Weddle Brothers Highway Group LLC: INDOT bid record

Weddle Brothers Highway Group LLC submitted 18 bids on Indiana DOT contracts in the data, from 09 FEB 2022 to 14 JAN 2026, and was the low bidder on 3 of them (17%). When it was not low, its total sat a median +19% above the low bid.

Owner
Indiana DOT
Low bid volume
$3,976,986
Latest bid
14 JAN 2026
Data through
05 NOV 2026
18Bids
3Low bids
17Win rate, percent
+19%Median gap to the low bid when not low, 15 bids

By year

YearBidsLow bidsWin rate
202211218%
20234125%
2024100%
2025100%
2026100%
Weddle Brothers Highway Group LLC, INDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
Vincennes9222%
Seymour4125%
Crawfordsville300%
Greenfield200%
Weddle Brothers Highway Group LLC, INDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Liquidated damages109-08359DOL1818 (100%)$1.00$1.00
Contract liens109-08360DOL1818 (100%)$1.00$1.00
Quality adjustments, failed materials109-08444DOL1818 (100%)$1.00$1.00
Quality adjustments, temporary traffic control devices109-08443DOL1818 (100%)$1.00$1.00
Project estimate adjustment109-08463DOL1111 (100%)$1.00$1.00
Quality adjustments, HMA109-08440DOL99 (100%)$1.00$1.00
Payment adjustment PG asphalt binder109-09489DOL88 (100%)$1.00$1.00
Portable changeable message sign801-11642EACH107 (70%)$4,205.00$4,500.00
Quality adjustments, failure to maintain temporary erosion and sediment control measures109-11362DOL77 (100%)$1.00$1.00
Stormwater management budget205-12108DOL66 (100%)$1.00$1.00
Construction sign, A801-06640EACH145 (36%)$175.50$193.50
Construction sign, B801-06645EACH115 (45%)$89.00$98.00
Weddle Brothers Highway Group LLC, INDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Weddle Brothers Highway Group LLC, INDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
14 JAN 2026R-45752-AVincennesSLIDE CORRECTION2 of 6$4,458,700+16%
10 SEP 2025R-43985-AVincennesSLIDE CORRECTION7 of 10$1,038,356+30%
14 NOV 2024R-42005-AVincennesROAD RECONSTRUCTION3 of 6$5,696,989+14%
09 AUG 2023B-42868-ASeymourBRIDGE THIN DECK OVERLAY6 of 6$259,763+60%
19 APR 2023B-43047-AGreenfieldBRIDGE THIN DECK OVERLAY2 of 4$1,001,035+8.0%
15 MAR 2023B-42717-AVincennesBRIDGE THIN DECK OVERLAY2 of 2$6,797,300+4.0%
19 JAN 2023R-41449-AVincennesSLIDE CORRECTION1 of 3$1,163,664Low, 1.0% under the second
07 DEC 2022B-42928-ACrawfordsvilleBRIDGE THIN DECK OVERLAY3 of 3$782,645+11%
13 OCT 2022B-42718-AVincennesBRIDGE THIN DECK OVERLAY2 of 3$828,410+11%
13 OCT 2022B-42719-AVincennesBRIDGE THIN DECK OVERLAY2 of 3$383,930+41%
13 OCT 2022B-42872-ASeymourBRIDGE DECK OVERLAY1 of 5$1,189,222Low, 5.0% under the second
14 SEP 2022B-42925-ACrawfordsvilleBRIDGE THIN DECK OVERLAY2 of 3$756,290+19%
10 AUG 2022B-42862-ASeymourBRIDGE THIN DECK OVERLAY5 of 5$573,120+21%
10 AUG 2022B-43657-BVincennesBRIDGE REPLACEMENT2 of 5$1,168,9000.0%
06 APR 2022B-42083-ASeymourBRIDGE THIN DECK OVERLAY3 of 3$215,738+32%
09 MAR 2022B-42052-ACrawfordsvilleBRIDGE THIN DECK OVERLAY2 of 4$1,530,697+20%
09 MAR 2022B-42205-AGreenfieldBRIDGE THIN DECK OVERLAY3 of 3$299,349+58%
09 FEB 2022R-40561-AVincennesSMALL STRUCTURE REPLACEMENT1 of 6$1,624,100Low, 1.0% under the second
Weddle Brothers Highway Group LLC: latest INDOT bids in the data

How this record was read

INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

  • Every bid counted here matched its published total to within one dollar; INDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy