INDOT contract R-42808-A bid tabulation
ROAD RECONSTRUCTION. Let by Indiana DOT on December 10, 2025, Posey, Vincennes. 4 bids received; low bid $5,640,528 by Ragle, Inc..
- Owner
- Indiana DOT
- Letting
- 10 DEC 2025
- Pay items
- 166
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ragle, Inc. | $5,640,528 | Low |
| 2 | Lutgring Brothers Inc | $5,795,000 | +3.0% |
| 3 | Blankenberger Brothers Inc | $5,798,000 | +3.0% |
| 4 | Deig Brothers Lumber & Constr | $6,337,908 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ragle, Inc. | 2. Lutgring Brothers Inc | 3. Blankenberger Brothers Inc | 4. Deig Brothers Lumber & Constr |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $100,000 | $55,000 | $82,000 | $150,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $280,000 | $285,000 | $289,900 | $305,000 |
| 0011 | Tree, 6 in., remove (201-02245) | EACH | 6 | $250.00 | $210.00 | $250.00 | $756.00 |
| 0012 | Tree, 10 in., remove (201-02250) | EACH | 5 | $490.00 | $400.00 | $490.00 | $1,008.00 |
| 0013 | Tree, 18 in., remove (201-02255) | EACH | 1 | $1,250.00 | $1,440.00 | $1,250.00 | $2,419.00 |
| 0014 | Tree, 30 in., remove (201-02260) | EACH | 4 | $2,287.50 | $2,550.00 | $2,250.00 | $3,629.00 |
| 0015 | Tree, 60 in., remove (201-02270) | EACH | 1 | $4,500.00 | $4,800.00 | $4,500.00 | $4,838.00 |
| 0016 | Clearing right-of-way (201-52370) | LS | 1 | $112,000 | $110,000 | $115,960 | $95,000 |
| 0017 | Pavement removal (202-02240) | SYS | 1,103 | $16.00 | $16.00 | $10.50 | $23.00 |
| 0018 | Pipe abandon and grout fill (202-02637) | LFT | 1,140 | $14.00 | $19.00 | $12.00 | $19.00 |
| 0019 | Pipe abandon and grout fill , asbestos-cement pipe (202-02637) | LFT | 114 | $25.00 | $51.00 | $26.00 | $51.00 |
| 0020 | Regulated asbestos containing materials, remove (202-03729) | LFT | 33 | $50.00 | $193.00 | $60.00 | $193.00 |
| 0021 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $45,000 | $30,000 | $34,000 | $31,490 |
| 0022 | Detector housing, remove (202-90277) | EACH | 2 | $300.00 | $650.00 | $160.00 | $692.00 |
| 0023 | Fire hydrant assembly, remove (202-97009) | EACH | 1 | $1,750.00 | $1,240.00 | $950.00 | $1,240.00 |
| 0024 | Excavation, common (203-02000) | CYS | 12,246 | $26.00 | $27.25 | $33.00 | $32.50 |
| 0025 | Excavation, waterway (203-51223) | CYS | 26 | $75.00 | $150.00 | $100.00 | $74.00 |
| 0026 | Pump around (205-11626) | EACH | 2 | $20,000 | $15,000 | $20,000 | $43,950 |
| 0027 | Stormwater management budget (205-12108) | DOL | 96,779.93 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0028 | Stormwater management implementation (205-12616) | LS | 1 | $20,000 | $12,000 | $23,000 | $35,275 |
| 0029 | SWQCP preparation (205-12618) | LS | 1 | $5,000.00 | $9,000.00 | $1,900.00 | $2,520.00 |
| 0030 | Subgrade treatment, type II (207-08264) | SYS | 1,850 | $30.00 | $35.00 | $30.50 | $33.00 |
| 0031 | Subgrade treatment, type ibc (207-12635) | SYS | 16,064 | $12.00 | $13.00 | $11.75 | $15.50 |
| 0032 | B borrow (211-02050) | CYS | 363 | $68.00 | $168.00 | $88.00 | $112.00 |
| 0033 | Structure backfill, type 2 (211-09265) | CYS | 1,311 | $80.00 | $80.00 | $90.00 | $56.50 |
| 0034 | Structure backfill, type 5 (211-09268) | CYS | 863 | $258.00 | $205.00 | $190.00 | $215.00 |
| 0035 | Geogrid, type IB (214-11796) | SYS | 1,349 | $2.25 | $5.00 | $3.00 | $5.40 |
| 0036 | Geotextile for pavement, type 2A (214-12238) | SYS | 482 | $3.55 | $6.00 | $4.75 | $6.50 |
| 0037 | Compacted aggregate, no. 5 (301-12232) | CYS | 75 | $85.00 | $140.00 | $85.00 | $112.00 |
| 0038 | Compacted aggregate, no. 8 (301-12233) | CYS | 24 | $66.00 | $200.00 | $67.00 | $136.00 |
| 0039 | Compacted aggregate, no. 53 (301-12234) | CYS | 1,652 | $110.00 | $113.00 | $97.50 | $98.00 |
| 0040 | Dense graded subbase (302-07455) | CYS | 310 | $139.00 | $155.00 | $126.00 | $142.00 |
| 0041 | Compacted aggregate, no. 53 (303-01180) | TON | 204 | $60.00 | $90.00 | $95.00 | $79.00 |
| 0042 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 988 | $130.00 | $130.00 | $130.00 | $142.00 |
| 0043 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 1,629 | $108.00 | $108.00 | $108.00 | $116.00 |
| 0044 | QC/QA-HMA, 3, 58S, base, 19.0 MM (401-000053) | TON | 4,561 | $91.00 | $91.00 | $91.00 | $114.00 |
| 0045 | Joint adhesive (401-11526) | LFT | 8,874 | $0.25 | $0.25 | $0.25 | $0.30 |
| 0046 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 4,657 | $4.75 | $4.75 | $4.75 | $5.30 |
| 0047 | Asphalt for tack coat (406-05520) | TON | 13 | $675.00 | $675.00 | $675.00 | $608.00 |
| 0048 | D-1 contraction joint (503-05240) | LFT | 48 | $14.00 | $60.00 | $86.00 | $26.00 |
| 0049 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 43.75 | $23.00 | $23.00 | $23.00 | $23.00 |
| 0050 | Guardrail transition, MGS with curb (601-12291) | EACH | 2 | $3,681.00 | $3,681.00 | $3,685.00 | $3,710.00 |
| 0051 | Guardrail end treatment, type OS (601-94689) | EACH | 2 | $2,425.00 | $2,425.00 | $2,425.00 | $2,445.00 |
| 0052 | Sidewalk, concrete (604-06070) | SYS | 3,228 | $56.00 | $49.00 | $72.00 | $56.00 |
| 0053 | Sidewalk, concrete , 9 in (604-06070) | SYS | 26 | $190.00 | $190.00 | $109.00 | $91.00 |
| 0054 | Curb ramp, concrete (604-08086) | SYS | 345 | $140.00 | $160.00 | $190.00 | $126.00 |
| 0055 | Detectable warning surfaces , brick (604-12083) | SYS | 35 | $215.00 | $205.00 | $530.00 | $208.00 |
| 0056 | Curb, integral concrete (605-06090) | LFT | 85 | $28.00 | $44.00 | $35.00 | $36.00 |
| 0057 | Curb and gutter, concrete (605-06140) | LFT | 6,761 | $26.00 | $32.75 | $29.00 | $29.00 |
| 0058 | Curb and gutter, concrete, type B (605-06145) | LFT | 691 | $24.05 | $33.00 | $35.00 | $29.00 |
| 0059 | Gutter, concrete, type A (607-06175) | LFT | 12 | $42.00 | $114.00 | $300.00 | $56.00 |
| 0060 | PCCP for approaches, 6 in. (610-08446) | SYS | 502 | $70.00 | $57.00 | $88.00 | $58.00 |
| 0061 | PCCP for approaches, 9 in. (610-09108) | SYS | 1,349 | $91.00 | $68.00 | $100.00 | $69.00 |
| 0062 | Mailbox assembly, single (611-06497) | EACH | 7 | $250.00 | $250.00 | $250.00 | $252.00 |
| 0063 | Monument, type B (615-06505) | EACH | 13 | $1,200.00 | $1,200.00 | $1,200.00 | $1,210.00 |
| 0064 | Riprap, class 1 (616-05688) | TON | 139 | $130.00 | $122.00 | $65.00 | $98.00 |
| 0065 | Riprap, revetment (616-06405) | TON | 479 | $88.00 | $100.00 | $90.00 | $95.00 |
| 0066 | Decorative stone (616-11736) | TON | 9 | $160.00 | $175.00 | $425.00 | $163.00 |
| 0067 | Geotextile for riprap, type 1A (616-12246) | SYS | 1,054 | $2.25 | $6.00 | $3.50 | $6.00 |
| 0068 | Mobilization and demobilization for seeding (621-01004) | EACH | 6 | $1,050.00 | $1,050.00 | $1,050.00 | $1,059.00 |
| 0069 | Erosion control blanket (621-02770) | SYS | 1,352 | $3.30 | $3.30 | $3.30 | $3.40 |
| 0070 | Seed mixture, type U (621-06554) | LBS | 590 | $5.00 | $29.44 | $29.50 | $30.00 |
| 0071 | Mulching material (621-06565) | TON | 6 | $2,255.00 | $2,255.00 | $2,255.00 | $2,273.00 |
| 0072 | Water (621-06567) | KGAL | 24 | $2.00 | $2.00 | $2.00 | $2.00 |
| 0073 | Sodding, nursery (621-06575) | SYS | 5,840 | $9.00 | $6.10 | $6.10 | $6.00 |
| 0074 | Weed barrier (621-09273) | SYS | 40 | $7.00 | $22.00 | $22.00 | $7.00 |
| 0075 | Plant, deciduous tree, single stem, over 2 in. to 2.5 in. (622-05650) | EACH | 10 | $577.00 | $577.00 | $577.00 | $581.00 |
| 0076 | Field office, type C (628-09403) | MOS | 12 | $2,100.00 | $3,250.00 | $2,400.00 | $2,170.00 |
| 0077 | Computer system equipment (628-11976) | EACH | 1 | $1,000.00 | $1,800.00 | $500.00 | $2,284.00 |
| 0078 | Computer system (628-11977) | EACH | 1 | $1,000.00 | $1,800.00 | $2,200.00 | $1,713.00 |
| 0079 | Topsoil processing and distribution (629-000149) | SYS | 18,075 | $3.50 | $5.00 | $0.85 | $6.50 |
| 0080 | Topsoil amendment budget (629-000150) | DOL | 36,150.20 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0081 | Test pile, indicator, production (701-09558) | LFT | 124 | $110.00 | $125.00 | $215.00 | $157.00 |
| 0082 | Test pile, indicator, restrike (701-09560) | EACH | 2 | $2,200.00 | $5,000.00 | $4,500.00 | $9,026.00 |
| 0083 | Pile shoe, HP 12 X 74 (701-09683) | EACH | 25 | $150.00 | $250.00 | $140.00 | $126.00 |
| 0084 | Pile, steel H, HP 12 X 74 (701-95780) | LFT | 1,326 | $115.00 | $90.00 | $122.65 | $170.00 |
| 0085 | Reinforcing bars, epoxy coated (703-06029) | LBS | 7,393 | $2.00 | $2.70 | $2.50 | $2.98 |
| 0086 | Concrete, C, superstructure (704-51002) | CYS | 13.50 | $380.00 | $800.00 | $630.00 | $570.00 |
| 0087 | Concrete bridge railing transition, type TPS-1 (706-06353) | EACH | 4 | $5,200.00 | $3,300.00 | $8,500.00 | $9,070.00 |
| 0088 | Reinforced concrete moment slab, 12 in. (706-08496) | SYS | 128 | $160.00 | $260.00 | $305.00 | $186.00 |
| 0089 | Railing, steel type PS-1 (706-11418) | LFT | 98 | $122.00 | $122.00 | $122.00 | $123.00 |
| 0090 | Railing, concrete type PS-1 (706-11604) | CYS | 7.20 | $3,000.00 | $1,750.00 | $3,100.00 | $4,375.00 |
| 0091 | Surface seal , bridge no 1 (709-51821) | LS | 1 | $1.00 | $5,000.00 | $810.00 | $6,552.00 |
| 0092 | Waterproofing membrane, type 2 (714-000086) | SFT | 3,579 | $3.00 | $6.00 | $2.50 | $3.50 |
| 0093 | Structure, reinforced concrete, box sections, 13 FT X 7 FT (714-11444) | LFT | 52 | $3,500.00 | $3,100.00 | $2,750.00 | $4,080.00 |
| 0094 | Valve box , remove (715-01525) | EACH | 1 | $40.00 | $465.00 | $220.00 | $465.00 |
| 0095 | Pipe end section, min. area 5.1 SFT (715-04555) | EACH | 2 | $2,400.00 | $3,200.00 | $2,950.00 | $3,016.00 |
| 0096 | Line stop , 12 in (715-04995) | EACH | 10 | $9,000.00 | $19,660 | $14,850 | $19,660 |
| 0097 | Line stop , 6 in. (715-04995) | EACH | 4 | $5,500.00 | $14,640 | $10,600 | $14,640 |
| 0098 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 1,179 | $58.00 | $57.00 | $85.00 | $91.00 |
| 0099 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 37 | $63.00 | $115.00 | $100.00 | $111.00 |
| 0100 | Pipe, type 2, circular, diameter 30 in. (715-05156) | LFT | 106 | $160.00 | $219.00 | $150.00 | $228.00 |
| 0101 | Pipe, type 3, circular, diameter 24 in. (715-05173) | LFT | 65 | $130.00 | $132.00 | $108.00 | $190.00 |
| 0102 | Pipe, sanitary sewer, diameter 6 in. , SDR-21 PVC (715-05711) | LFT | 270 | $84.00 | $147.00 | $82.00 | $147.00 |
| 0103 | Video inspection for pipe (715-09064) | LFT | 1,427 | $2.00 | $5.00 | $2.30 | $2.30 |
| 0104 | Pipe, type 3, deformed, min. area 5.1 SFT (715-09769) | LFT | 44 | $275.00 | $284.00 | $200.00 | $358.00 |
| 0105 | Water service connection , 2 in (715-11896) | EACH | 1 | $3,500.00 | $6,400.00 | $4,000.00 | $6,400.00 |
| 0106 | Gate valve and valve box, 12 in. , C900 (715-12674) | EACH | 1 | $6,300.00 | $5,318.00 | $5,700.00 | $5,318.00 |
| 0107 | Pipe end section, diameter 12 in. (715-46000) | EACH | 15 | $1,050.00 | $750.00 | $700.00 | $1,032.00 |
| 0108 | Pipe end section, diameter 15 in. (715-46005) | EACH | 1 | $1,125.00 | $900.00 | $750.00 | $1,174.00 |
| 0109 | Pipe end section, diameter 24 in. (715-46020) | EACH | 2 | $1,600.00 | $1,500.00 | $1,500.00 | $1,873.00 |
| 0110 | Pipe end section, diameter 30 in. (715-46030) | EACH | 2 | $2,000.00 | $2,000.00 | $1,500.00 | $2,300.00 |
| 0111 | Tapping sleeve with valve , 12 in X 12 in (715-90853) | EACH | 4 | $13,000 | $15,212 | $14,000 | $15,212 |
| 0112 | Tapping sleeve with valve , 12 in X 6 in (715-90853) | EACH | 1 | $9,000.00 | $7,966.00 | $8,900.00 | $7,966.00 |
| 0113 | Tapping sleeve with valve , 12 in X 8 in (715-90853) | EACH | 1 | $11,000 | $9,974.00 | $10,000 | $9,974.00 |
| 0116 | Water main, 8 in. , C900 (715-93913) | LFT | 68 | $175.00 | $206.00 | $180.00 | $206.00 |
| 0118 | Gate valve, 8 in. , with valve box (715-96948) | EACH | 1 | $3,300.00 | $3,093.00 | $3,600.00 | $3,093.00 |
| 0119 | Water main, 12 in. , C900 (715-98165) | LFT | 354 | $285.00 | $278.00 | $280.00 | $278.00 |
| 0120 | Inlet, type HA5, modified , modified (720-09079) | EACH | 9 | $3,600.00 | $3,600.00 | $4,900.00 | $4,860.00 |
| 0121 | Casting, manhole, adjust to grade (720-12798) | EACH | 4 | $900.00 | $1,600.00 | $900.00 | $963.00 |
| 0122 | Inlet, type E7 (720-45030) | EACH | 3 | $3,000.00 | $2,400.00 | $3,000.00 | $3,430.00 |
| 0123 | Inlet, type F7 (720-45035) | EACH | 1 | $3,000.00 | $3,200.00 | $3,000.00 | $3,696.00 |
| 0124 | Inlet, type E7, modified (720-45130) | EACH | 2 | $3,100.00 | $2,600.00 | $3,000.00 | $3,430.00 |
| 0125 | Inlet, type F7, modified (720-45135) | EACH | 2 | $3,100.00 | $2,700.00 | $3,000.00 | $3,698.00 |
| 0126 | Manhole, type C4, modified (720-45510) | EACH | 1 | $6,000.00 | $3,600.00 | $4,300.00 | $8,015.00 |
| 0127 | Manhole, type N4 , modified (720-91110) | EACH | 1 | $30,000 | $22,000 | $18,650 | $29,000 |
| 0128 | Inlet, type B15, modified (720-93409) | EACH | 21 | $4,500.00 | $4,800.00 | $3,900.00 | $4,805.00 |
| 0129 | Inlet, type C15, modified (720-93411) | EACH | 18 | $4,500.00 | $4,900.00 | $3,900.00 | $5,072.00 |
| 0130 | Fire hydrant assembly , valve and fittings (720-96999) | EACH | 3 | $11,000 | $10,770 | $11,000 | $10,770 |
| 0131 | Inlet, type B15 (720-98174) | EACH | 1 | $4,500.00 | $5,400.00 | $3,900.00 | $4,695.00 |
| 0132 | Manhole, type L4, modified (720-98869) | EACH | 1 | $15,000 | $9,800.00 | $10,750 | $14,615 |
| 0133 | Structure, coated reinforced concrete, three-sided sections, 432 in. X 118 in. (723-000096) | LFT | 50 | $12,000 | $10,030 | $8,100.00 | $8,018.00 |
| 0134 | Road closure sign assembly (801-04308) | EACH | 14 | $261.00 | $345.00 | $345.00 | $377.00 |
| 0135 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 7,150 | $1.46 | $2.45 | $2.45 | $2.70 |
| 0136 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 1,740 | $1.72 | $2.95 | $2.95 | $3.25 |
| 0137 | Detour route marker assembly (801-06625) | EACH | 54 | $158.00 | $120.00 | $120.00 | $131.00 |
| 0138 | Construction sign, type A (801-06640) | EACH | 47 | $227.00 | $195.00 | $195.00 | $213.00 |
| 0139 | Construction sign, type B (801-06645) | EACH | 6 | $112.00 | $98.00 | $98.00 | $107.00 |
| 0140 | Maintaining traffic (801-06775) | LS | 1 | $53,000 | $78,864 | $188,024 | $98,466 |
| 0141 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $5,500.00 | $6,107.00 | $6,200.00 | $6,155.00 |
| 0142 | Barricade, type III-B (801-07119) | LFT | 336 | $15.44 | $16.00 | $16.00 | $17.50 |
| 0143 | Temporary traffic barrier, type 2 (801-08401) | LFT | 314 | $50.00 | $50.00 | $85.00 | $57.00 |
| 0144 | Temporary pedestrian channelizer (801-12862) | LFT | 32 | $25.00 | $35.00 | $92.00 | $38.00 |
| 0145 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 320 | $20.00 | $27.00 | $27.00 | $28.00 |
| 0146 | Sign, sheet, relocate (802-07060) | EACH | 2 | $80.00 | $160.00 | $160.00 | $170.00 |
| 0147 | Sign, double-faced, sheet, with legend, 0.080 in. thickness (802-09837) | SFT | 5 | $40.00 | $45.00 | $45.00 | $48.00 |
| 0148 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 141 | $23.00 | $28.00 | $28.00 | $30.00 |
| 0149 | Sign, double-faced, sheet, with legend, 0.100 in. thickness (802-09839) | SFT | 34 | $25.00 | $45.00 | $45.00 | $48.00 |
| 0150 | Solar powered flashing beacon assembly (805-06742) | EACH | 2 | $15,000 | $14,800 | $14,800 | $15,750 |
| 0151 | Signal cable, roadway loop, copper, 1C/14 gauge (805-78470) | LFT | 950 | $1.25 | $1.20 | $1.20 | $1.30 |
| 0152 | Signal detector housing (805-78785) | EACH | 2 | $1,500.00 | $3,750.00 | $3,750.00 | $3,990.00 |
| 0153 | Saw cut for roadway loop detector and sealant (805-78795) | LFT | 385 | $10.00 | $11.00 | $11.00 | $11.70 |
| 0154 | Pavement message marking, remove (808-05866) | SYS | 4 | $195.00 | $195.00 | $195.00 | $273.00 |
| 0155 | Line, remove (808-06716) | LFT | 870 | $1.25 | $1.25 | $1.25 | $1.40 |
| 0156 | Grooving for pavement markings (808-12032) | LFT | 8,439 | $0.45 | $0.45 | $0.45 | $0.50 |
| 0157 | Line, thermoplastic, solid, white, 10 in. (808-12953) | LFT | 77 | $2.95 | $2.95 | $2.95 | $3.25 |
| 0158 | Transverse marking, thermoplastic, crosswalk line, white, 12 in. (808-74815) | LFT | 236 | $3.95 | $3.95 | $3.95 | $4.30 |
| 0159 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 65 | $1.95 | $1.95 | $1.95 | $2.15 |
| 0160 | Line, thermoplastic, broken, yellow, 4 in. (808-75240) | LFT | 30 | $2.45 | $2.45 | $2.45 | $2.65 |
| 0161 | Line, thermoplastic, solid, yellow, 4 in. (808-75245) | LFT | 7,582 | $0.98 | $0.98 | $0.98 | $1.00 |
| 0162 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 685 | $1.95 | $1.95 | $1.95 | $1.50 |
| 0163 | Transverse marking, thermoplastic, crosshatch line, yellow, 12 in. (808-75278) | LFT | 153 | $3.95 | $3.95 | $3.95 | $4.30 |
| 0164 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 220 | $6.95 | $6.95 | $6.95 | $7.00 |
| 0165 | Transverse marking, thermoplastic, crosswalk line, white, 6 in. (808-75300) | LFT | 558 | $1.95 | $1.95 | $1.95 | $2.10 |
| 0166 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 3 | $150.00 | $150.00 | $150.00 | $164.00 |
| 0167 | Pavement message marking, thermoplastic, RXR (808-75340) | EACH | 2 | $595.00 | $595.00 | $595.00 | $650.00 |
| 0168 | Pavement message marking, thermoplastic, school , zone (808-75350) | EACH | 4 | $595.00 | $595.00 | $595.00 | $650.00 |
| 0169 | Water service connection , 1 in. (715-11896) | EACH | 1 | $3,500.00 | $3,580.00 | $3,000.00 | $3,580.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of December 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.