INDOT contract R-43985-A bid tabulation
SLIDE CORRECTION. Let by Indiana DOT on September 10, 2025, Spencer, Vincennes. 10 bids received; low bid $796,500 by Lutgring Brothers Inc.
- Owner
- Indiana DOT
- Letting
- 10 SEP 2025
- Pay items
- 63
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lutgring Brothers Inc | $796,500 | Low |
| 2 | Ragle, Inc. | $817,282 | +3.0% |
| 3 | E & B Paving LLC | $832,000 | +4.0% |
| 4 | Jbi Construction Inc | $939,973 | +18% |
| 5 | 5 Star Company Inc | $1,000,699 | +26% |
| 6 | Blankenberger Brothers Inc | $1,020,620 | +28% |
| 7 | Weddle Brothers Highway Group LLC | $1,038,356 | +30% |
| 8 | C & R Construction and Consulting LLC | $1,048,497 | +32% |
| 9 | Morphey Construction Inc. | $1,052,000 | +32% |
| 10 | Force Construction Co Inc | $1,057,290 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lutgring Brothers Inc | 2. Ragle, Inc. | 3. E & B Paving LLC | 4. Jbi Construction Inc | 5. 5 Star Company Inc | 6. Blankenberger Brothers Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $7,000.00 | $7,000.00 | $26,952 | $18,600 | $15,000 | $23,383 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 3 | $200.00 | $450.00 | $500.00 | $650.00 | $250.00 | $1,600.00 |
| 0003 | Inspection hole, 3 FT deep or less (107-09367) | EACH | 3 | $200.00 | $325.00 | $500.00 | $360.00 | $225.00 | $850.00 |
| 0004 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $30,478 | $40,000 | $40,000 | $46,500 | $78,000 | $51,030 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $14,000 | $16,000 | $14,500 | $77,600 | $32,000 | $55,000 |
| 0013 | Inlet, remove (202-91385) | EACH | 1 | $750.00 | $275.00 | $670.92 | $650.00 | $150.00 | $120.00 |
| 0014 | Pipe, remove (202-96133) | LFT | 107 | $20.00 | $30.00 | $58.46 | $50.00 | $12.00 | $35.00 |
| 0015 | Excavation, common (203-02000) | CYS | 4,010 | $28.00 | $28.00 | $20.00 | $22.00 | $25.00 | $41.50 |
| 0016 | Stormwater management budget (205-12108) | DOL | 9,004 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0017 | Stormwater management implementation (205-12616) | LS | 1 | $5,000.00 | $2,500.00 | $7,700.00 | $35,000 | $7,500.00 | $10,000 |
| 0018 | SWQCP preparation (205-12618) | LS | 1 | $1,000.00 | $3,500.00 | $3,000.00 | $3,500.00 | $3,500.00 | $1,750.00 |
| 0019 | Subgrade treatment, type II (207-08264) | SYS | 109 | $40.00 | $22.00 | $25.00 | $24.00 | $36.00 | $31.00 |
| 0020 | Subgrade treatment, type IC (207-09935) | SYS | 1,222 | $32.00 | $30.00 | $32.00 | $27.00 | $29.00 | $30.50 |
| 0021 | Structure backfill, type 1 (211-09264) | CYS | 101 | $50.00 | $45.00 | $65.00 | $55.00 | $95.00 | $85.59 |
| 0022 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,222 | $4.00 | $3.75 | $2.48 | $3.00 | $5.00 | $4.00 |
| 0023 | Compacted aggregate, no. 2 (301-12231) | CYS | 376 | $66.00 | $60.00 | $72.00 | $66.00 | $53.00 | $74.00 |
| 0024 | Compacted aggregate, no. 5 (301-12232) | CYS | 215 | $72.00 | $70.00 | $79.00 | $91.50 | $53.00 | $81.00 |
| 0025 | Compacted aggregate, no. 53 (301-12234) | CYS | 332 | $99.00 | $84.00 | $85.00 | $87.00 | $55.00 | $76.00 |
| 0026 | Compacted aggregate, no. 53 (303-01180) | TON | 303 | $60.00 | $40.00 | $52.00 | $37.00 | $41.00 | $50.68 |
| 0027 | Milling, asphalt, 2 in. (306-08036) | SYS | 1,040 | $8.00 | $5.50 | $7.24 | $4.00 | $4.00 | $8.00 |
| 0028 | Milling, approach (306-08432) | SYS | 90 | $16.00 | $7.00 | $10.64 | $8.00 | $4.00 | $8.00 |
| 0029 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 237 | $171.00 | $171.00 | $171.00 | $171.00 | $195.00 | $171.00 |
| 0030 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 153 | $160.00 | $160.00 | $160.00 | $160.00 | $171.00 | $160.00 |
| 0031 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 345 | $108.00 | $108.00 | $108.00 | $108.00 | $155.00 | $108.00 |
| 0032 | Joint adhesive (401-11526) | LFT | 1,306 | $1.60 | $1.60 | $1.60 | $1.60 | $1.00 | $1.60 |
| 0033 | Asphalt for tack coat (406-05520) | TON | 2 | $1.00 | $1.00 | $1.00 | $1.00 | $1,000.00 | $1.00 |
| 0034 | HMA for approaches, type B (610-07487) | TON | 29 | $252.00 | $252.00 | $252.00 | $252.00 | $171.00 | $252.00 |
| 0035 | Mailbox assembly, reset, single (611-08232) | EACH | 1 | $625.00 | $300.00 | $625.00 | $450.00 | $200.00 | $600.00 |
| 0036 | Riprap, class 1 (616-05688) | TON | 4,142 | $40.00 | $40.00 | $40.25 | $45.00 | $65.00 | $44.50 |
| 0037 | Riprap, uniform (616-06451) | TON | 1,319 | $42.50 | $45.00 | $40.25 | $47.00 | $55.00 | $58.00 |
| 0038 | Geotextile for riprap, type 1A (616-12246) | SYS | 3,503 | $2.50 | $2.50 | $1.59 | $1.00 | $6.00 | $2.50 |
| 0039 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $1,050.00 | $500.00 | $1,000.00 | $1,050.00 | $550.00 | $500.00 |
| 0040 | Erosion control blanket (621-02770) | SYS | 944 | $3.61 | $2.00 | $2.25 | $3.61 | $2.00 | $2.00 |
| 0041 | Mulched seeding, type R (621-06559) | SYS | 944 | $3.00 | $2.75 | $2.25 | $3.00 | $2.50 | $2.75 |
| 0042 | Computer system equipment (628-11976) | EACH | 1 | $800.00 | $1,000.00 | $700.00 | $300.00 | $500.00 | $300.00 |
| 0043 | Field office, type D (628-12683) | MOS | 12 | $1,900.00 | $3,000.00 | $3,050.00 | $3,000.00 | $2,500.00 | $2,200.00 |
| 0044 | Pipe, type 1, circular, diameter 24 in. (715-05123) | LFT | 74 | $82.00 | $135.00 | $180.00 | $150.00 | $80.00 | $170.00 |
| 0045 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 59 | $81.00 | $90.00 | $160.00 | $80.00 | $80.00 | $150.00 |
| 0046 | Pipe end section, diameter 18 in. (715-46010) | EACH | 1 | $1,300.00 | $1,400.00 | $1,200.00 | $1,600.00 | $750.00 | $950.00 |
| 0047 | Pipe end section, diameter 24 in. (715-46020) | EACH | 2 | $1,000.00 | $925.00 | $2,800.00 | $1,800.00 | $1,100.00 | $1,200.00 |
| 0048 | Inlet, type P12A, modified (720-95310) | EACH | 1 | $6,000.00 | $6,500.00 | $5,900.00 | $5,800.00 | $5,000.00 | $6,500.00 |
| 0049 | Road closure sign assembly (801-04308) | EACH | 16 | $389.00 | $250.00 | $389.00 | $389.00 | $205.00 | $265.00 |
| 0050 | Detour route marker assembly (801-06625) | EACH | 36 | $186.00 | $125.00 | $186.00 | $186.00 | $80.00 | $120.00 |
| 0051 | Construction sign, type A (801-06640) | EACH | 18 | $271.00 | $200.00 | $271.00 | $271.00 | $154.00 | $165.00 |
| 0052 | Maintaining traffic (801-06775) | LS | 1 | $4,000.00 | $8,000.00 | $11,061 | $18,000 | $38,000 | $40,000 |
| 0053 | Barricade, type III-A (801-07118) | LFT | 132 | $18.41 | $16.50 | $18.41 | $18.41 | $15.00 | $14.00 |
| 0054 | Barricade, type III-B (801-07119) | LFT | 78 | $18.41 | $19.00 | $18.41 | $18.41 | $16.00 | $14.00 |
| 0055 | Sign, sheet, remove (802-04089) | EACH | 1 | $350.00 | $100.00 | $350.00 | $125.00 | $105.00 | $210.00 |
| 0056 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 39 | $46.00 | $35.00 | $46.00 | $46.00 | $34.00 | $50.00 |
| 0057 | Sign, sheet, relocate (802-07060) | EACH | 6 | $550.00 | $150.00 | $550.00 | $550.00 | $210.00 | $600.00 |
| 0058 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 15 | $48.00 | $40.00 | $48.00 | $48.00 | $27.00 | $48.00 |
| 0059 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 1,304 | $0.83 | $0.30 | $0.83 | $0.83 | $1.30 | $0.30 |
| 0060 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 1,304 | $0.83 | $0.30 | $0.83 | $0.83 | $1.30 | $0.30 |
| 0061 | Snowplowable raised pavement marker (808-75998) | EACH | 18 | $184.00 | $175.00 | $184.00 | $184.00 | $300.00 | $250.00 |
| 0062 | Right-of-way marker (615-06490) | EACH | 14 | $700.00 | $425.00 | $425.00 | $425.00 | $440.00 | $425.00 |
| 0063 | Pavement removal (202-02240) | SYS | 1,071 | $17.00 | $37.00 | $25.00 | $25.00 | $11.00 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of September 10, 2025. Compiled by Mirage Metrics.