IDOT contract 99760 bid tabulation
City Of Marion, section 23-00131-00-BT. Let by Illinois DOT on August 1, 2025, Williamson, District 09. 3 bids received; low bid $2,142,142 by Samron Midwest Contracting, Inc..
- Owner
- Illinois DOT
- Letting
- 01 AUG 2025
- Pay items
- 62
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Samron Midwest Contracting, Inc. | $2,142,142 | Low |
| 2 | E. T. Simonds Construction Company | $2,158,961 | +1.0% |
| 3 | Kieffer Bros. Construction Co., Inc. | $2,799,509 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Samron Midwest Contracting, Inc. | 2. E. T. Simonds Construction Company | 3. Kieffer Bros. Construction Co., Inc. |
|---|---|---|---|---|---|---|
| 1 | Ornam light unit comp (X0326654) | EACH | 64 | $8,450.00 | $9,255.17 | $9,713.00 |
| 2 | Sign panel T1 SPL DS (X2600031) | SF | 7 | $135.00 | $107.25 | $141.00 |
| 3 | Remov EX flar end sec (X5427602) | EACH | 1 | $580.00 | $330.00 | $1,590.00 |
| 4 | Manhole special (X6020084) | EACH | 8 | $6,100.00 | $10,866 | $9,172.00 |
| 5 | Inlets SPL N1 (X6024242) | EACH | 6 | $3,500.00 | $7,198.27 | $4,175.00 |
| 6 | Inlets SPL N2 (X6024244) | EACH | 1 | $6,000.00 | $6,599.82 | $6,443.00 |
| 7 | Inlets SPL N3 (X6024246) | EACH | 1 | $4,500.00 | $8,090.50 | $5,143.00 |
| 8 | Inlets SPL N4 (X6024248) | EACH | 1 | $6,500.00 | $13,092 | $8,847.00 |
| 9 | Inlets SPL N5 (X6024250) | EACH | 6 | $4,000.00 | $6,578.00 | $4,694.00 |
| 10 | Sign panel T1 SPL (X7200105) | SF | 23 | $90.00 | $79.75 | $95.00 |
| 11 | Elect serv install SP (X8040102) | EACH | 2 | $3,500.00 | $10,159 | $10,661 |
| 12 | Conc retain wall rem (Z0075496) | LF | 11 | $67.00 | $484.00 | $132.00 |
| 13 | Trainees (Z0076600) | HR | 1,500 | $0.80 | $0.80 | $0.80 |
| 14 | Trainees TPG (Z0076604) | HR | 1,500 | $15.00 | $15.00 | $15.00 |
| 15 | Trench backfill (20800150) | CY | 273 | $50.00 | $44.00 | $40.00 |
| 16 | Seeding CL 2 (25000200) | ACRE | 2.75 | $1,400.00 | $1,320.00 | $2,885.09 |
| 17 | Nitrogen fert nutr (25000400) | LB | 250 | $3.00 | $3.30 | $1.00 |
| 18 | Phosphorus fert nutr (25000500) | LB | 250 | $3.00 | $3.30 | $1.00 |
| 19 | Potassium fert nutr (25000600) | LB | 250 | $3.00 | $3.30 | $1.00 |
| 20 | Agr ground limestone (25000700) | TON | 5.40 | $250.00 | $220.00 | $407.63 |
| 21 | Mulch method 2 (25100115) | ACRE | 2.75 | $3,000.00 | $2,750.00 | $1,952.00 |
| 22 | Temp eros contr seed (28000250) | LB | 270 | $2.50 | $3.30 | $6.00 |
| 23 | Perimeter eros bar (28000400) | LF | 5,356 | $4.00 | $4.13 | $5.00 |
| 24 | Inlet & pipe protect (28000500) | EACH | 14 | $200.00 | $203.50 | $177.00 |
| 25 | Agg surf course TY B (40200800) | TON | 1,238 | $46.00 | $60.55 | $41.50 |
| 26 | PCC driveway pavt 10 (42300600) | SY | 327 | $0.01 | $160.42 | $275.00 |
| 27 | PC conc sidewalk 5 (42400200) | SF | 61,508 | $11.40 | $8.42 | $17.00 |
| 28 | PC conc sidewalk 8 (42400410) | SF | 827 | $12.00 | $15.34 | $21.00 |
| 29 | Detectable warnings (42400800) | SF | 323 | $40.00 | $34.34 | $29.00 |
| 30 | Drive pavement rem (44000200) | SY | 265 | $15.00 | $20.90 | $23.00 |
| 31 | Curb rem (44000300) | LF | 113 | $17.00 | $9.90 | $13.00 |
| 32 | Comb curb gutter rem (44000500) | LF | 383 | $19.00 | $12.10 | $11.00 |
| 33 | Sidewalk rem (44000600) | SF | 8,073 | $2.50 | $4.40 | $5.00 |
| 34 | Paved ditch removal (44004000) | LF | 218 | $16.00 | $12.10 | $19.00 |
| 35 | Paved SHLD removal (44004250) | SY | 296 | $35.00 | $38.28 | $17.00 |
| 36 | Conc headwall removal (50104400) | EACH | 1 | $500.00 | $1,980.00 | $954.00 |
| 37 | Pipe culvert remov (50105220) | LF | 45 | $12.00 | $22.00 | $26.00 |
| 38 | PRC flar end sec 42 (54213687) | EACH | 1 | $4,200.00 | $7,227.00 | $7,348.00 |
| 39 | Concrete collar (54248510) | CY | 2.20 | $1,200.00 | $880.00 | $1,014.00 |
| 40 | Storm sew CL A 1 12 (550A0050) | LF | 259 | $56.00 | $88.41 | $78.00 |
| 41 | Storm sew CL A 1 15 (550A0070) | LF | 286 | $59.00 | $100.35 | $91.00 |
| 42 | Storm sew CL A 1 18 (550A0090) | LF | 199 | $75.00 | $104.11 | $94.00 |
| 43 | Storm sew CL A 1 24 (550A0120) | LF | 134 | $100.00 | $134.66 | $121.00 |
| 44 | Storm sew CL A 1 30 (550A0140) | LF | 475 | $120.00 | $152.05 | $150.00 |
| 45 | Storm sew CL A 1 36 (550A0160) | LF | 328 | $140.00 | $172.37 | $167.00 |
| 46 | Storm sew CL A 1 42 (550A0180) | LF | 30 | $165.00 | $676.79 | $192.00 |
| 47 | Inlets adjust (60260100) | EACH | 1 | $1,500.00 | $4,400.00 | $185.00 |
| 48 | Conc curb TB (60600605) | LF | 194 | $35.00 | $36.33 | $76.00 |
| 49 | Comb CC&G TB6.12 (60603800) | LF | 270 | $55.00 | $51.48 | $41.00 |
| 50 | Comb CC&G TY B-6.24 (60605000) | LF | 1,348 | $65.00 | $47.96 | $61.00 |
| 51 | Mobilization (67100100) | LS | 1 | $128,000 | $71,437 | $81,924 |
| 52 | TR cont & prot 701501 (70102620) | LS | 1 | $50,000 | $42,975 | $67,720 |
| 53 | TR cont & prot 701601 (70102630) | LS | 1 | $35,704 | $10,945 | $48,192 |
| 54 | TR cont & prot 701801 (70102640) | LS | 1 | $6,000.00 | $1,339.80 | $26,603 |
| 55 | Sign panel T1 (72000100) | SF | 5 | $80.00 | $44.00 | $84.00 |
| 56 | Teles STL sin support (72800100) | LF | 69 | $17.00 | $76.45 | $17.00 |
| 57 | Paint PVT MK line 6 (78001130) | LF | 480 | $7.00 | $6.56 | $10.00 |
| 58 | Paint PVT MK line 12 (78001150) | LF | 204 | $13.50 | $13.11 | $16.00 |
| 59 | Paint PVT MK line 24 (78001180) | LF | 31 | $32.00 | $30.80 | $25.00 |
| 60 | PVT MKG rem WTR blast (78300202) | SF | 125 | $55.00 | $52.16 | $233.20 |
| 61 | UD 2#6 #8G xlpuse 1 (81603040) | LF | 1,300 | $22.00 | $18.28 | $19.18 |
| 62 | LT cont pedm 240V100 (82500335) | EACH | 2 | $11,500 | $11,797 | $12,380 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.