IDOT contract 99687 bid tabulation
Project Number: Iu4T-842- / /, section 19-00156-00-SP. Let by Illinois DOT on January 17, 2025, Williamson, District 09. 2 bids received; low bid $2,026,739 by Samron Midwest Contracting, Inc..
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 63
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Samron Midwest Contracting, Inc. | $2,026,739 | Low |
| 2 | E. T. Simonds Construction Company | $2,089,819 | +3.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Samron Midwest Contracting, Inc. | 2. E. T. Simonds Construction Company |
|---|---|---|---|---|---|
| 1 | Weed barrier fabric (X0321501) | SY | 160 | $4.00 | $8.24 |
| 2 | Landscaping gravel (X0323117) | SY | 160 | $25.00 | $43.26 |
| 3 | Stamp CLRD PCC med 4 (X1700011) | SF | 3,631 | $8.24 | $16.84 |
| 4 | Stamped CLRDPCCPVT8J (X4200468) | SY | 1,313 | $0.01 | $170.87 |
| 5 | Inlets SPL (X6024240) | EACH | 6 | $6,000.00 | $5,726.70 |
| 6 | Conc median surf 4 SP (X6061310) | SF | 5,282 | $7.00 | $8.18 |
| 7 | Comb CC&G TM SPL (X6061815) | LF | 423 | $70.00 | $46.40 |
| 8 | Traf cont & prot SPL (X7010216) | LS | 1 | $61,000 | $3,672.90 |
| 9 | Changeable MSG SN SPL (X7010239) | CAL WK | 12 | $900.00 | $288.75 |
| 10 | Construction layout (Z0013798) | LS | 1 | $61,500 | $22,494 |
| 11 | Tree remov acres (20100500) | ACRE | 1 | $10,900 | $24,042 |
| 12 | Earth excavation (20200100) | CY | 3,713 | $15.00 | $9.33 |
| 13 | Rem & disp uns matl (20201200) | CY | 1,196 | $16.00 | $17.85 |
| 14 | Furnished excavation (20400800) | CY | 4,733 | $13.00 | $17.82 |
| 15 | Trench backfill (20800150) | CY | 98 | $55.00 | $55.31 |
| 16 | Seeding CL 2A (25000210) | ACRE | 1.70 | $7,500.00 | $1,751.00 |
| 17 | Nitrogen fert nutr (25000400) | LB | 153 | $2.00 | $3.09 |
| 18 | Phosphorus fert nutr (25000500) | LB | 153 | $2.00 | $3.09 |
| 19 | Potassium fert nutr (25000600) | LB | 153 | $2.00 | $3.09 |
| 20 | Agr ground limestone (25000700) | TON | 3.50 | $105.00 | $206.00 |
| 21 | Mulch method 2 (25100115) | ACRE | 1.70 | $2,000.00 | $1,236.00 |
| 22 | Erosion contr blanket (25100630) | SY | 6,585 | $2.00 | $1.49 |
| 23 | Temp eros contr seed (28000250) | LB | 346 | $2.50 | $2.50 |
| 24 | Temp ditch checks (28000305) | LF | 150 | $5.00 | $13.80 |
| 25 | Perimeter eros bar (28000400) | LF | 3,566 | $4.00 | $4.61 |
| 26 | Inlet & pipe protect (28000500) | EACH | 6 | $100.00 | $135.21 |
| 27 | Stone riprap CL A4 (28100107) | SY | 18 | $95.00 | $60.30 |
| 28 | Filter fabric (28200200) | SY | 18 | $50.00 | $6.31 |
| 29 | Agg subgrade improve (30300001) | CY | 3,810 | $55.00 | $47.48 |
| 30 | Agg base cse A 12 (35101100) | SY | 9,322 | $20.00 | $19.62 |
| 31 | PCC PVT 8 jointed (42000301) | SY | 6,657 | $68.00 | $81.94 |
| 32 | Protective coat (42001300) | SY | 8,961 | $0.01 | $0.01 |
| 33 | Pavement rem (44000100) | SY | 4,950 | $10.00 | $6.31 |
| 34 | Pipe culvert remov (50105220) | LF | 249 | $15.00 | $8.26 |
| 35 | P cul CL A 1 24 (542A0229) | LF | 100 | $95.00 | $116.26 |
| 36 | P cul CL A 1 30 (542A0235) | LF | 63 | $125.00 | $155.81 |
| 37 | P cul CL D 1 18 (542D0223) | LF | 77 | $45.00 | $44.35 |
| 38 | PRC flar end sec 24 (54213669) | EACH | 5 | $2,675.00 | $1,551.87 |
| 39 | PRC flar end sec 30 (54213675) | EACH | 2 | $3,000.00 | $2,171.05 |
| 40 | Storm sew CL A 1 24 (550A0120) | LF | 370 | $98.00 | $119.33 |
| 41 | Man TA 4 dia T1F CL (60218400) | EACH | 1 | $3,350.00 | $3,422.37 |
| 42 | Man TA 4 dia T3F&G (60218500) | EACH | 10 | $3,800.00 | $3,672.31 |
| 43 | Inlets TB T8G (60240301) | EACH | 1 | $2,800.00 | $2,516.69 |
| 44 | Conc curb TB (60600605) | LF | 213 | $45.00 | $48.03 |
| 45 | Comb CC&G TY B-6.24 (60605000) | LF | 3,722 | $65.00 | $52.76 |
| 46 | Fur erect row markers (66600105) | EACH | 12 | $300.00 | $180.25 |
| 47 | Mobilization (67100100) | LS | 1 | $120,000 | $46,133 |
| 48 | Sign panel T1 (72000100) | SF | 213 | $26.00 | $30.90 |
| 49 | Sign panel T3 (72000300) | SF | 162 | $62.00 | $82.40 |
| 50 | Metal post TY B (72900200) | LF | 81 | $17.00 | $23.69 |
| 51 | Wood sin support (73000100) | LF | 446 | $30.00 | $28.84 |
| 52 | Mod ureth PM LTR-sym (78009000) | SF | 103 | $9.00 | $7.87 |
| 53 | Mod ureth PM line 4 (78009004) | LF | 6,844 | $3.00 | $2.63 |
| 54 | Mod ureth PM line 12 (78009012) | LF | 398 | $9.00 | $7.73 |
| 55 | Mod ureth PM line 18 (78009018) | LF | 41 | $16.00 | $14.42 |
| 56 | Elect serv install (80400100) | EACH | 1 | $7,800.00 | $7,405.48 |
| 57 | Undrgrd C CNC 2 (81028750) | LF | 313 | $25.00 | $23.00 |
| 58 | UD 2#10#10GXLPUSE 3/4 (81603010) | LF | 652 | $18.00 | $12.46 |
| 59 | Lum LED rdwy G (82110007) | EACH | 7 | $1,000.00 | $1,029.76 |
| 60 | LT cont PM 240V 30 (82500300) | EACH | 1 | $11,000 | $7,787.93 |
| 61 | LT P A 35MH 15DA (83001600) | EACH | 7 | $4,300.00 | $5,001.76 |
| 62 | LP F M 15BC 8 5/8X6 (83600356) | EACH | 7 | $1,780.00 | $1,097.52 |
| 63 | Bkwy dev cou SS SCRN (83800650) | EACH | 7 | $1,750.00 | $301.93 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.