IDOT contract 97870 bid tabulation
Troy, section 21-00036-00-BT. Let by Illinois DOT on June 13, 2025, Madison, District 08. 2 bids received; low bid $683,304 by Stutz Excavating, Inc..
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 63
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stutz Excavating, Inc. | $683,304 | Low |
| 2 | Keller Construction, Inc. | $770,728 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stutz Excavating, Inc. | 2. Keller Construction, Inc. |
|---|---|---|---|---|---|
| 1 | T-quercus rubra 2-1/2 (A2007120) | EACH | 2 | $750.00 | $2,450.00 |
| 2 | Constructn layout SPL (X0320050) | LS | 1 | $13,000 | $6,140.00 |
| 3 | Potholing (X1700066) | EACH | 20 | $530.00 | $550.00 |
| 4 | Concrete headwall SPL (X5036003) | EACH | 1 | $10,425 | $22,000 |
| 5 | Box culvert removal (X5400005) | LF | 15 | $125.00 | $200.00 |
| 6 | Inlets TA W/SPL F&G (X6023508) | EACH | 1 | $1,910.00 | $3,500.00 |
| 7 | Inlets SPL N1 (X6024242) | EACH | 1 | $5,625.00 | $10,000 |
| 8 | Inlets SPL N2 (X6024244) | EACH | 1 | $3,265.00 | $5,000.00 |
| 9 | Conc gutter SPL (X6062400) | LF | 228 | $52.80 | $81.11 |
| 10 | Traf cont & prot SPL (X7010216) | LS | 1 | $5,900.00 | $6,350.00 |
| 11 | Bollards (Z0004002) | EACH | 12 | $3,795.00 | $3,622.50 |
| 12 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 |
| 13 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 |
| 14 | Tree remov 6-15 (20100110) | UNIT | 12 | $60.00 | $167.00 |
| 15 | Earth excavation (20200100) | CY | 780 | $56.25 | $66.15 |
| 16 | Furnished excavation (20400800) | CY | 700 | $75.35 | $35.20 |
| 17 | Trench backfill (20800150) | CY | 27 | $117.00 | $55.00 |
| 18 | Seeding CL 1A (25000110) | ACRE | 1.50 | $3,000.00 | $4,825.50 |
| 19 | Nitrogen fert nutr (25000400) | LB | 135 | $2.00 | $9.24 |
| 20 | Phosphorus fert nutr (25000500) | LB | 135 | $2.00 | $9.24 |
| 21 | Potassium fert nutr (25000600) | LB | 135 | $2.00 | $9.24 |
| 22 | Mulch method 1 (25100105) | ACRE | 1.50 | $3,940.00 | $5,455.00 |
| 23 | Erosion contr blanket (25100630) | SY | 1,430 | $2.90 | $5.50 |
| 24 | Temp ditch checks (28000305) | LF | 36 | $22.00 | $27.75 |
| 25 | Perimeter eros bar (28000400) | LF | 4,736 | $3.35 | $4.55 |
| 26 | Inlet & pipe protect (28000500) | EACH | 15 | $265.00 | $429.00 |
| 27 | Stone riprap CL A4 (28100107) | SY | 10 | $156.00 | $160.00 |
| 28 | PR lim stab soil M 12 (31000600) | SY | 3,854 | $5.25 | $2.75 |
| 29 | Lime (31001500) | TON | 101 | $240.00 | $186.00 |
| 30 | Agg base cse A 4 (35100300) | SY | 457 | $24.00 | $0.01 |
| 31 | Agg base cse A 6 (35100500) | SY | 3,910 | $7.25 | $11.65 |
| 32 | Bit matls PR CT (40600275) | LB | 8,411 | $1.85 | $1.28 |
| 33 | HMA SC IL-9.5 C N50 (40604050) | TON | 611 | $168.00 | $163.72 |
| 34 | PC conc sidewalk 6 (42400300) | SF | 2,185 | $9.35 | $13.23 |
| 35 | Detectable warnings (42400800) | SF | 269 | $52.80 | $87.94 |
| 36 | Curb rem (44000300) | LF | 41 | $19.50 | $27.15 |
| 37 | Comb curb gutter rem (44000500) | LF | 60 | $24.50 | $18.55 |
| 38 | Sidewalk rem (44000600) | SF | 732 | $3.35 | $1.95 |
| 39 | Welded wire reinf (44200050) | SY | 169 | $19.80 | $14.00 |
| 40 | CL B patch T4 8 (44200944) | SY | 169 | $128.00 | $243.00 |
| 41 | Dowel bars 1 1/4 (44201298) | EACH | 120 | $26.50 | $20.10 |
| 42 | CL D patch T4 6 (44201723) | SY | 111 | $165.00 | $158.70 |
| 43 | Tie bars 1/2 (44213198) | EACH | 60 | $17.50 | $20.85 |
| 44 | Saw cuts (44213200) | LF | 140 | $13.20 | $10.80 |
| 45 | PCBC 3X2 (54010302) | LF | 28 | $762.00 | $850.00 |
| 46 | P cul CL A 1 15 (542A0220) | LF | 121.50 | $102.00 | $120.00 |
| 47 | PRC flar end sec 15 (54213660) | EACH | 8 | $1,725.00 | $2,250.00 |
| 48 | Concrete collar (54248510) | CY | 3.10 | $830.00 | $525.00 |
| 49 | Water valves adjust (56109210) | EACH | 2 | $210.00 | $645.00 |
| 50 | Dom met VLTS adj (56500300) | EACH | 1 | $435.00 | $1,230.00 |
| 51 | Conc curb TB (60600605) | LF | 32 | $52.80 | $168.50 |
| 52 | Comb CC&G TB6.18 (60604400) | LF | 60 | $52.80 | $100.59 |
| 53 | Non SPL waste disposl (66900200) | CY | 10 | $260.00 | $123.00 |
| 54 | Soil disposal analy (66900530) | EACH | 1 | $1,650.00 | $1,575.00 |
| 55 | Reg sub P-const plan (66901001) | LS | 1 | $2,200.00 | $2,100.00 |
| 56 | Reg sub F con report (66901003) | LS | 1 | $2,200.00 | $2,100.00 |
| 57 | Reg sub mon (66901006) | CAL DAY | 5 | $1,095.00 | $1,044.75 |
| 58 | Mobilization (67100100) | LS | 1 | $33,000 | $75,000 |
| 59 | Sign panel T1 (72000100) | SF | 164.50 | $38.50 | $36.75 |
| 60 | Teles STL sin support (72800100) | LF | 90 | $21.00 | $19.95 |
| 61 | Wood sin support (73000100) | LF | 297 | $44.00 | $42.00 |
| 62 | Paint PVT MK line 4 (78001110) | LF | 1,746 | $1.45 | $0.90 |
| 63 | Paint PVT MK line 24 (78001180) | LF | 606 | $13.50 | $3.94 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.