.00 |
| 11 | Construction layout (Z0013798) | LS | 1 | $24,000 | $51,000 |
| 12 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 |
| 13 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 |
| 14 | Tree remov acres (20100500) | ACRE | 3 | $5,035.00 | $19,000 |
| 15 | Earth excavation (20200100) | CY | 1,920 | $35.50 | $25.00 |
| 16 | Trench backfill (20800150) | CY | 55 | $42.50 | $34.00 |
| 17 | Topsoil F & P 4 (21101615) | SY | 7,649 | $14.50 | $12.00 |
| 18 | Seeding CL 1B (25000115) | ACRE | 2 | $6,000.00 | $4,500.00 |
| 19 | Nitrogen fert nutr (25000400) | LB | 143 | $6.50 | $3.00 |
| 20 | Phosphorus fert nutr (25000500) | LB | 143 | $6.50 | $3.00 |
| 21 | Potassium fert nutr (25000600) | LB | 143 | $6.50 | $3.00 |
| 22 | Mulch method 2 (25100115) | ACRE | 2 | $3,700.00 | $5,000.00 |
| 23 | Erosion contr blanket (25100630) | SY | 1,113 | $3.50 | $4.00 |
| 24 | Temp eros contr seed (28000250) | LB | 158 | $10.50 | $12.00 |
| 25 | Temp ditch checks (28000305) | LF | 168 | $37.50 | $15.00 |
| 26 | Perimeter eros bar (28000400) | LF | 11,145 | $7.65 | $4.00 |
| 27 | Inlet & pipe protect (28000500) | EACH | 6 | $455.00 | $450.00 |
| 28 | Stone riprap CL A3 (28100105) | SY | 34 | $59.00 | $55.00 |
| 29 | Filter fabric (28200200) | SY | 25 | $10.75 | $30.00 |
| 30 | Process mod soil 12 (30200650) | SY | 7,339 | $3.60 | $0.01 |
| 31 | Lime (30201500) | TON | 198 | $189.00 | $0.01 |
| 32 | Agg base cse A 6 (35100500) | SY | 7,346 | $15.00 | $13.50 |
| 33 | Agg surf cse A 4 (40200300) | SY | 72 | $22.50 | $25.00 |
| 34 | Bit matls PR CT (40600275) | LB | 14,157 | $1.30 | $1.06 |
| 35 | HMA SC IL-9.5FG C N50 (40604000) | TON | 1,061 | $183.50 | $196.69 |
| 36 | HMA SC IL-9.5 C N70 (40604052) | TON | 9 | $1,775.00 | $634.49 |
| 37 | PCC PVT 8 jointed (42000301) | SY | 660 | $104.00 | $115.00 |
| 38 | PCC driveway pavt 6 (42300200) | SY | 36 | $249.00 | $200.00 |
| 39 | PC conc sidewalk 5 (42400200) | SF | 2,124 | $15.25 | $12.50 |
| 40 | Detectable warnings (42400800) | SF | 212 | $35.00 | $70.00 |
| 41 | Pavement rem (44000100) | SY | 214 | $61.00 | $35.00 |
| 42 | Curb rem (44000300) | LF | 303 | $17.00 | $27.00 |
| 43 | Sidewalk rem (44000600) | SF | 14 | $76.00 | $60.00 |
| 44 | Bridge rail removal (50104000) | LF | 148 | $12.15 | $30.00 |
| 45 | Pipe culvert remov (50105220) | LF | 47 | $34.50 | $100.00 |
| 46 | Bicycle railing (50901720) | LF | 148 | $240.50 | $672.63 |
| 47 | PRC flar end sec 12 (54213657) | EACH | 2 | $1,175.00 | $2,320.00 |
| 48 | PRC flar end sec 18 (54213663) | EACH | 1 | $1,550.00 | $2,820.00 |
| 49 | Storm sew CL A 1 12 (550A0050) | LF | 107 | $59.00 | $130.00 |
| 50 | Storm sew CL A 1 18 (550A0090) | LF | 82 | $72.00 | $135.00 |
| 51 | Man TA 4 dia T1F OL (60218300) | EACH | 1 | $2,825.00 | $4,300.00 |
| 52 | Conc curb TB (60600605) | LF | 561 | $55.00 | $34.00 |
| 53 | Comb CC&G TB6.18 (60604400) | LF | 57 | $175.00 | $80.00 |
| 54 | Comb CC&G TB6.24 aep (60605100) | LF | 359 | $111.00 | $80.00 |
| 55 | SPBGR TY A 6FT posts (63000001) | LF | 13 | $130.50 | $331.92 |
| 56 | Non SPL waste disposl (66900200) | CY | 75 | $118.50 | $222.66 |
| 57 | Soil disposal analy (66900530) | EACH | 2 | $1,715.00 | $1,533.36 |
| 58 | Reg sub P-const plan (66901001) | LS | 1 | $2,325.00 | $2,326.47 |
| 59 | Reg sub F con report (66901003) | LS | 1 | $2,325.00 | $2,326.47 |
| 60 | Reg sub mon (66901006) | CAL DAY | 5 | $1,260.00 | $1,258.41 |
| 61 | Mobilization (67100100) | LS | 1 | $64,002 | $90,000 |
| 62 | Sign panel T1 (72000100) | SF | 154 | $31.75 | $53.00 |
| 63 | Teles STL sin support (72800100) | LF | 100 | $24.00 | $65.00 |
| 64 | Wood sin support (73000100) | LF | 200 | $41.50 | $70.00 |
| 65 | Paint PVT MK line 4 (78001110) | LF | 5,342 | $1.50 | $4.75 |
| 66 | Paint PVT MK line 12 (78001150) | LF | 40 | $26.50 | $26.50 |
| 67 | Paint PVT MK line 24 (78001180) | LF | 105 | $31.75 | $53.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.