INDOT contract B-43779-A bid tabulation
BRIDGE DECK OVERLAY. Let by Indiana DOT on July 9, 2025, Dekalb, Noble, Fort Wayne. 4 bids received; low bid $4,269,910 by Pioneer Associates Inc.
- Owner
- Indiana DOT
- Letting
- 09 JUL 2025
- Pay items
- 113
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pioneer Associates Inc | $4,269,910 | Low |
| 2 | R L McCoy Inc | $4,622,362 | +8.0% |
| 3 | E & B Paving LLC | $4,786,000 | +12% |
| 4 | Milestone Contractors LP | $5,079,886 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pioneer Associates Inc | 2. R L McCoy Inc | 3. E & B Paving LLC | 4. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $44,000 | $40,000 | $75,000 | $51,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0012 | Mobilization and demobilization (110-01001) | LS | 1 | $245,500 | $231,100 | $243,484 | $253,994 |
| 0013 | Clearing right-of-way (201-52370) | LS | 1 | $45,200 | $46,200 | $47,861 | $50,799 |
| 0014 | Pavement removal (202-02240) | SYS | 1,908 | $50.00 | $60.00 | $60.00 | $90.00 |
| 0015 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $92,500 | $160,000 | $175,000 | $130,000 |
| 0016 | Present structure, remove portions, structure no. 2 (202-51328) | LS | 1 | $92,500 | $160,000 | $175,000 | $130,000 |
| 0017 | Present structure, remove portions, structure no. 3 (202-51328) | LS | 1 | $98,500 | $165,000 | $170,000 | $130,000 |
| 0018 | Present structure, remove portions, structure no. 4 (202-51328) | LS | 1 | $98,500 | $165,000 | $170,000 | $130,000 |
| 0019 | Excavation, common (203-02000) | CYS | 370 | $70.00 | $100.00 | $90.00 | $90.00 |
| 0020 | Linear grading (203-08607) | LFT | 2,431 | $6.00 | $6.00 | $3.00 | $6.00 |
| 0021 | Excavation, waterway (203-51223) | CYS | 200 | $110.00 | $55.00 | $90.00 | $72.00 |
| 0022 | Stormwater management budget (205-12108) | DOL | 64,187 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0023 | Stormwater management implementation (205-12616) | LS | 1 | $22,800 | $10,000 | $50,000 | $10,500 |
| 0024 | SWQCP preparation (205-12618) | LS | 1 | $2,500.00 | $3,900.00 | $2,500.00 | $2,700.00 |
| 0025 | Cofferdam (206-51235) | LS | 1 | $32,300 | $130,000 | $50,000 | $85,000 |
| 0026 | Subgrade treatment, type IC (207-09935) | SYS | 2,164 | $65.00 | $58.00 | $75.00 | $70.00 |
| 0027 | Aggregate for end bent backfill (211-06467) | CYS | 168 | $170.00 | $200.00 | $155.00 | $195.00 |
| 0028 | Structure backfill, type 1 (211-09264) | CYS | 28 | $80.00 | $170.00 | $120.00 | $470.00 |
| 0029 | Structure backfill, type 5 (211-09268) | CYS | 100 | $216.00 | $200.00 | $237.00 | $380.00 |
| 0030 | Geotextile for pavement, type 2B (214-12239) | SYS | 2,568 | $6.00 | $4.00 | $10.00 | $4.75 |
| 0031 | Compacted aggregate, no. 53 (301-12234) | CYS | 44 | $120.00 | $240.00 | $125.00 | $200.00 |
| 0032 | Subbase for PCCP (302-06464) | CYS | 646 | $145.00 | $155.00 | $140.00 | $260.00 |
| 0033 | Compacted aggregate, no. 53 (303-01180) | TON | 264 | $73.00 | $95.00 | $75.00 | $89.00 |
| 0034 | Milling, transition (306-08043) | SYS | 1,776 | $5.00 | $12.00 | $6.00 | $6.00 |
| 0035 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 148 | $235.00 | $235.00 | $250.00 | $235.00 |
| 0036 | Joint adhesive, surface (401-10258) | LFT | 1,260 | $0.80 | $0.80 | $1.00 | $0.80 |
| 0037 | Asphalt for tack coat (406-05520) | TON | 2 | $1,075.00 | $1,075.00 | $210.00 | $1,075.00 |
| 0038 | Cracks and joints in asphalt pavement, rout and seal (408-07478) | TON | 2 | $822.00 | $822.00 | $3,000.00 | $1,200.00 |
| 0039 | PCCP, 12 in. (502-06329) | SYS | 1,100 | $147.00 | $134.00 | $90.00 | $140.00 |
| 0040 | Retrofitted tie bars (503-03489) | EACH | 152 | $14.00 | $14.00 | $15.00 | $35.00 |
| 0041 | D-1 contraction joint (503-05240) | LFT | 912 | $13.00 | $14.25 | $25.00 | $25.00 |
| 0042 | Jointed reinforced concrete pavement, 12 in. (503-12476) | SYS | 676 | $200.00 | $200.00 | $225.00 | $190.00 |
| 0043 | Terminal joint, type PCCP (503-12478) | LFT | 152 | $380.00 | $455.00 | $250.00 | $390.00 |
| 0044 | Expansion joint with load transfer (503-12479) | LFT | 152 | $16.00 | $18.00 | $55.00 | $35.00 |
| 0045 | Guardrail, remove (601-02241) | LFT | 2,455 | $4.00 | $4.00 | $4.00 | $4.00 |
| 0046 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 1,008 | $24.00 | $24.00 | $24.00 | $24.00 |
| 0047 | Guardrail, MGS W-beam, double faced, 6 FT 3 in. spacing (601-12284) | LFT | 350 | $34.00 | $34.00 | $34.00 | $34.00 |
| 0048 | Guardrail height transition, MGS (601-12289) | EACH | 2 | $1,050.00 | $1,050.00 | $1,050.00 | $1,050.00 |
| 0049 | Guardrail transition, MGS without curb (601-12292) | EACH | 10 | $3,550.00 | $3,550.00 | $3,550.00 | $3,550.00 |
| 0050 | Guardrail, MGS W-beam, cable terminal anchor (601-12294) | EACH | 1 | $1,200.00 | $1,200.00 | $1,200.00 | $1,200.00 |
| 0051 | Guardrail end treatment, type OS (601-94689) | EACH | 5 | $4,085.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0052 | Guardrail end treatment, type MS (601-94690) | EACH | 2 | $5,500.00 | $5,500.00 | $5,500.00 | $5,500.00 |
| 0053 | Barrier delineator (602-06729) | EACH | 48 | $20.00 | $25.00 | $25.00 | $37.00 |
| 0054 | Fence, farm field, reset (603-06060) | LFT | 180 | $50.00 | $49.25 | $49.25 | $49.25 |
| 0055 | Milled PCCP corrugations, conventional (606-11064) | LFT | 840 | $3.00 | $5.00 | $1.50 | $6.00 |
| 0056 | Milled HMA corrugations, conventional (606-12399) | LFT | 3,280 | $3.00 | $5.00 | $1.50 | $5.00 |
| 0057 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 792 | $270.00 | $310.00 | $275.00 | $255.00 |
| 0058 | Riprap, revetment (616-06405) | TON | 1,641 | $70.00 | $95.00 | $75.00 | $84.00 |
| 0059 | Geotextile for riprap, type 1A (616-12246) | SYS | 2,180 | $3.00 | $4.00 | $6.00 | $3.00 |
| 0060 | Inspection hole (616-93772) | EACH | 24 | $300.00 | $400.00 | $200.00 | $480.00 |
| 0061 | Mobilization and demobilization for seeding (621-01004) | EACH | 4 | $725.00 | $500.00 | $725.00 | $725.00 |
| 0062 | Erosion control blanket (621-02770) | SYS | 2,566 | $3.20 | $2.15 | $3.20 | $3.20 |
| 0063 | Mulched seeding, type R (621-06559) | SYS | 4,308 | $1.90 | $2.25 | $1.90 | $1.90 |
| 0064 | Water (621-06567) | KGAL | 18 | $5.00 | $1.00 | $5.00 | $5.00 |
| 0065 | Sodding (621-06574) | SYS | 76 | $74.00 | $23.00 | $74.00 | $74.00 |
| 0066 | Seed mixture, emergent wetland (621-06737) | LBS | 1 | $1,025.00 | $875.00 | $1,025.00 | $1,025.00 |
| 0067 | Field office, type C (628-09403) | MOS | 18 | $3,875.00 | $2,450.00 | $3,375.00 | $3,200.00 |
| 0068 | Temporary shoring (702-04325) | LS | 1 | $75,000 | $35,000 | $80,000 | $40,000 |
| 0069 | Grates, basins, and fittings, cast iron (702-12076) | EACH | 8 | $2,890.00 | $1,600.00 | $1,200.00 | $2,700.00 |
| 0070 | Field drilled hole in concrete (702-51863) | EACH | 152 | $27.00 | $30.00 | $25.00 | $12.00 |
| 0071 | Reinforcing bars, epoxy coated (703-06029) | LBS | 82,656 | $2.00 | $1.52 | $1.25 | $2.50 |
| 0072 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 748 | $60.00 | $50.00 | $30.00 | $45.00 |
| 0073 | Concrete, C, superstructure (704-51002) | CYS | 168.80 | $2,100.00 | $2,450.00 | $1,200.00 | $4,000.00 |
| 0074 | Railing, concrete type FC , modified (706-11600) | CYS | 9.60 | $4,600.00 | $3,400.00 | $1,000.00 | $5,000.00 |
| 0075 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 16 | $4,250.00 | $3,900.00 | $4,000.00 | $3,000.00 |
| 0076 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $3,000.00 | $4,000.00 | $20,000 | $2,000.00 |
| 0077 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $3,000.00 | $4,000.00 | $20,000 | $2,000.00 |
| 0078 | Surface seal , bridge no. 3 (709-51821) | LS | 1 | $5,000.00 | $5,000.00 | $20,000 | $2,000.00 |
| 0079 | Surface seal , bridge no. 4 (709-51821) | LS | 1 | $5,000.00 | $5,000.00 | $20,000 | $2,000.00 |
| 0080 | Patching concrete structures (710-09158) | SFT | 300 | $10.00 | $80.00 | $10.00 | $120.00 |
| 0081 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 836 | $20.00 | $20.00 | $10.00 | $26.00 |
| 0082 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 588 | $42.00 | $34.00 | $15.00 | $37.00 |
| 0083 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 348 | $28.00 | $38.00 | $15.00 | $21.00 |
| 0084 | Pipe extension, circular, diameter 6 in. , PVC (715-06566) | LFT | 28 | $110.00 | $150.00 | $20.00 | $760.00 |
| 0085 | Outlet protector, type 1 (718-06528) | EACH | 16 | $1,500.00 | $1,800.00 | $950.00 | $760.00 |
| 0086 | Geotextile for underdrains, type 2A (718-12307) | SYS | 1,120 | $3.00 | $2.00 | $5.00 | $6.00 |
| 0087 | Aggregate for underdrains (718-52610) | CYS | 88 | $120.00 | $65.00 | $75.00 | $175.00 |
| 0088 | Hydrodemolition (722-01066) | SYS | 1,916 | $80.00 | $102.00 | $80.00 | $100.00 |
| 0089 | Bridge deck overlay budget (722-12380) | DOL | 44,212 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0090 | Bridge deck, remove concrete surface (722-12464) | SYS | 1,916 | $15.00 | $11.00 | $15.00 | $16.00 |
| 0091 | Longitudinal grooving (722-12732) | SYS | 2,878 | $6.00 | $14.00 | $10.00 | $7.25 |
| 0092 | Bridge deck patching, full depth (722-51401) | SFT | 284 | $70.00 | $15.00 | $25.00 | $60.00 |
| 0093 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 33,038 | $1.40 | $1.39 | $1.75 | $1.75 |
| 0094 | Construction sign, type A (801-06640) | EACH | 114 | $307.00 | $307.00 | $250.00 | $250.00 |
| 0095 | Construction sign, type B (801-06645) | EACH | 12 | $154.00 | $154.00 | $150.00 | $150.00 |
| 0096 | Flashing arrow sign (801-06710) | DAY | 720 | $16.00 | $16.00 | $15.00 | $15.00 |
| 0097 | Maintaining traffic (801-06775) | LS | 1 | $132,500 | $45,000 | $553,500 | $107,939 |
| 0098 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 4 | $6,600.00 | $6,600.00 | $6,600.00 | $6,600.00 |
| 0099 | Barricade, type III-A (801-07118) | LFT | 36 | $16.00 | $16.07 | $20.00 | $20.00 |
| 0100 | Temporary traffic barrier, type 2 (801-08401) | LFT | 1,660 | $30.00 | $38.00 | $37.50 | $50.00 |
| 0101 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 1,520 | $35.00 | $75.00 | $37.50 | $70.00 |
| 0102 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 16 | $1,015.00 | $1,014.00 | $400.00 | $400.00 |
| 0103 | Delineator post, flexible, type I (804-11920) | EACH | 16 | $30.00 | $31.43 | $125.00 | $125.00 |
| 0104 | Line, remove (808-06716) | LFT | 11,127 | $0.80 | $0.79 | $0.50 | $0.50 |
| 0105 | Retro-reflectivity testing (808-09381) | LS | 1 | $3,000.00 | $3,000.00 | $750.00 | $750.00 |
| 0106 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 7,691 | $1.45 | $1.44 | $1.15 | $1.15 |
| 0107 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 1,484 | $1.45 | $1.44 | $1.15 | $1.15 |
| 0108 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 2,533 | $1.90 | $1.89 | $1.15 | $1.15 |
| 0109 | Grooving for pavement markings (808-12032) | LFT | 9,908 | $0.90 | $0.88 | $0.60 | $0.60 |
| 0110 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 18 | $250.00 | $30.00 | $5.00 | $33.00 |
| 0112 | Bridge deck overlay, silica fume modified (722-01061) | SYS | 2,126 | $160.00 | $120.00 | $150.00 | $140.00 |
| 0113 | Inertial profiler, bridge encounter (704-000080) | LS | 1 | $24,000 | $8,000.00 | $15,000 | $14,000 |
| 0114 | Corrective grinding, bridge encounter (704-000082) | LS | 1 | $15,600 | $60,000 | $25,000 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 9, 2025. Compiled by Mirage Metrics.