IDOT contract 99284 bid tabulation
Herrin, section 06-00054-00-FP. Let by Illinois DOT on August 1, 2025, Williamson, District 09. 4 bids received; low bid $2,069,759 by Samron Midwest Contracting, Inc..
- Owner
- Illinois DOT
- Letting
- 01 AUG 2025
- Pay items
- 51
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Samron Midwest Contracting, Inc. | $2,069,759 | Low |
| 2 | E. T. Simonds Construction Company | $2,074,342 | 0.0% |
| 3 | Sierra Bravo Contractors, LLC | $2,228,117 | +8.0% |
| 4 | Baxmeyer Construction, Inc. | $2,451,438 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Samron Midwest Contracting, Inc. | 2. E. T. Simonds Construction Company | 3. Sierra Bravo Contractors, LLC | 4. Baxmeyer Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | PCC PVMT 8 SPL W IC (LR420129) | SY | 8,988 | $74.00 | $82.50 | $86.00 | $83.00 |
| 2 | Inlets SPL (X6024240) | EACH | 28 | $6,100.00 | $5,794.67 | $7,085.11 | $4,500.00 |
| 3 | Traf cont-prot BLR 21 (X7011800) | LS | 1 | $25,000 | $4,133.96 | $4,853.05 | $1,000.00 |
| 4 | Trainees (Z0076600) | HR | 1,000 | $0.80 | $0.80 | $0.80 | $0.80 |
| 5 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 | $15.00 | $15.00 | $15.00 |
| 6 | Tree remov acres (20100500) | ACRE | 4.04 | $12,000 | $10,166 | $17,656 | $16,770 |
| 7 | Earth excavation (20200100) | CY | 5,895 | $16.00 | $15.98 | $12.45 | $23.00 |
| 8 | Furnished excavation (20400800) | CY | 4,259 | $19.00 | $20.48 | $16.66 | $14.25 |
| 9 | Porous gran embank (20700220) | CY | 46 | $35.00 | $46.68 | $75.43 | $73.50 |
| 10 | Trench backfill (20800150) | CY | 531 | $45.00 | $44.24 | $48.10 | $50.00 |
| 11 | Seeding CL 2 (25000200) | ACRE | 4 | $2,300.00 | $1,260.00 | $1,260.00 | $3,050.00 |
| 12 | Nitrogen fert nutr (25000400) | LB | 361 | $2.00 | $3.15 | $3.15 | $5.15 |
| 13 | Phosphorus fert nutr (25000500) | LB | 361 | $2.00 | $3.15 | $3.15 | $5.15 |
| 14 | Potassium fert nutr (25000600) | LB | 361 | $2.00 | $3.15 | $3.15 | $5.15 |
| 15 | Agr ground limestone (25000700) | TON | 8 | $400.00 | $210.00 | $210.00 | $400.75 |
| 16 | Mulch method 2 (25100115) | ACRE | 4 | $2,000.00 | $1,260.00 | $1,260.00 | $5,800.00 |
| 17 | Temp eros contr seed (28000250) | LB | 1,600 | $3.00 | $2.71 | $2.20 | $4.00 |
| 18 | Temp ditch checks (28000305) | LF | 610 | $25.00 | $13.18 | $30.13 | $26.50 |
| 19 | Perimeter eros bar (28000400) | LF | 1,921 | $3.00 | $4.94 | $5.06 | $8.00 |
| 20 | Inlet & pipe protect (28000500) | EACH | 31 | $200.00 | $148.52 | $194.89 | $245.00 |
| 21 | Stone riprap CL A4 (28100107) | SY | 266 | $50.00 | $37.70 | $49.08 | $68.00 |
| 22 | Filter fabric (28200200) | SY | 266 | $3.00 | $3.30 | $4.08 | $7.75 |
| 23 | Sub gran mat A 6 (31100500) | SY | 10,170 | $10.00 | $10.78 | $10.72 | $11.00 |
| 24 | PCC PVT 8 (42000300) | SY | 808 | $85.00 | $98.06 | $87.94 | $99.00 |
| 25 | PCC driveway pavt 8 (42300400) | SY | 250 | $105.00 | $102.67 | $110.10 | $136.50 |
| 26 | PC conc sidewalk 5 (42400200) | SF | 26,582 | $6.50 | $6.95 | $7.07 | $6.75 |
| 27 | Detectable warnings (42400800) | SF | 20 | $40.00 | $37.53 | $30.14 | $28.00 |
| 28 | Pavement rem (44000100) | SY | 346 | $16.00 | $14.46 | $22.01 | $10.00 |
| 29 | Sidewalk rem (44000600) | SF | 1,000 | $3.50 | $2.29 | $2.64 | $1.10 |
| 30 | Box cul end sec C1 (54001001) | EACH | 2 | $16,000 | $26,143 | $22,791 | $19,766 |
| 31 | PCBC 8X3 (54010803) | LF | 56 | $925.00 | $924.21 | $849.10 | $827.00 |
| 32 | P cul CL A 1 18 (542A0223) | LF | 76 | $70.00 | $88.69 | $82.32 | $68.00 |
| 33 | PRC flar end sec 18 (54213663) | EACH | 4 | $2,000.00 | $1,871.24 | $1,894.22 | $1,534.00 |
| 34 | PRC flar end sec 30 (54213675) | EACH | 4 | $3,200.00 | $2,671.01 | $2,521.29 | $2,419.00 |
| 35 | PRC flar end sec 36 (54213681) | EACH | 2 | $3,300.00 | $3,114.10 | $2,652.44 | $2,538.00 |
| 36 | Storm sew CL A 1 15 (550A0070) | LF | 1,385 | $58.00 | $69.67 | $69.83 | $65.00 |
| 37 | Storm sew CL A 1 18 (550A0090) | LF | 220 | $80.00 | $79.55 | $78.12 | $78.00 |
| 38 | Storm sew CL A 1 24 (550A0120) | LF | 301 | $100.00 | $106.26 | $105.55 | $96.00 |
| 39 | Storm sew CL A 1 30 (550A0140) | LF | 394 | $125.00 | $140.11 | $138.48 | $130.00 |
| 40 | Storm sew CL A 1 36 (550A0160) | LF | 66 | $160.00 | $181.57 | $168.35 | $188.00 |
| 41 | Inlets reconst (60262700) | EACH | 2 | $1,100.00 | $2,873.33 | $2,225.25 | $3,370.00 |
| 42 | Comb CC&G TB6.12 (60603800) | LF | 371 | $55.00 | $73.50 | $47.25 | $108.50 |
| 43 | Fur erect row markers (66600105) | EACH | 42 | $250.00 | $248.43 | $196.85 | $325.00 |
| 44 | Mobilization (67100100) | LS | 1 | $124,000 | $38,052 | $133,682 | $354,130 |
| 45 | Traf cont-prot 701201 (70100450) | LS | 1 | $15,000 | $2,634.50 | $7,430.33 | $11,220 |
| 46 | Sign panel T1 (72000100) | SF | 13 | $30.00 | $26.45 | $30.45 | $39.10 |
| 47 | Teles STL sin support (72800100) | LF | 30 | $15.00 | $13.73 | $23.10 | $21.50 |
| 48 | Pref PL PM TB STD L4 (78003111) | LF | 745 | $5.00 | $6.89 | $11.45 | $7.00 |
| 49 | Pref PL PM TB STD L24 (78003181) | LF | 40 | $20.00 | $26.60 | $82.16 | $27.00 |
| 50 | GRV RCSD PVT MRKG 5 (78011025) | LF | 745 | $17.00 | $3.13 | $0.11 | $3.15 |
| 51 | GRV RCSD PVT MRKG 25 (78011125) | LF | 40 | $35.00 | $21.89 | $0.26 | $22.05 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.