INDOT contract B-43972-A bid tabulation
BRIDGE DECK OVERLAY, BRIDGE THIN DECK OVERLAY. Let by Indiana DOT on September 10, 2025, Gibson, Spencer, Warrick, Vincennes. 4 bids received; low bid $1,665,138 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 10 SEP 2025
- Pay items
- 78
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $1,665,138 | Low |
| 2 | Beaty Construction Inc | $1,848,307 | +11% |
| 3 | Ragle, Inc. | $1,959,321 | +18% |
| 4 | Blankenberger Brothers Inc | $1,993,400 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Beaty Construction Inc | 3. Ragle, Inc. | 4. Blankenberger Brothers Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $5,800.00 | $9,000.00 | $18,500 | $20,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $81,491 | $263,851 | $98,000 | $149,600 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $16,650 | $29,895 | $19,500 | $19,900 |
| 0012 | Stormwater management budget (205-12108) | DOL | 11,057 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0013 | Stormwater management implementation (205-12616) | LS | 1 | $13,250 | $11,536 | $5,000.00 | $20,000 |
| 0014 | Subgrade treatment, type II (207-08264) | SYS | 818 | $60.00 | $33.32 | $34.50 | $56.70 |
| 0015 | Geogrid, type IB (214-11796) | SYS | 818 | $0.75 | $2.71 | $3.50 | $3.40 |
| 0016 | Widening with HMA, type C (304-07494) | TON | 541 | $220.00 | $230.39 | $201.00 | $225.00 |
| 0017 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 899 | $6.50 | $7.03 | $5.50 | $7.50 |
| 0018 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 75 | $240.00 | $315.00 | $225.00 | $315.00 |
| 0019 | Joint adhesive (401-11526) | LFT | 6,258 | $0.25 | $1.15 | $0.50 | $1.15 |
| 0020 | Asphalt for tack coat (406-05521) | SYS | 2,535 | $2.50 | $0.30 | $2.50 | $0.30 |
| 0021 | Joints in PCCP, saw and seal (507-08272) | LFT | 570 | $3.95 | $13.73 | $8.25 | $7.89 |
| 0022 | Milled HMA corrugations, conventional (606-12399) | LFT | 1,840 | $1.13 | $5.05 | $2.00 | $3.50 |
| 0023 | Riprap, revetment (616-06405) | TON | 9 | $600.00 | $165.87 | $95.00 | $165.00 |
| 0024 | Geotextile for riprap, type 2A (616-12248) | SYS | 18 | $41.99 | $53.29 | $10.00 | $21.50 |
| 0025 | Clean drains (619-98427) | EACH | 3 | $250.00 | $50.00 | $50.00 | $500.00 |
| 0026 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $500.00 | $500.00 | $500.00 | $500.00 |
| 0027 | Mulched seeding, type R (621-06559) | SYS | 2,727 | $2.75 | $2.75 | $2.75 | $2.75 |
| 0028 | Computer system equipment (628-11976) | EACH | 2 | $500.00 | $540.00 | $750.00 | $550.00 |
| 0029 | Field office, type D (628-12683) | MOS | 12 | $3,500.00 | $7,521.53 | $3,150.00 | $2,700.00 |
| 0030 | Fiber wrap concrete casing system , bridge no 3 (709-04647) | LS | 1 | $17,316 | $18,000 | $17,316 | $17,316 |
| 0031 | Fiber wrap concrete casing system , bridge no 4 (709-04647) | LS | 1 | $3,400.00 | $9,000.00 | $38,929 | $3,400.00 |
| 0032 | Fiber wrap concrete strengthening system , bridge no. 5 (709-12600) | LS | 1 | $38,929 | $18,000 | $3,400.00 | $38,929 |
| 0033 | Surface seal , bridge no 1 (709-51821) | LS | 1 | $4,422.00 | $3,241.83 | $4,422.00 | $4,422.00 |
| 0034 | Surface seal , bridge no 2 (709-51821) | LS | 1 | $3,096.00 | $2,116.53 | $3,096.00 | $3,096.00 |
| 0035 | Surface seal , bridge no 3 (709-51821) | LS | 1 | $6,417.00 | $6,083.64 | $6,417.00 | $6,417.00 |
| 0036 | Surface seal , bridge no 4 (709-51821) | LS | 1 | $6,417.00 | $6,083.64 | $6,417.00 | $6,417.00 |
| 0037 | Patching concrete structures (710-09158) | SFT | 430 | $197.00 | $60.00 | $197.00 | $135.40 |
| 0038 | Bridge deck overlay, rigid (722-000134) | SYS | 3,092 | $75.00 | $109.61 | $110.00 | $130.50 |
| 0039 | Bridge deck, remove concrete overlay and surface (722-000183) | SYS | 3,092 | $9.00 | $10.40 | $5.65 | $13.50 |
| 0040 | Hydrodemolition (722-01066) | SYS | 3,092 | $58.50 | $64.37 | $75.00 | $70.00 |
| 0041 | Bridge deck overlay budget (722-12380) | DOL | 53,840 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0042 | Longitudinal grooving (722-12732) | SYS | 3,092 | $10.50 | $4.59 | $5.00 | $7.00 |
| 0043 | Bridge deck patching, full depth (722-51401) | SFT | 200 | $50.00 | $130.54 | $60.00 | $76.00 |
| 0044 | Bridge deck patching, partial depth (722-51852) | SFT | 443 | $5.00 | $2.50 | $5.00 | $5.00 |
| 0045 | Overlay dam (722-51874) | SFT | 348 | $102.00 | $29.15 | $50.00 | $90.00 |
| 0046 | Concrete for patching bridge expansion joint (724-12461) | SFT | 264 | $50.00 | $123.99 | $170.00 | $140.00 |
| 0047 | Bridge expansion joint seal, type PCF, replace (724-12779) | LFT | 132 | $76.00 | $74.17 | $100.00 | $95.00 |
| 0048 | Epoxy injection, epoxy injection adhesive (727-000188) | GAL | 3 | $65.00 | $150.00 | $65.00 | $65.00 |
| 0049 | Epoxy injection, crack preparation (727-90308) | LFT | 49 | $122.00 | $90.00 | $122.00 | $122.00 |
| 0050 | Epoxy injection, furnishing equipment , bridge no 3 (727-93560) | LS | 1 | $965.00 | $1,200.00 | $965.00 | $965.00 |
| 0051 | Epoxy injection, furnishing equipment , bridge no. 5 (727-93560) | LS | 1 | $965.00 | $1,200.00 | $965.00 | $965.00 |
| 0052 | Warranted polymer overlay, bridge deck (738-12855) | SYS | 2,456 | $37.50 | $53.13 | $37.50 | $37.50 |
| 0053 | Road closure sign assembly (801-04308) | EACH | 6 | $384.00 | $384.00 | $384.00 | $245.00 |
| 0054 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 30,895 | $1.89 | $1.89 | $1.89 | $2.95 |
| 0055 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 10 | $10.94 | $10.94 | $10.94 | $15.00 |
| 0056 | Detour route marker assembly (801-06625) | EACH | 22 | $189.00 | $189.00 | $189.00 | $98.00 |
| 0057 | Construction sign, type A (801-06640) | EACH | 64 | $281.00 | $281.00 | $281.00 | $145.00 |
| 0058 | Construction sign, type B (801-06645) | EACH | 5 | $121.00 | $121.00 | $121.00 | $89.00 |
| 0059 | Flashing arrow sign (801-06710) | DAY | 279 | $18.00 | $18.00 | $18.00 | $15.00 |
| 0060 | Maintaining traffic (801-06775) | LS | 1 | $134,005 | $34,198 | $314,500 | $130,465 |
| 0061 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 4 | $12,500 | $8,400.00 | $8,400.00 | $8,400.00 |
| 0062 | Barricade, type III-A (801-07118) | LFT | 112 | $17.65 | $17.65 | $17.65 | $14.00 |
| 0063 | Barricade, type III-B (801-07119) | LFT | 152 | $17.65 | $17.65 | $17.65 | $14.00 |
| 0064 | Temporary traffic barrier, type 2 (801-08401) | LFT | 1,253 | $20.00 | $32.37 | $50.00 | $52.50 |
| 0065 | Truck mounted attenuator (801-12042) | DAY | 42 | $1,200.00 | $262.00 | $250.00 | $500.00 |
| 0066 | Temporary pavement marking, removable, 7 in. (801-12390) | LFT | 12,033 | $2.65 | $2.65 | $2.65 | $3.95 |
| 0067 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 12 | $781.00 | $781.00 | $781.00 | $850.00 |
| 0068 | Reference post (802-04893) | EACH | 4 | $2,000.00 | $550.00 | $275.00 | $750.00 |
| 0069 | Pavement message marking, remove (808-05866) | SYS | 2 | $32.44 | $32.44 | $32.44 | $245.00 |
| 0070 | Transverse marking, remove (808-06368) | LFT | 96 | $3.55 | $3.55 | $3.55 | $3.95 |
| 0071 | Line, remove (808-06716) | LFT | 1,287 | $0.78 | $0.78 | $0.78 | $0.98 |
| 0072 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 1,412 | $1.24 | $1.24 | $1.24 | $1.25 |
| 0073 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 1,522 | $1.24 | $1.24 | $1.24 | $1.25 |
| 0074 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 354 | $1.67 | $1.67 | $1.67 | $1.95 |
| 0075 | Pavement message marking, multi- component, lane indication arrow (808-10077) | EACH | 1 | $259.00 | $259.00 | $259.00 | $195.00 |
| 0076 | Transverse marking, multi-component, crosshatch line, yellow, 24 in. (808-10119) | LFT | 96 | $14.84 | $14.84 | $14.84 | $9.95 |
| 0077 | Grooving for pavement markings (808-12032) | LFT | 450 | $2.04 | $2.04 | $2.04 | $2.95 |
| 0078 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 12 | $60.00 | $250.00 | $25.00 | $35.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of September 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.