INDOT contract B-39418-B bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on January 15, 2025, Warrick, Vincennes. 3 bids received; low bid $1,357,800 by Blankenberger Brothers Inc.
- Owner
- Indiana DOT
- Letting
- 15 JAN 2025
- Pay items
- 58
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Blankenberger Brothers Inc | $1,357,800 | Low |
| 2 | E & B Paving LLC | $1,370,000 | +1.0% |
| 3 | Deig Brothers Lumber & Constr | $1,474,931 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Blankenberger Brothers Inc | 2. E & B Paving LLC | 3. Deig Brothers Lumber & Constr |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $12,000 | $30,000 | $20,200 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $80,000 | $67,000 | $72,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $25,000 | $13,750 | $34,720 |
| 0011 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $38,000 | $34,000 | $75,540 |
| 0012 | Guardrail end treatment, remove (202-93741) | EACH | 4 | $200.00 | $200.00 | $202.00 |
| 0013 | Excavation, unclassified (203-02020) | CYS | 1,660 | $54.50 | $76.00 | $42.00 |
| 0014 | Borrow (203-02070) | CYS | 765 | $35.00 | $40.00 | $57.00 |
| 0015 | Pump around (205-11626) | EACH | 1 | $25,000 | $28,000 | $40,600 |
| 0016 | Stormwater management budget (205-12108) | DOL | 9,856 | $1.00 | $1.00 | $1.00 |
| 0017 | Stormwater management implementation (205-12616) | LS | 1 | $15,000 | $42,000 | $15,135 |
| 0018 | Subgrade treatment, type IC (207-09935) | SYS | 1,512 | $45.00 | $36.00 | $47.00 |
| 0019 | Structure backfill, type 2 (211-09265) | CYS | 845 | $76.50 | $75.00 | $94.00 |
| 0020 | Structure backfill, type 5 (211-09268) | CYS | 400 | $211.00 | $187.00 | $225.00 |
| 0021 | Compacted aggregate, no. 53 (303-01180) | TON | 139 | $73.35 | $100.00 | $74.00 |
| 0022 | Widening with HMA, type B (304-07493) | TON | 53 | $325.00 | $325.00 | $328.00 |
| 0023 | Milling, transition (306-08043) | SYS | 499 | $9.85 | $16.00 | $30.00 |
| 0024 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 141 | $195.00 | $195.00 | $197.00 |
| 0025 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 31 | $300.00 | $300.00 | $303.00 |
| 0026 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 216 | $150.00 | $150.00 | $152.00 |
| 0027 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 463 | $120.00 | $120.00 | $122.00 |
| 0028 | Joint adhesive, surface (401-10258) | LFT | 935 | $0.60 | $0.60 | $0.70 |
| 0029 | Joint adhesive, intermediate (401-10259) | LFT | 790 | $0.60 | $0.60 | $0.70 |
| 0030 | Liquid asphalt sealant (401-11785) | LFT | 925 | $0.39 | $0.39 | $0.40 |
| 0031 | Asphalt for tack coat (406-05521) | SYS | 5,187 | $0.15 | $0.15 | $0.20 |
| 0032 | Guardrail, remove (601-02241) | LFT | 499 | $3.00 | $3.00 | $3.10 |
| 0033 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 318.75 | $20.00 | $20.00 | $21.50 |
| 0034 | Guardrail, MGS, structure top-mounted post (601-12293) | EACH | 14 | $365.00 | $365.00 | $370.00 |
| 0035 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $2,800.00 | $2,800.00 | $2,825.00 |
| 0036 | Monument, type B (615-06505) | EACH | 2 | $1,150.00 | $1,150.00 | $1,160.00 |
| 0037 | Riprap, class 1 (616-05688) | TON | 398 | $82.00 | $110.00 | $125.00 |
| 0038 | Geotextile for riprap, type 1B (616-12247) | SYS | 362 | $6.00 | $3.50 | $11.00 |
| 0039 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $1,050.00 | $900.00 | $1,065.00 |
| 0040 | Mulched seeding, type R (621-06559) | SYS | 2,051 | $3.34 | $1.00 | $3.50 |
| 0041 | Sodding (621-06574) | SYS | 45 | $98.00 | $60.00 | $100.00 |
| 0042 | Computer system equipment (628-11976) | EACH | 2 | $550.00 | $700.00 | $1,370.00 |
| 0043 | Field office, type D (628-12683) | MOS | 12 | $2,600.00 | $3,325.00 | $2,840.00 |
| 0044 | Surface seal (709-51821) | LS | 1 | $5,000.00 | $1.00 | $3,240.00 |
| 0045 | Waterproofing membrane type 2 (714-000086) | SFT | 3,000 | $3.00 | $3.50 | $3.25 |
| 0046 | Geotextile for underdrains, type 1A (718-12305) | SYS | 3,726 | $1.45 | $2.50 | $7.00 |
| 0047 | Structure, reinforced concrete, three-sided (723-11270) | LFT | 60 | $8,100.00 | $6,915.00 | $7,600.00 |
| 0048 | Road closure sign assembly (801-04308) | EACH | 4 | $245.00 | $245.00 | $250.00 |
| 0049 | Detour route marker assembly (801-06625) | EACH | 59 | $98.00 | $98.00 | $100.00 |
| 0050 | Construction sign, type A (801-06640) | EACH | 31 | $145.00 | $145.00 | $147.00 |
| 0051 | Maintaining traffic (801-06775) | LS | 1 | $28,744 | $57,113 | $33,600 |
| 0052 | Barricade, type III-A (801-07118) | LFT | 48 | $14.00 | $14.00 | $14.50 |
| 0053 | Barricade, type III-B (801-07119) | LFT | 24 | $14.00 | $14.00 | $14.50 |
| 0054 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 1,180 | $1.15 | $1.15 | $1.50 |
| 0055 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 1,100 | $1.15 | $1.15 | $1.50 |
| 0056 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 80 | $2.95 | $2.95 | $3.00 |
| 0057 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 15 | $20.00 | $55.00 | $137.00 |
| 0058 | Snowplowable raised pavement marker (808-75998) | EACH | 15 | $135.00 | $135.00 | $137.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.