INDOT contract B-43226-A bid tabulation
SMALL STRUCTURES AND DRAINS CONSTRUCTION. Let by Indiana DOT on January 15, 2025, Vanderburgh, Vincennes. 6 bids received; low bid $986,053 by Deig Brothers Lumber & Constr.
- Owner
- Indiana DOT
- Letting
- 15 JAN 2025
- Pay items
- 52
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Deig Brothers Lumber & Constr | $986,053 | Low |
| 2 | Ragle, Inc. | $1,066,249 | +8.0% |
| 3 | S.A.M.M. Trucking & Excavating Inc | $1,086,074 | +10% |
| 4 | Koberstein Contracting Inc | $1,187,996 | +20% |
| 5 | E & B Paving LLC | $1,263,052 | +28% |
| 6 | Yardberry Landscape Company | $1,857,586 | +88% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Deig Brothers Lumber & Constr | 2. Ragle, Inc. | 3. S.A.M.M. Trucking & Excavating Inc | 4. Koberstein Contracting Inc | 5. E & B Paving LLC | 6. Yardberry Landscape Company |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $15,500 | $23,230 | $24,000 | $24,000 | $36,140 | $35,000 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 2 | $1,100.00 | $850.00 | $450.00 | $910.00 | $4,500.00 | $1,000.00 |
| 0003 | Inspection hole, 3 FT deep or less (107-09367) | EACH | 3 | $918.00 | $820.00 | $270.00 | $920.00 | $4,000.00 | $750.00 |
| 0004 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $48,000 | $47,598 | $54,000 | $62,500 | $62,500 | $100,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $40,500 | $18,985 | $21,000 | $20,800 | $19,570 | $30,000 |
| 0011 | Catch basin, remove (202-02928) | EACH | 2 | $1,235.00 | $750.00 | $680.00 | $460.00 | $2,450.00 | $1,000.00 |
| 0012 | Inlet, remove (202-91385) | EACH | 4 | $1,235.00 | $275.00 | $340.00 | $460.00 | $2,450.00 | $1,000.00 |
| 0013 | Pipe, remove (202-96133) | LFT | 209 | $21.00 | $18.00 | $25.00 | $9.00 | $25.00 | $70.00 |
| 0014 | Pipe end section, remove (202-98488) | EACH | 2 | $517.00 | $275.00 | $365.00 | $400.00 | $1,050.00 | $500.00 |
| 0015 | Excavation, common (203-02000) | CYS | 32 | $177.00 | $85.00 | $80.00 | $1,700.00 | $105.00 | $150.00 |
| 0016 | Pump around (205-11626) | EACH | 8 | $6,007.00 | $7,200.00 | $15,000 | $6,300.00 | $7,000.00 | $5,000.00 |
| 0017 | Stormwater management budget (205-12108) | DOL | 16,900 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0018 | Stormwater management implementation (205-12616) | LS | 1 | $10,000 | $7,850.00 | $2,500.00 | $10,000 | $35,000 | $20,000 |
| 0019 | Structure backfill, type 2 (211-09265) | CYS | 109 | $57.00 | $76.00 | $60.00 | $72.00 | $70.00 | $150.00 |
| 0020 | Flowable backfill, non- removable (213-09269) | CYS | 21 | $1,370.00 | $810.00 | $600.00 | $670.00 | $1,500.00 | $250.00 |
| 0021 | Riprap, class 1 (616-05688) | TON | 20 | $130.00 | $91.00 | $140.00 | $121.00 | $165.00 | $180.00 |
| 0022 | Riprap , class I modified (616-06396) | TON | 5 | $130.00 | $145.00 | $260.00 | $326.00 | $215.00 | $600.00 |
| 0023 | Riprap, revetment (616-06405) | TON | 33 | $128.00 | $88.00 | $135.00 | $152.00 | $160.00 | $150.00 |
| 0024 | Geotextile for riprap, type 1A (616-12246) | SYS | 105 | $11.00 | $5.00 | $5.00 | $21.00 | $5.50 | $20.00 |
| 0025 | Mobilization and demobilization for seeding (621-01004) | EACH | 6 | $1,060.00 | $1,050.00 | $1,050.00 | $450.00 | $1,050.00 | $700.00 |
| 0026 | Erosion control blanket (621-02770) | SYS | 30 | $99.50 | $12.00 | $100.00 | $6.00 | $98.40 | $15.00 |
| 0027 | Mulched seeding, type U (621-06560) | SYS | 1,338 | $8.00 | $7.77 | $8.00 | $1.00 | $7.77 | $2.00 |
| 0028 | Computer system equipment (628-11976) | EACH | 2 | $1,730.00 | $1,110.00 | $500.00 | $1,143.00 | $700.00 | $1,500.00 |
| 0029 | Field office, type D (628-12683) | MOS | 12 | $2,415.00 | $5,375.00 | $1,300.00 | $3,300.00 | $3,350.00 | $2,500.00 |
| 0030 | Pipe, type 1, circular, diameter 15 in. (715-05119) | LFT | 75 | $453.00 | $113.00 | $75.00 | $145.00 | $220.00 | $120.00 |
| 0031 | Pipe, type 1, circular, diameter 18 in. (715-05121) | LFT | 18 | $328.00 | $65.00 | $78.00 | $215.00 | $225.00 | $150.00 |
| 0032 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 141 | $107.00 | $74.00 | $58.00 | $140.00 | $115.00 | $110.00 |
| 0033 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 117 | $119.00 | $84.00 | $75.00 | $145.00 | $120.00 | $120.00 |
| 0034 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 95 | $170.00 | $85.00 | $78.00 | $166.00 | $135.00 | $140.00 |
| 0035 | Video inspection for pipe (715-09064) | LFT | 446 | $6.00 | $2.00 | $3.50 | $6.00 | $5.75 | $25.00 |
| 0036 | Pipe end section, diameter 15 in. (715-46005) | EACH | 3 | $1,385.00 | $1,125.00 | $1,300.00 | $2,500.00 | $1,400.00 | $2,500.00 |
| 0037 | Pipe end section, diameter 18 in. (715-46010) | EACH | 3 | $1,495.00 | $1,232.00 | $1,350.00 | $2,600.00 | $1,510.00 | $3,000.00 |
| 0038 | Pipe installation, trenchless, 15 in. (716-07631) | LFT | 197 | $832.00 | $810.00 | $900.00 | $1,030.00 | $780.00 | $2,100.00 |
| 0039 | Pipe installation, trenchless, 18 in. (716-07632) | LFT | 213 | $792.00 | $825.00 | $1,000.00 | $1,100.00 | $1,200.00 | $2,300.00 |
| 0040 | Inlet, type E7 (720-45030) | EACH | 1 | $3,700.00 | $2,725.00 | $4,000.00 | $5,100.00 | $4,250.00 | $3,500.00 |
| 0041 | Inlet, type P12A (720-45070) | EACH | 7 | $5,155.00 | $3,600.00 | $4,500.00 | $6,500.00 | $5,100.00 | $4,000.00 |
| 0042 | Manhole, type C4 (720-45410) | EACH | 1 | $5,125.00 | $5,208.00 | $14,000 | $6,700.00 | $8,050.00 | $5,000.00 |
| 0043 | Inlet, type N12A (720-91246) | EACH | 1 | $6,970.00 | $5,153.00 | $5,500.00 | $6,700.00 | $6,700.00 | $6,000.00 |
| 0044 | Construction sign, type A (801-06640) | EACH | 21 | $147.00 | $145.00 | $145.00 | $223.00 | $203.00 | $225.00 |
| 0045 | Construction sign, type B (801-06645) | EACH | 14 | $90.00 | $89.00 | $89.00 | $111.00 | $101.00 | $180.00 |
| 0046 | Flashing arrow sign (801-06710) | DAY | 60 | $15.00 | $15.00 | $15.00 | $17.00 | $15.00 | $50.00 |
| 0047 | Maintaining traffic (801-06775) | LS | 1 | $41,530 | $65,912 | $48,650 | $60,000 | $100,000 | $150,000 |
| 0048 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 8 | $6,155.00 | $5,615.00 | $6,500.00 | $6,100.00 | $6,100.00 | $13,000 |
| 0049 | Barricade, type III-A (801-07118) | LFT | 24 | $15.00 | $14.00 | $14.00 | $17.00 | $15.09 | $20.00 |
| 0050 | Temporary traffic barrier, type 2 (801-08401) | LFT | 2,592 | $34.00 | $80.00 | $60.00 | $52.00 | $63.00 | $75.00 |
| 0051 | Portable changeable message sign (801-11642) | EACH | 2 | $3,600.00 | $3,500.00 | $3,500.00 | $3,511.00 | $3,511.00 | $3,500.00 |
| 0052 | Law enforcement officer (801-12324) | HRS | 250 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 15, 2025. Compiled by Mirage Metrics.