Deig Brothers Lumber & Constr: INDOT bid record
Deig Brothers Lumber & Constr submitted 14 bids on Indiana DOT contracts in the data, from 06 APR 2022 to 10 DEC 2025, and was the low bidder on 2 of them (14%). When it was not low, its total sat a median +13% above the low bid.
- Owner
- Indiana DOT
- Low bid volume
- $6,282,244
- Latest bid
- 10 DEC 2025
- Data through
- 05 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 3 | 0 | 0% |
| 2023 | 4 | 1 | 25% |
| 2024 | 2 | 0 | 0% |
| 2025 | 5 | 1 | 20% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Liquidated damages | 109-08359 | DOL | 14 | 14 (100%) | $1.00 | $1.00 |
| Contract liens | 109-08360 | DOL | 14 | 14 (100%) | $1.00 | $1.00 |
| Quality adjustments, failed materials | 109-08444 | DOL | 14 | 14 (100%) | $1.00 | $1.00 |
| Quality adjustments, temporary traffic control devices | 109-08443 | DOL | 14 | 14 (100%) | $1.00 | $1.00 |
| Stormwater management budget | 205-12108 | DOL | 14 | 14 (100%) | $1.00 | $1.00 |
| Quality adjustments, failure to maintain temporary erosion and sediment control measures | 109-11362 | DOL | 13 | 13 (100%) | $1.00 | $1.00 |
| Quality adjustments, HMA | 109-08440 | DOL | 12 | 12 (100%) | $1.00 | $1.00 |
| Payment adjustment, PG asphalt binder | 109-09489 | DOL | 6 | 6 (100%) | $1.00 | $1.00 |
| Payment adjustment PG asphalt binder | 109-09489 | DOL | 5 | 5 (100%) | $1.00 | $1.00 |
| Quality adjustments, pavement traffic markings | 109-09377 | DOL | 5 | 5 (100%) | $1.00 | $1.00 |
| Excavation, common | 203-02000 | CYS | 12 | 3 (25%) | $30.75 | $63.00 |
| Structure backfill, type 2 | 211-09265 | CYS | 12 | 3 (25%) | $76.25 | $82.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Ragle, Inc. | 11 | 6 of 11 |
| Blankenberger Brothers Inc | 9 | 9 of 9 |
| E & B Paving LLC | 8 | 6 of 8 |
| Lutgring Brothers Inc | 4 | 3 of 4 |
| CLR Inc | 3 | 0 of 3 |
| Koberstein Contracting Inc | 3 | 2 of 3 |
| Kerns Excavating LLC | 2 | 2 of 2 |
| S.A.M.M. Trucking & Excavating Inc | 2 | 1 of 2 |
| Weddle Brothers Highway Group LLC | 1 | 1 of 1 |
| J B I Construction Inc | 1 | 1 of 1 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 10 DEC 2025 | R-42808-A | Vincennes | ROAD RECONSTRUCTION | 4 of 4 | $6,337,908 | +12% |
| 13 NOV 2025 | B-43235-A | Vincennes | BRIDGE REPLACEMENT | 4 of 6 | $1,730,093 | +16% |
| 12 MAR 2025 | R-44695-A | Vincennes | SMALL STRUCTURES AND DRAINS CONSTRUCTION | 2 of 4 | $5,214,876 | +13% |
| 15 JAN 2025 | B-39418-B | Vincennes | BRIDGE REPLACEMENT | 3 of 3 | $1,474,931 | +9.0% |
| 15 JAN 2025 | B-43226-A | Vincennes | SMALL STRUCTURES AND DRAINS CONSTRUCTION | 1 of 6 | $986,053 | Low, 8.0% under the second |
| 09 OCT 2024 | R-44971-A | Vincennes | SLIDE CORRECTION | 6 of 7 | $627,636 | +27% |
| 10 JUL 2024 | R-41772-A | Vincennes | ROAD RECONSTRUCTION | 6 of 6 | $11,578,175 | +31% |
| 13 DEC 2023 | R-37845-A | Vincennes | INTERSECTION IMPROVEMENT AND SMALL STRUCTURE REPLACEMENT | 1 of 2 | $5,296,191 | Low, 8.0% under the second |
| 09 AUG 2023 | R-44029-A | Vincennes | CURVE CORRECTION | 5 of 6 | $765,188 | +10% |
| 15 MAR 2023 | R-41408-A | Vincennes | SLIDE CORRECTION | 5 of 5 | $703,187 | +46% |
| 10 FEB 2023 | R-41599-A | Vincennes | ROAD RECONSTRUCTION | 3 of 3 | $24,726,621 | +16% |
| 10 AUG 2022 | B-43657-B | Vincennes | BRIDGE REPLACEMENT | 3 of 5 | $1,172,263 | +1.0% |
| 05 MAY 2022 | R-43212-A | Vincennes | DRAINAGE DITCH CORRECTION | 2 of 2 | $1,317,907 | +7.0% |
| 06 APR 2022 | R-41598-B | Vincennes | ASPHALT RESURFACE | 2 of 3 | $14,313,590 | +4.0% |
How this record was read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Every bid counted here matched its published total to within one dollar; INDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.