INDOT contract B-42399-B bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on February 11, 2026, Harrison, Seymour. 4 bids received; low bid $1,578,608 by Force Construction Co Inc.
- Owner
- Indiana DOT
- Letting
- 11 FEB 2026
- Pay items
- 80
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Force Construction Co Inc | $1,578,608 | Low |
| 2 | Milestone Contractors LP | $1,744,000 | +10% |
| 3 | E & B Paving LLC | $1,754,000 | +11% |
| 4 | Mac Construction & Excavating Inc | $1,763,800 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Force Construction Co Inc | 2. Milestone Contractors LP | 3. E & B Paving LLC | 4. Mac Construction & Excavating Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $12,970 | $16,000 | $25,000 | $50,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $75,000 | $87,000 | $87,700 | $85,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $20,850 | $64,000 | $10,000 | $130,000 |
| 0011 | Present structure, remove, structure no. , 064-31-06286 A (202-51330) | LS | 1 | $23,690 | $125,000 | $70,000 | $147,186 |
| 0012 | Sign, remove (202-74035) | EACH | 1 | $374.00 | $350.00 | $800.00 | $127.00 |
| 0013 | Pipe, remove (202-96133) | LFT | 24 | $42.00 | $62.00 | $48.00 | $65.00 |
| 0014 | Excavation, common (203-02000) | CYS | 1,359 | $42.00 | $58.00 | $100.00 | $60.00 |
| 0015 | Excavation, waterway (203-51223) | CYS | 210 | $71.00 | $58.00 | $116.00 | $79.00 |
| 0016 | Stormwater management budget (205-12108) | DOL | 19,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0017 | Stormwater management implementation (205-12616) | LS | 1 | $4,088.00 | $18,000 | $15,000 | $20,000 |
| 0018 | Excavation, X (206-51215) | CYS | 166 | $106.00 | $170.00 | $136.00 | $180.00 |
| 0019 | Excavation, dry (206-51225) | CYS | 24 | $69.00 | $50.00 | $106.00 | $86.00 |
| 0020 | Subgrade treatment, type II (207-08264) | SYS | 84 | $41.00 | $32.00 | $107.00 | $29.00 |
| 0021 | Subgrade treatment, type IC (207-09935) | SYS | 1,563 | $38.00 | $42.00 | $44.00 | $28.00 |
| 0022 | Structure backfill, type 2 (211-09265) | CYS | 48 | $67.00 | $60.00 | $125.00 | $45.00 |
| 0023 | Structure backfill, type 5 (211-09268) | CYS | 486 | $275.00 | $225.00 | $274.00 | $252.00 |
| 0024 | Geogrid, type IB (214-11796) | SYS | 1,563 | $5.20 | $2.60 | $3.00 | $6.00 |
| 0025 | Compacted aggregate, no. 2 (301-12231) | CYS | 89 | $128.00 | $70.00 | $65.00 | $82.00 |
| 0026 | Compacted aggregate, no. 53 (301-12234) | CYS | 89 | $96.00 | $65.00 | $67.00 | $87.00 |
| 0027 | Dense graded subbase (302-07455) | CYS | 14 | $126.00 | $69.00 | $126.00 | $77.00 |
| 0028 | Compacted aggregate, no. 53 (303-01180) | TON | 208 | $52.00 | $57.00 | $63.00 | $77.00 |
| 0029 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 312 | $11.00 | $14.00 | $3.91 | $16.00 |
| 0030 | Milling, transition (306-08043) | SYS | 560 | $9.90 | $10.00 | $3.91 | $13.00 |
| 0031 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 193 | $140.00 | $132.00 | $135.00 | $170.00 |
| 0032 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 193 | $106.00 | $98.00 | $102.00 | $150.00 |
| 0033 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 462 | $81.00 | $77.50 | $78.00 | $105.00 |
| 0034 | Joint adhesive (401-11526) | LFT | 3,900 | $0.10 | $0.65 | $0.10 | $0.43 |
| 0035 | Asphalt for tack coat (406-05521) | SYS | 2,330 | $0.10 | $0.15 | $0.10 | $0.50 |
| 0036 | Guardrail terminal system, W-beam, curved, type 7 (601-05071) | EACH | 1 | $3,638.00 | $3,500.00 | $4,000.00 | $4,000.00 |
| 0037 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 231.25 | $21.00 | $20.00 | $27.00 | $27.00 |
| 0038 | Guardrail height transition, MGS (601-12289) | EACH | 1 | $1,034.00 | $995.00 | $1,025.00 | $1,025.00 |
| 0039 | Guardrail, MGS, structure top-mounted posts , modified (601-12293) | EACH | 14 | $442.00 | $425.00 | $635.00 | $635.00 |
| 0040 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $3,742.00 | $3,600.00 | $3,200.00 | $3,200.00 |
| 0041 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 56.25 | $25.00 | $24.00 | $30.00 | $30.00 |
| 0042 | PCCP for approaches, 6 in. (610-08446) | SYS | 84 | $108.00 | $112.50 | $175.00 | $101.58 |
| 0043 | Right-of-way marker (615-06490) | EACH | 11 | $187.00 | $180.00 | $200.00 | $200.00 |
| 0044 | Monument, type B (615-06505) | EACH | 2 | $1,247.00 | $1,200.00 | $1,750.00 | $1,750.00 |
| 0045 | Riprap, class 1 (616-05688) | TON | 688 | $74.00 | $52.00 | $110.00 | $77.00 |
| 0046 | Riprap, class 2 (616-05689) | TON | 100 | $108.00 | $52.00 | $120.00 | $75.00 |
| 0047 | Riprap, revetment (616-06405) | TON | 63 | $72.00 | $51.00 | $100.00 | $60.00 |
| 0048 | Geomembrane (616-09395) | SYS | 717 | $67.00 | $62.00 | $73.00 | $8.00 |
| 0049 | Geotextile for riprap, type 1A (616-12246) | SYS | 958 | $4.50 | $2.80 | $2.00 | $1.41 |
| 0050 | Geotextile for riprap, type 2A (616-12248) | SYS | 121 | $10.00 | $6.00 | $7.00 | $1.58 |
| 0051 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $936.00 | $1,500.00 | $800.00 | $800.00 |
| 0052 | Seed mixture, native (621-03909) | LBS | 12 | $416.00 | $175.00 | $150.00 | $150.00 |
| 0053 | Fertilizer for permanent seeding (621-06545) | TON | 1 | $832.00 | $5.00 | $10.00 | $10.00 |
| 0054 | Mulched seeding, type R (621-06559) | SYS | 138 | $2.10 | $20.00 | $15.00 | $15.00 |
| 0055 | Water (621-06567) | KGAL | 1 | $10.00 | $1.00 | $0.01 | $0.01 |
| 0056 | Sodding (621-06574) | SYS | 260 | $26.00 | $15.75 | $16.00 | $16.00 |
| 0057 | Field office, type C (628-09403) | MOS | 24 | $3,430.00 | $3,625.00 | $3,200.00 | $3,100.00 |
| 0058 | Computer system equipment (628-11976) | EACH | 2 | $890.00 | $1,000.00 | $1,000.00 | $1,080.00 |
| 0059 | Concrete, B, footings (702-51015) | CYS | 77.50 | $783.00 | $1,230.00 | $1,050.00 | $700.00 |
| 0060 | Reinforcing bars, epoxy coated (703-06029) | LBS | 97,693 | $1.50 | $1.50 | $1.50 | $1.75 |
| 0061 | Concrete, C, superstructure (704-51002) | CYS | 209.40 | $1,498.00 | $2,100.00 | $1,780.00 | $1,350.00 |
| 0062 | Waterproofing membrane, type 2 (714-000086) | SFT | 1,969 | $5.70 | $3.80 | $10.00 | $8.00 |
| 0063 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 10 | $410.00 | $325.00 | $290.00 | $110.00 |
| 0064 | Pipe, type 3, circular, diameter 12 in. (715-05168) | LFT | 42 | $121.00 | $92.00 | $170.00 | $120.00 |
| 0065 | Geotextile for underdrains, type 1B (718-12306) | SYS | 296 | $5.50 | $7.00 | $3.00 | $2.43 |
| 0066 | Casting, type 2, furnish and adjust to grade (720-44015) | EACH | 1 | $1,501.00 | $1,400.00 | $6,500.00 | $1,800.00 |
| 0067 | Road closure sign assembly (801-04308) | EACH | 2 | $281.00 | $270.00 | $270.00 | $175.00 |
| 0068 | Detour route marker assembly (801-06625) | EACH | 23 | $210.00 | $202.00 | $202.00 | $85.00 |
| 0069 | Construction sign, type A (801-06640) | EACH | 14 | $304.00 | $292.00 | $292.00 | $200.00 |
| 0070 | Maintaining traffic (801-06775) | LS | 1 | $157,000 | $25,571 | $42,301 | $83,500 |
| 0071 | Barricade, type III-A (801-07118) | LFT | 48 | $15.00 | $14.00 | $14.00 | $15.00 |
| 0072 | Barricade, type III-B (801-07119) | LFT | 48 | $17.00 | $16.00 | $16.00 | $15.00 |
| 0073 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 11.50 | $33.00 | $32.00 | $20.00 | $20.00 |
| 0074 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 5 | $33.00 | $32.00 | $94.00 | $94.00 |
| 0075 | Grooving for pavement markings (808-12032) | LFT | 2,113 | $4.20 | $4.00 | $4.00 | $2.00 |
| 0076 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 1,300 | $3.10 | $3.01 | $3.01 | $3.00 |
| 0077 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 650 | $3.10 | $3.01 | $3.01 | $3.00 |
| 0078 | Line, thermoplastic, broken, yellow, 6 in. (808-96078) | LFT | 163 | $7.30 | $7.06 | $7.06 | $3.00 |
| 0079 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 4 | $820.00 | $712.50 | $1,300.00 | $920.00 |
| 0080 | Inspection hole, 3 FT deep or less (107-09367) | EACH | 4 | $820.00 | $712.50 | $1,300.00 | $800.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 11, 2026. Compiled by Mirage Metrics.