INDOT contract B-42951-A bid tabulation
SCOUR PROTECTION. Let by Indiana DOT on January 14, 2026, Boone, Tippecanoe, White, Crawfordsville. 5 bids received; low bid $558,192 by 5 Star Company Inc.
- Owner
- Indiana DOT
- Letting
- 14 JAN 2026
- Pay items
- 40
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | 5 Star Company Inc | $558,192 | Low |
| 2 | Milestone Contractors LP | $745,245 | +34% |
| 3 | Morphey Construction Inc. | $938,938 | +68% |
| 4 | Crackers Demo LLC | $996,957 | +79% |
| 5 | Yarberry Companies Inc | $1,102,042 | +97% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. 5 Star Company Inc | 2. Milestone Contractors LP | 3. Morphey Construction Inc. | 4. Crackers Demo LLC | 5. Yarberry Companies Inc |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $15,000 | $14,500 | $20,000 | $10,000 | $45,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Mobilization and demobilization (110-01001) | LS | 1 | $45,000 | $37,250 | $70,000 | $128,000 | $60,000 |
| 0009 | Clearing right-of-way (201-52370) | LS | 1 | $21,500 | $22,360 | $35,000 | $50,000 | $60,000 |
| 0010 | Debris, remove, structure no. 1 (201-90788) | LS | 1 | $5,500.00 | $3,600.00 | $40,000 | $13,000 | $20,000 |
| 0011 | Debris, remove, structure no. 3 (201-90788) | LS | 1 | $2,950.00 | $3,500.00 | $30,000 | $1,600.00 | $25,000 |
| 0012 | Excavation, waterway (203-51223) | CYS | 73 | $89.00 | $60.00 | $140.00 | $160.00 | $250.00 |
| 0013 | Pump around (205-11626) | EACH | 2 | $5,000.00 | $41,000 | $10,000 | $33,000 | $25,000 |
| 0014 | Stormwater management budget (205-12108) | DOL | 48,065 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0015 | Stormwater management implementation (205-12616) | LS | 1 | $4,800.00 | $1,535.00 | $15,000 | $42,000 | $16,000 |
| 0016 | Cofferdam (206-51235) | LS | 1 | $20,000 | $45,000 | $50,000 | $69,000 | $70,000 |
| 0017 | Compacted aggregate, no. 53 (301-12234) | CYS | 18 | $55.00 | $210.00 | $130.00 | $415.00 | $125.00 |
| 0018 | Guardrail, reset (601-06035) | LFT | 125 | $100.00 | $92.50 | $92.50 | $92.50 | $100.00 |
| 0019 | Hand dig guardrail post holes (601-09238) | EACH | 20 | $165.00 | $150.00 | $150.00 | $150.00 | $170.00 |
| 0020 | Riprap, class 1 (616-05688) | TON | 570 | $100.00 | $190.00 | $170.00 | $195.00 | $275.00 |
| 0021 | Riprap, class 2 (616-05689) | TON | 617 | $100.00 | $220.00 | $170.00 | $215.00 | $275.00 |
| 0022 | Geotextile for riprap, type 1A (616-12246) | SYS | 1,455 | $4.50 | $1.20 | $2.81 | $1.50 | $15.00 |
| 0023 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $650.00 | $400.00 | $1,000.00 | $400.00 | $750.00 |
| 0024 | Mulched seeding, type R (621-06559) | SYS | 2,068 | $2.00 | $3.68 | $10.00 | $3.68 | $2.00 |
| 0025 | Seed mixture, floodplain (621-12612) | LBS | 3 | $150.00 | $537.00 | $2,000.00 | $537.00 | $750.00 |
| 0026 | Sign, 'DO not spray' (621-52448) | EACH | 4 | $200.00 | $100.00 | $125.00 | $100.00 | $55.00 |
| 0027 | Field office, type C (628-09403) | MOS | 8 | $2,000.00 | $3,800.00 | $2,200.00 | $5,000.00 | $3,000.00 |
| 0028 | Mobile internet service , 1 each (628-09409) | MOS | 8 | $350.00 | $150.00 | $500.00 | $100.00 | $300.00 |
| 0029 | Computer system equipment (628-11976) | EACH | 2 | $400.00 | $300.00 | $750.00 | $135.00 | $1,500.00 |
| 0030 | Computer system (628-11977) | EACH | 1 | $1,000.00 | $800.00 | $1,500.00 | $585.00 | $1,500.00 |
| 0031 | Temporary causeway (713-04331) | LS | 1 | $65,000 | $81,500 | $150,000 | $100,000 | $75,000 |
| 0032 | Temporary pipe (713-04509) | LS | 1 | $28,500 | $14,000 | $8,497.12 | $2,500.00 | $70,000 |
| 0033 | Construction sign, type C (801-03290) | EACH | 3 | $305.00 | $350.00 | $350.00 | $350.00 | $385.00 |
| 0034 | Construction sign, type D (801-03291) | EACH | 2 | $210.00 | $250.00 | $250.00 | $250.00 | $275.00 |
| 0035 | Construction sign, type A (801-06640) | EACH | 24 | $155.00 | $165.00 | $165.00 | $165.00 | $195.00 |
| 0036 | Construction sign, type B (801-06645) | EACH | 3 | $80.00 | $100.00 | $100.00 | $100.00 | $120.00 |
| 0037 | Flashing arrow sign (801-06710) | DAY | 30 | $32.00 | $15.00 | $15.00 | $15.00 | $40.00 |
| 0038 | Maintaining traffic (801-06775) | LS | 1 | $75,000 | $29,989 | $90,329 | $41,500 | $68,000 |
| 0039 | Portable changeable message sign (801-11642) | EACH | 1 | $2,100.00 | $4,200.00 | $4,200.00 | $4,200.00 | $4,620.00 |
| 0040 | Riprap, class 1 , with live stakes (616-05688) | TON | 145 | $221.00 | $270.00 | $440.00 | $570.00 | $400.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 14, 2026. Compiled by Mirage Metrics.