INDOT contract B-43235-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on November 13, 2025, Warrick, Vincennes. 6 bids received; low bid $1,490,348 by Ragle, Inc..
- Owner
- Indiana DOT
- Letting
- 13 NOV 2025
- Pay items
- 65
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ragle, Inc. | $1,490,348 | Low |
| 2 | Blankenberger Brothers Inc | $1,588,925 | +7.0% |
| 3 | E & B Paving LLC | $1,651,850 | +11% |
| 4 | Deig Brothers Lumber & Constr | $1,730,093 | +16% |
| 5 | CLR Inc | $1,759,122 | +18% |
| 6 | Force Construction Co Inc | $1,938,075 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ragle, Inc. | 2. Blankenberger Brothers Inc | 3. E & B Paving LLC | 4. Deig Brothers Lumber & Constr | 5. CLR Inc | 6. Force Construction Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $15,000 | $20,000 | $38,641 | $21,001 | $75,000 | $8,315.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Mobilization and demobilization (110-01001) | LS | 1 | $74,250 | $80,000 | $82,000 | $86,000 | $87,650 | $96,000 |
| 0009 | Clearing right-of-way (201-52370) | LS | 1 | $29,500 | $31,400 | $32,000 | $74,280 | $35,075 | $37,050 |
| 0010 | Present structure, remove, structure no. 068-87-01583 (202-51330) | LS | 1 | $64,500 | $40,000 | $175,000 | $34,025 | $100,000 | $45,270 |
| 0011 | Excavation, common (203-02000) | CYS | 2,695 | $14.00 | $45.90 | $41.88 | $40.00 | $20.00 | $67.00 |
| 0012 | Excavation, unclassified (203-02020) | CYS | 1,030 | $14.00 | $41.15 | $71.61 | $104.00 | $20.00 | $97.00 |
| 0013 | Borrow (203-02070) | CYS | 2,135 | $20.00 | $30.00 | $4.19 | $36.77 | $20.00 | $39.00 |
| 0014 | Excavation, waterway (203-51223) | CYS | 180 | $14.00 | $60.00 | $60.98 | $59.50 | $20.00 | $110.00 |
| 0015 | Pump around (205-11626) | EACH | 1 | $20,000 | $37,000 | $48,000 | $38,900 | $50,000 | $23,010 |
| 0016 | Stormwater management budget (205-12108) | DOL | 22,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0017 | Stormwater management implementation (205-12616) | LS | 1 | $8,000.00 | $25,000 | $38,919 | $14,000 | $5,000.00 | $21,120 |
| 0018 | SWQCP preparation (205-12618) | LS | 1 | $3,000.00 | $10,000 | $1,705.57 | $2,000.00 | $1,200.00 | $3,118.00 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 929 | $45.00 | $50.25 | $66.50 | $61.00 | $65.00 | $27.00 |
| 0020 | Structure backfill, type 2 (211-09265) | CYS | 1,003 | $95.00 | $74.70 | $82.77 | $99.00 | $105.00 | $81.00 |
| 0021 | Geotextile for pavement, type 2B (214-12239) | SYS | 929 | $4.00 | $5.00 | $2.12 | $7.00 | $6.50 | $3.70 |
| 0022 | Compacted aggregate, no. 53 (301-12234) | CYS | 8 | $150.00 | $316.30 | $425.42 | $148.00 | $195.00 | $201.00 |
| 0023 | Compacted aggregate, no. 53 (303-01180) | TON | 189 | $70.00 | $77.45 | $79.28 | $106.00 | $77.00 | $35.00 |
| 0024 | Widening with HMA, type B (304-07493) | TON | 142 | $150.00 | $120.00 | $159.83 | $128.00 | $310.00 | $232.00 |
| 0025 | Milling, transition (306-08043) | SYS | 1,147 | $7.00 | $5.20 | $7.38 | $14.00 | $5.00 | $4.60 |
| 0026 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 149 | $170.00 | $170.00 | $173.40 | $181.00 | $345.00 | $244.00 |
| 0027 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 104 | $160.00 | $160.00 | $148.00 | $170.00 | $160.00 | $177.00 |
| 0028 | QC/QA-HMA, 4, 58S, base, 25.0 MM (401-000048) | TON | 256 | $120.00 | $120.00 | $108.00 | $128.00 | $120.00 | $160.00 |
| 0029 | Joint adhesive (401-11526) | LFT | 1,100 | $0.75 | $0.75 | $1.09 | $0.80 | $0.75 | $1.30 |
| 0030 | Asphalt for tack coat (406-05521) | SYS | 3,160 | $0.25 | $0.25 | $0.22 | $0.27 | $0.25 | $0.30 |
| 0031 | D-1 contraction joint (503-05240) | LFT | 76 | $30.00 | $78.50 | $92.74 | $25.00 | $75.00 | $62.00 |
| 0032 | Guardrail, remove (601-02241) | LFT | 633 | $2.00 | $2.00 | $5.33 | $2.20 | $2.25 | $2.10 |
| 0033 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 50 | $20.00 | $20.00 | $21.32 | $21.30 | $22.50 | $21.00 |
| 0034 | Guardrail transition, MGS without curb (601-12292) | EACH | 4 | $3,200.00 | $3,200.00 | $3,571.03 | $3,405.00 | $3,610.00 | $3,326.00 |
| 0035 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $2,900.00 | $2,900.00 | $3,171.29 | $3,087.00 | $3,270.00 | $3,014.00 |
| 0036 | Milled HMA corrugations, conventional (606-12399) | LFT | 1,650 | $3.56 | $5.50 | $4.05 | $4.20 | $3.00 | $8.30 |
| 0037 | Right-of-way marker (615-06490) | EACH | 10 | $173.00 | $173.00 | $170.56 | $184.00 | $135.00 | $180.00 |
| 0038 | Monument, type B (615-06505) | EACH | 2 | $979.00 | $979.00 | $1,071.31 | $1,042.00 | $750.00 | $1,018.00 |
| 0039 | Riprap, revetment (616-06405) | TON | 1,232 | $65.00 | $63.00 | $69.75 | $89.00 | $74.00 | $75.00 |
| 0040 | Geotextile for riprap, type 1A (616-12246) | SYS | 1,255 | $3.50 | $3.80 | $2.10 | $5.74 | $4.75 | $1.50 |
| 0041 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $200.00 | $950.00 | $213.19 | $200.00 | $200.00 | $208.00 |
| 0042 | Erosion control blanket (621-02770) | SYS | 2,573 | $1.75 | $2.10 | $1.87 | $1.90 | $2.00 | $1.80 |
| 0043 | Mulched seeding, type R (621-06559) | SYS | 2,573 | $1.25 | $0.65 | $1.33 | $1.25 | $1.50 | $1.30 |
| 0044 | Plant, deciduous shrub, 36 in. to 48 in. (622-05641) | EACH | 14 | $375.00 | $95.00 | $399.74 | $379.00 | $425.00 | $390.00 |
| 0045 | Computer system equipment (628-11976) | EACH | 2 | $1,000.00 | $500.00 | $746.19 | $1,360.00 | $100.00 | $1,668.00 |
| 0046 | Field office, type D (628-12683) | MOS | 18 | $2,000.00 | $2,890.00 | $2,999.21 | $2,493.00 | $1,250.00 | $6,117.00 |
| 0047 | Reinforcing bars, epoxy coated (703-06029) | LBS | 6,744 | $2.50 | $2.75 | $3.20 | $2.80 | $2.50 | $1.80 |
| 0048 | Reinforced concrete moment slab, 12 in. (706-08496) | SYS | 165 | $246.00 | $320.50 | $272.89 | $251.00 | $295.00 | $520.00 |
| 0049 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $1,395.00 | $1,395.00 | $2,387.80 | $1,786.00 | $2,600.00 | $1,450.00 |
| 0050 | Railing, concrete type C, modified (706-94947) | CYS | 10.70 | $911.00 | $911.00 | $788.83 | $1,062.00 | $950.00 | $947.00 |
| 0051 | Surface seal (709-51821) | LS | 1 | $500.00 | $1.00 | $4,796.91 | $6,558.00 | $500.00 | $4,677.00 |
| 0052 | Waterproofing membrane, type 2 (714-000086) | SFT | 3,658 | $4.25 | $2.65 | $3.97 | $4.80 | $5.00 | $4.70 |
| 0053 | Structure, reinforced concrete, three-sided (723-10171) | LFT | 68 | $9,000.00 | $7,650.00 | $5,371.31 | $6,835.00 | $8,055.00 | $7,099.00 |
| 0054 | Road closure sign assembly (801-04308) | EACH | 3 | $245.00 | $260.00 | $277.15 | $305.00 | $350.00 | $255.00 |
| 0055 | Detour route marker assembly (801-06625) | EACH | 24 | $98.00 | $148.00 | $157.77 | $122.00 | $85.00 | $102.00 |
| 0056 | Construction sign, type A (801-06640) | EACH | 12 | $165.00 | $198.00 | $211.06 | $205.00 | $170.00 | $172.00 |
| 0057 | Maintaining traffic (801-06775) | LS | 1 | $10,000 | $18,287 | $45,082 | $33,000 | $80,000 | $138,001 |
| 0058 | Barricade, type III-A (801-07118) | LFT | 96 | $12.00 | $15.88 | $16.93 | $15.00 | $18.00 | $12.00 |
| 0059 | Barricade, type III-B (801-07119) | LFT | 72 | $12.00 | $15.88 | $16.93 | $15.00 | $20.00 | $12.00 |
| 0060 | Sign, ground mounted, reset (802-91122) | EACH | 6 | $101.00 | $101.00 | $479.69 | $108.00 | $75.00 | $105.00 |
| 0061 | Line, paint, broken, yellow, 6 in. (808-12764) | LFT | 60 | $9.95 | $1.03 | $1.10 | $12.40 | $1.25 | $10.00 |
| 0062 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 1,100 | $0.45 | $0.99 | $1.06 | $0.60 | $1.25 | $0.45 |
| 0063 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 850 | $0.45 | $0.99 | $1.06 | $0.60 | $1.25 | $0.45 |
| 0064 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 13 | $10.00 | $33.09 | $43.71 | $76.00 | $45.00 | $260.00 |
| 0065 | Snowplowable raised pavement marker (808-75998) | EACH | 13 | $245.00 | $189.00 | $201.47 | $305.00 | $75.00 | $255.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of November 13, 2025. Compiled by Mirage Metrics.