INDOT contract B-42240-A bid tabulation
BRIDGE REPLACEMENT AND SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on January 15, 2025, Clay, Vigo, Crawfordsville. 4 bids received; low bid $1,884,651 by Milestone Contractors LP.
- Owner
- Indiana DOT
- Letting
- 15 JAN 2025
- Pay items
- 103
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Milestone Contractors LP | $1,884,651 | Low |
| 2 | Morphey Construction Inc. | $2,033,011 | +8.0% |
| 3 | William Charles Construction Company | $2,178,000 | +16% |
| 4 | CLR Inc | $2,249,545 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Milestone Contractors LP | 2. Morphey Construction Inc. | 3. William Charles Construction Company | 4. CLR Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $29,000 | $15,000 | $75,000 | $60,000 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 4 | $2,300.00 | $1,500.00 | $2,500.00 | $600.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $89,000 | $101,650 | $107,081 | $111,800 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $33,000 | $35,300 | $50,000 | $44,700 |
| 0013 | Center curb, concrete, remove (202-02273) | SYS | 402 | $31.00 | $40.00 | $50.00 | $70.00 |
| 0014 | Present structure, remove, structure no. 340-11-10492 (202-51330) | LS | 1 | $77,000 | $20,000 | $35,000 | $60,000 |
| 0015 | Pipe, remove (202-96133) | LFT | 144 | $260.00 | $40.00 | $60.00 | $175.00 |
| 0016 | Foundation for signing, remove (202-99626) | EACH | 1 | $3,200.00 | $1,000.00 | $1,500.00 | $2,500.00 |
| 0017 | Excavation, common (203-02000) | CYS | 690 | $72.00 | $40.00 | $100.00 | $90.00 |
| 0018 | Pump around (205-11626) | EACH | 2 | $15,540 | $10,000 | $35,000 | $20,000 |
| 0019 | Stormwater management budget (205-12108) | DOL | 34,966 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0020 | Stormwater management implementation (205-12616) | LS | 1 | $8,000.00 | $5,000.00 | $20,000 | $2,500.00 |
| 0021 | Subgrade treatment, type II (207-08264) | SYS | 251 | $27.60 | $20.00 | $25.00 | $15.00 |
| 0022 | Subgrade treatment, type IC (207-09935) | SYS | 1,643 | $28.00 | $40.00 | $60.00 | $49.00 |
| 0023 | Structure backfill, type 2 (211-09265) | CYS | 393 | $110.00 | $98.00 | $30.00 | $108.00 |
| 0024 | Structure backfill, type 5 (211-09268) | CYS | 633 | $172.00 | $150.00 | $125.00 | $130.00 |
| 0025 | Geotextile for pavement, type 2A (214-12238) | SYS | 272 | $6.00 | $3.00 | $7.00 | $6.00 |
| 0026 | Geotextile for pavement, type 2B (214-12239) | SYS | 503 | $6.50 | $4.00 | $8.00 | $7.00 |
| 0027 | Compacted aggregate, no. 5 (301-12232) | CYS | 49 | $260.00 | $120.00 | $130.00 | $145.00 |
| 0028 | Compacted aggregate, no. 53 (301-12234) | CYS | 39 | $260.00 | $120.00 | $120.00 | $160.00 |
| 0029 | Compacted aggregate, no. 53 (303-01180) | TON | 292 | $61.00 | $60.00 | $70.00 | $125.00 |
| 0030 | HMA patching, full depth, type B (304-12623) | TON | 183 | $350.00 | $420.00 | $400.00 | $384.00 |
| 0031 | Milling, asphalt, 2 in. (306-08036) | SYS | 852 | $14.60 | $8.00 | $15.00 | $17.00 |
| 0032 | Milling, profile (306-11872) | SYS | 717 | $12.00 | $8.00 | $10.00 | $18.00 |
| 0033 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 95 | $235.00 | $235.00 | $235.00 | $263.00 |
| 0034 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 147 | $255.00 | $255.00 | $255.00 | $285.00 |
| 0035 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 129 | $245.00 | $245.00 | $245.00 | $245.00 |
| 0036 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 97 | $320.00 | $320.00 | $320.00 | $320.00 |
| 0037 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 393 | $193.00 | $193.00 | $193.00 | $193.00 |
| 0038 | Joint adhesive, surface (401-10258) | LFT | 2,753 | $4.00 | $4.00 | $4.00 | $4.00 |
| 0039 | Joint adhesive, intermediate (401-10259) | LFT | 960 | $4.00 | $4.00 | $4.00 | $4.00 |
| 0040 | Liquid asphalt sealant (401-11785) | LFT | 2,753 | $2.00 | $2.00 | $2.00 | $2.00 |
| 0041 | HMA for temporary pavement, type D (402-10087) | TON | 310 | $150.00 | $218.00 | $200.00 | $150.00 |
| 0042 | Asphalt for tack coat (406-05520) | TON | 2 | $770.00 | $770.00 | $770.00 | $770.00 |
| 0043 | Guardrail, remove (601-02241) | LFT | 171 | $3.00 | $3.00 | $3.00 | $3.25 |
| 0044 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 582 | $18.00 | $18.00 | $18.00 | $20.00 |
| 0045 | Guardrail, MGS, structure top-mounted post (601-12293) | EACH | 12 | $360.00 | $360.00 | $360.00 | $400.00 |
| 0046 | Guardrail, MGS W-beam, cable terminal anchor (601-12294) | EACH | 2 | $1,300.00 | $1,300.00 | $1,300.00 | $1,475.00 |
| 0047 | Guardrail end treatment, type OS (601-94689) | EACH | 6 | $2,900.00 | $2,900.00 | $2,900.00 | $3,250.00 |
| 0048 | Center curb, concrete, type B (605-06245) | SYS | 402 | $132.00 | $183.05 | $220.00 | $277.00 |
| 0049 | HMA for approaches, type B (610-07487) | TON | 43 | $350.00 | $458.76 | $350.00 | $392.00 |
| 0050 | Mailbox assembly, reset, single (611-08232) | EACH | 4 | $200.00 | $200.00 | $200.00 | $200.00 |
| 0051 | Mailbox assembly, reset, double (611-08233) | EACH | 1 | $415.00 | $415.00 | $415.00 | $415.00 |
| 0052 | Right-of-way marker (615-06490) | EACH | 8 | $150.00 | $150.00 | $150.00 | $150.00 |
| 0053 | Monument, type B (615-06505) | EACH | 4 | $950.00 | $950.00 | $950.00 | $950.00 |
| 0054 | Riprap, class 2 (616-05689) | TON | 56 | $170.00 | $150.00 | $120.00 | $175.00 |
| 0055 | Riprap, revetment (616-06405) | TON | 568 | $65.00 | $130.00 | $90.00 | $77.00 |
| 0056 | Riprap, revetment , hand place (616-06405) | TON | 41 | $175.00 | $130.00 | $200.00 | $175.00 |
| 0057 | Slopewall (616-06455) | SYS | 5 | $1.00 | $0.01 | $400.00 | $40.00 |
| 0058 | Geotextile for riprap, type 1A (616-12246) | SYS | 746 | $3.00 | $2.00 | $4.00 | $6.00 |
| 0059 | Mobilization and demobilization for seeding (621-01004) | EACH | 4 | $950.00 | $950.00 | $950.00 | $150.00 |
| 0060 | Mulched seeding, type R (621-06559) | SYS | 2,736 | $1.25 | $7.00 | $1.23 | $2.15 |
| 0061 | Mulching material (621-06565) | TON | 1 | $565.00 | $565.00 | $565.00 | $532.00 |
| 0062 | Water (621-06567) | KGAL | 1 | $175.00 | $175.00 | $175.00 | $1.00 |
| 0063 | Sodding (621-06574) | SYS | 100 | $42.75 | $60.00 | $42.75 | $12.00 |
| 0064 | Seed mixture, emergent wetland (621-06737) | LBS | 1 | $619.00 | $1,000.00 | $619.00 | $600.00 |
| 0065 | Field office, type C (628-09403) | MOS | 8 | $3,400.00 | $3,000.00 | $3,000.00 | $950.00 |
| 0066 | Computer system equipment (628-11976) | EACH | 1 | $1,000.00 | $500.00 | $888.00 | $150.00 |
| 0067 | Concrete, A , headwall (702-90915) | CYS | 21.80 | $2,250.00 | $2,100.00 | $2,000.00 | $1,850.00 |
| 0068 | Concrete, A , sanitary sewer encasement (702-90915) | CYS | 1.20 | $1,500.00 | $2,100.00 | $2,000.00 | $4,000.00 |
| 0069 | Reinforcing bars, epoxy coated (703-06029) | LBS | 2,332 | $4.00 | $2.00 | $3.50 | $1.75 |
| 0070 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 130 | $29.00 | $15.00 | $30.00 | $29.00 |
| 0071 | Pipe, type 1, circular, diameter 60 in. (715-05133) | LFT | 146 | $385.00 | $340.00 | $400.00 | $423.00 |
| 0072 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 69 | $165.00 | $80.00 | $90.00 | $128.00 |
| 0073 | Concrete anchor, diameter 60 in. (715-05841) | EACH | 1 | $7,500.00 | $7,500.00 | $10,000 | $6,400.00 |
| 0074 | Pipe end section, diameter 15 in. (715-46005) | EACH | 6 | $950.00 | $2,000.00 | $1,400.00 | $1,200.00 |
| 0075 | Geotextile for underdrains, type 2A (718-12307) | SYS | 90 | $9.10 | $3.00 | $10.00 | $18.00 |
| 0076 | Aggregate for underdrains (718-52610) | CYS | 12 | $160.00 | $110.00 | $130.00 | $225.00 |
| 0077 | Structure, coated reinforced concrete, three-sided sections, 432 in. X 144 in. (723-12337) | LFT | 44 | $8,990.00 | $12,200 | $11,250 | $12,875 |
| 0078 | Road closure sign assembly (801-04308) | EACH | 5 | $207.00 | $207.00 | $261.00 | $230.00 |
| 0079 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 8,904 | $1.20 | $1.20 | $1.44 | $1.30 |
| 0080 | Detour route marker assembly (801-06625) | EACH | 16 | $151.00 | $151.00 | $156.00 | $169.00 |
| 0081 | Construction sign, type A (801-06640) | EACH | 18 | $162.00 | $162.00 | $207.00 | $181.00 |
| 0082 | Construction sign, type B (801-06645) | EACH | 4 | $92.00 | $92.00 | $104.00 | $92.00 |
| 0083 | Temporary raised pavement marker, grade 1 (801-06649) | EACH | 23 | $15.00 | $100.00 | $31.86 | $33.00 |
| 0084 | Maintaining traffic (801-06775) | LS | 1 | $49,400 | $117,699 | $100,000 | $103,583 |
| 0085 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 1 | $6,500.00 | $6,500.00 | $6,500.00 | $10,400 |
| 0086 | Barricade, type III-A (801-07118) | LFT | 48 | $11.00 | $10.00 | $15.23 | $11.00 |
| 0087 | Barricade, type III-B (801-07119) | LFT | 96 | $11.00 | $11.00 | $15.23 | $12.00 |
| 0088 | Temporary traffic barrier, type 2 (801-08401) | LFT | 333 | $60.00 | $45.00 | $69.34 | $48.00 |
| 0089 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 159 | $77.00 | $90.00 | $76.06 | $73.00 |
| 0090 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 7 | $38.00 | $38.00 | $38.00 | $42.00 |
| 0091 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 21 | $38.00 | $38.00 | $38.00 | $42.00 |
| 0092 | Sign, sheet, and supports, remove (802-07059) | EACH | 4 | $85.00 | $85.00 | $85.00 | $95.00 |
| 0093 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 14 | $25.00 | $25.00 | $25.00 | $28.00 |
| 0094 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 9 | $25.00 | $25.00 | $25.00 | $28.00 |
| 0095 | Line, remove (808-06716) | LFT | 278 | $0.70 | $0.63 | $1.28 | $1.00 |
| 0096 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 619 | $1.30 | $1.29 | $1.02 | $1.40 |
| 0097 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 450 | $1.80 | $1.71 | $1.55 | $1.90 |
| 0098 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 619 | $1.30 | $1.30 | $1.02 | $1.40 |
| 0099 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 1,172 | $1.80 | $1.71 | $1.55 | $1.90 |
| 0100 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 8 | $50.00 | $20.00 | $155.00 | $72.00 |
| 0101 | Snowplowable raised pavement marker (808-75998) | EACH | 18 | $125.00 | $125.00 | $109.00 | $140.00 |
| 0102 | Line, thermoplastic, broken, white, 6 in. (808-96075) | LFT | 368 | $4.00 | $3.52 | $2.09 | $4.00 |
| 0103 | Flashing arrow sign (801-06710) | DAY | 30 | $10.00 | $10.00 | $15.00 | $35.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 15, 2025. Compiled by Mirage Metrics.