INDOT contract B-42842-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on January 15, 2025, Allen, Fort Wayne. 4 bids received; low bid $952,963 by R L McCoy Inc.
- Owner
- Indiana DOT
- Letting
- 15 JAN 2025
- Pay items
- 76
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | R L McCoy Inc | $952,963 | Low |
| 2 | Miller Bros Construction Inc | $994,677 | +4.0% |
| 3 | Pioneer Associates Inc | $1,227,947 | +29% |
| 4 | Milestone Contractors LP | $1,334,599 | +40% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R L McCoy Inc | 2. Miller Bros Construction Inc | 3. Pioneer Associates Inc | 4. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $8,100.00 | $6,945.00 | $13,200 | $55,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $47,600 | $50,000 | $102,500 | $66,730 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $19,000 | $3,000.00 | $9,750.00 | $26,692 |
| 0011 | Present structure, remove, structure no. 02-00141 (202-51330) | LS | 1 | $62,000 | $80,000 | $51,500 | $179,365 |
| 0012 | Excavation, common (203-02000) | CYS | 725 | $65.00 | $70.00 | $55.00 | $130.00 |
| 0013 | Excavation, waterway (203-51223) | CYS | 280 | $48.00 | $55.00 | $30.00 | $77.50 |
| 0014 | Pump around (205-11626) | EACH | 1 | $10,000 | $40,000 | $14,500 | $25,000 |
| 0015 | Stormwater management budget (205-12108) | DOL | 21,630 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $3,500.00 | $8,200.00 | $7,500.00 | $4,341.56 |
| 0017 | Cofferdam (206-51235) | LS | 1 | $10,000 | $1.00 | $19,500 | $39,968 |
| 0018 | Subgrade treatment, type IC (207-09935) | SYS | 1,572 | $40.00 | $21.00 | $45.00 | $39.00 |
| 0019 | Aggregate for end bent backfill (211-06467) | CYS | 48 | $115.00 | $310.00 | $115.00 | $218.00 |
| 0020 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,689 | $5.00 | $5.00 | $8.00 | $4.00 |
| 0021 | Subbase for PCCP (302-06464) | CYS | 30 | $135.00 | $145.00 | $150.00 | $342.00 |
| 0022 | Compacted aggregate, no. 53 (303-01180) | TON | 239 | $50.00 | $45.00 | $50.00 | $86.00 |
| 0023 | Compacted aggregate, no. 73 (303-07449) | TON | 21 | $56.00 | $50.00 | $50.00 | $184.00 |
| 0024 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 119 | $139.00 | $139.00 | $139.00 | $139.00 |
| 0025 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 199 | $118.00 | $118.00 | $118.00 | $118.00 |
| 0026 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 483 | $97.00 | $97.00 | $97.00 | $97.00 |
| 0027 | Joint adhesive, surface (401-10258) | LFT | 800 | $0.38 | $0.38 | $0.38 | $0.38 |
| 0028 | Joint adhesive, intermediate (401-10259) | LFT | 800 | $0.46 | $0.46 | $0.46 | $0.46 |
| 0029 | Liquid asphalt sealant (401-11785) | LFT | 800 | $0.01 | $0.01 | $0.01 | $0.01 |
| 0030 | Asphalt for tack coat (406-05521) | SYS | 2,845 | $0.34 | $0.34 | $0.34 | $0.34 |
| 0031 | Guardrail transition, type TGB (601-01522) | EACH | 2 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0032 | Guardrail transition, type TGB , modified (601-01522) | EACH | 2 | $3,300.00 | $3,000.00 | $3,300.00 | $3,300.00 |
| 0033 | Guardrail terminal system, W-beam curved, type 3 (601-01846) | EACH | 1 | $3,100.00 | $2,600.00 | $3,100.00 | $3,100.00 |
| 0034 | Guardrail end treatment, type OS , SKT 350 (601-94689) | EACH | 1 | $2,900.00 | $2,775.00 | $3,600.00 | $2,900.00 |
| 0035 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 13 | $140.00 | $22.00 | $140.00 | $140.00 |
| 0036 | Barrier delineator (602-06729) | EACH | 4 | $25.00 | $25.00 | $35.00 | $78.00 |
| 0037 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 125 | $265.00 | $190.00 | $250.00 | $225.00 |
| 0038 | Mailbox assembly, reset, single (611-08232) | EACH | 1 | $250.00 | $200.00 | $250.00 | $250.00 |
| 0039 | Right-of-way marker (615-06490) | EACH | 6 | $145.00 | $145.00 | $145.00 | $145.00 |
| 0040 | Monument, type B (615-06505) | EACH | 3 | $999.00 | $855.00 | $999.00 | $999.00 |
| 0041 | Riprap, revetment (616-06405) | TON | 480 | $72.00 | $37.00 | $50.00 | $77.00 |
| 0042 | Geotextile for riprap, type 1A (616-12246) | SYS | 769 | $4.00 | $4.00 | $4.00 | $5.00 |
| 0043 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $400.00 | $400.00 | $400.00 | $400.00 |
| 0044 | Fertilizer , for permanent seeding (621-06545) | TON | 1 | $790.00 | $790.00 | $790.00 | $790.00 |
| 0045 | Seed mixture, type R (621-06553) | LBS | 30 | $18.95 | $18.95 | $19.00 | $18.95 |
| 0046 | Mulching material (621-06565) | TON | 1 | $690.00 | $690.00 | $690.00 | $690.00 |
| 0047 | Water (621-06567) | KGAL | 1 | $5.00 | $5.00 | $5.00 | $5.00 |
| 0048 | Sodding (621-06574) | SYS | 7 | $184.00 | $184.00 | $184.00 | $184.00 |
| 0049 | Permanent turf reinforcement mat (621-08161) | SYS | 553 | $9.95 | $9.95 | $10.00 | $9.95 |
| 0050 | Seed mixture, floodplain (621-12612) | LBS | 3 | $285.00 | $285.00 | $285.00 | $285.00 |
| 0051 | Sign, "DO not spray" (621-52448) | EACH | 2 | $90.00 | $90.00 | $90.00 | $90.00 |
| 0052 | Field office, type A (628-09401) | MOS | 12 | $3,300.00 | $3,600.00 | $3,100.00 | $3,910.00 |
| 0053 | Test pile, indicator, production (701-09558) | LFT | 112 | $84.00 | $90.00 | $140.00 | $77.00 |
| 0054 | Pile shoe, HP 12 X 53 (701-09739) | EACH | 12 | $200.00 | $155.00 | $240.00 | $400.00 |
| 0055 | Pile, steel H, HP 12 X 53 (701-51195) | LFT | 552 | $55.00 | $70.00 | $110.00 | $63.00 |
| 0056 | Concrete, A, substructure (702-51005) | CYS | 59.20 | $800.00 | $1,025.00 | $1,400.00 | $1,200.00 |
| 0057 | Reinforcing bars (703-06028) | LBS | 9,153 | $1.35 | $1.40 | $2.00 | $2.00 |
| 0058 | Reinforcing bars, epoxy coated (703-06029) | LBS | 14,639 | $1.45 | $1.55 | $2.00 | $2.10 |
| 0059 | Concrete, C, superstructure (704-51002) | CYS | 50.70 | $1,550.00 | $1,350.00 | $2,200.00 | $1,400.00 |
| 0060 | Railing, concrete type FC , modified (706-09960) | LFT | 37 | $260.00 | $200.00 | $200.00 | $250.00 |
| 0061 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $3,000.00 | $4,500.00 | $4,600.00 | $2,500.00 |
| 0062 | Structural member, concrete, box beam, 21 in. X 48 in. (707-11494) | LFT | 450 | $293.00 | $347.00 | $475.00 | $310.00 |
| 0063 | Surface seal (709-51821) | LS | 1 | $500.00 | $3,682.00 | $1,200.00 | $1,742.31 |
| 0064 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 100 | $30.00 | $12.00 | $25.00 | $16.00 |
| 0065 | Geotextile for underdrains, type 1A (718-12305) | SYS | 117 | $7.00 | $10.00 | $10.00 | $4.00 |
| 0066 | Longitudinal grooving (722-12732) | SYS | 325 | $18.00 | $11.22 | $13.00 | $15.00 |
| 0067 | Bearing assembly, elastomeric (726-92406) | EACH | 36 | $100.00 | $350.00 | $290.00 | $200.00 |
| 0068 | Road closure sign assembly (801-04308) | EACH | 8 | $250.00 | $250.00 | $250.00 | $250.00 |
| 0069 | Detour route marker assembly (801-06625) | EACH | 33 | $140.00 | $140.00 | $140.00 | $140.00 |
| 0070 | Construction sign, type A (801-06640) | EACH | 17 | $150.00 | $150.00 | $150.00 | $150.00 |
| 0071 | Maintaining traffic (801-06775) | LS | 1 | $500.00 | $6,500.00 | $19,500 | $20,000 |
| 0072 | Barricade, type III-A (801-07118) | LFT | 96 | $14.00 | $14.00 | $14.00 | $14.00 |
| 0073 | Barricade, type III-B (801-07119) | LFT | 96 | $14.00 | $14.00 | $14.00 | $14.00 |
| 0074 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 14 | $29.00 | $17.00 | $17.00 | $29.00 |
| 0075 | Sign post, type A (802-76055) | LFT | 22 | $38.00 | $12.00 | $12.00 | $38.00 |
| 0076 | Sign, ground mounted, reset (802-91122) | EACH | 1 | $207.00 | $352.00 | $352.00 | $207.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 15, 2025. Compiled by Mirage Metrics.