INDOT contract B-44405-A bid tabulation
BRIDGE DECK OVERLAY AND SMALL STRUCTURES CONSTRUCTION. Let by Indiana DOT on August 5, 2026, Dearborn, Seymour. 3 bids received; low bid $8,238,784 by Beaty Construction Inc.
- Owner
- Indiana DOT
- Letting
- 05 AUG 2026
- Pay items
- 163
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Beaty Construction Inc | $8,238,784 | Low |
| 2 | Milestone Contractors LP | $8,697,000 | +6.0% |
| 3 | Paul H Rohe Company Inc | $8,710,831 | +6.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Beaty Construction Inc | 2. Milestone Contractors LP | 3. Paul H Rohe Company Inc |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $20,000 | $35,000 | $23,700 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $410,000 | $432,800 | $284,290 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $82,000 | $275,000 | $82,940 |
| 0012 | Pavement removal (202-02240) | SYS | 1,773 | $50.00 | $38.60 | $27.00 |
| 0013 | Headwall, remove (202-02271) | EACH | 1 | $3,500.00 | $1,875.00 | $4,985.00 |
| 0014 | Pipe abandon and grout fill (202-02637) | LFT | 645 | $85.00 | $89.20 | $93.00 |
| 0015 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $141,000 | $225,000 | $193,280 |
| 0016 | Present structure, remove portions, structure no. 2 (202-51328) | LS | 1 | $141,000 | $225,000 | $198,600 |
| 0017 | Curb, asphalt, remove (202-94749) | LFT | 80 | $8.00 | $22.10 | $25.00 |
| 0018 | Barrier wall, concrete, remove (202-94954) | LFT | 971 | $18.00 | $81.60 | $54.00 |
| 0019 | Impact attenuator, remove (202-95027) | EACH | 2 | $4,000.00 | $13,400 | $990.00 |
| 0020 | Pipe, remove (202-96133) | LFT | 65 | $250.00 | $69.75 | $58.00 |
| 0021 | Excavation, common (203-02000) | CYS | 1,243 | $40.00 | $78.60 | $82.00 |
| 0022 | Linear grading (203-08607) | LFT | 140 | $10.00 | $50.00 | $40.00 |
| 0023 | Pump around (205-11626) | EACH | 2 | $60,000 | $45,000 | $16,170 |
| 0024 | Stormwater management budget (205-12108) | DOL | 71,039 | $1.00 | $1.00 | $1.00 |
| 0025 | Stormwater management implementation (205-12616) | LS | 1 | $80,000 | $91,000 | $50,000 |
| 0026 | SWQCP preparation (205-12618) | LS | 1 | $2,000.00 | $2,000.00 | $5,000.00 |
| 0027 | Subgrade treatment, type IC (207-09935) | SYS | 2,209 | $50.00 | $57.80 | $60.00 |
| 0028 | B borrow (211-02050) | CYS | 215 | $56.00 | $70.60 | $140.00 |
| 0029 | Aggregate for end bent backfill (211-06467) | CYS | 175 | $280.00 | $321.00 | $160.00 |
| 0030 | Structure backfill, type 2 (211-09265) | CYS | 229 | $56.00 | $70.00 | $150.00 |
| 0031 | Flowable backfill, removable (213-09270) | CYS | 61 | $200.00 | $343.00 | $420.00 |
| 0032 | Geotextile for pavement, type 2B (214-12239) | SYS | 2,357 | $4.50 | $4.55 | $6.50 |
| 0033 | Compacted aggregate, no. 8 (301-12233) | CYS | 448 | $275.00 | $83.12 | $140.00 |
| 0034 | Subbase for PCCP (302-06464) | CYS | 230 | $210.00 | $187.00 | $180.00 |
| 0035 | Compacted aggregate, no. 53 (303-01180) | TON | 982 | $45.00 | $58.35 | $76.00 |
| 0036 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 2,277 | $8.00 | $11.90 | $13.00 |
| 0037 | Milling, transition (306-08043) | SYS | 2,087 | $12.00 | $13.00 | $11.00 |
| 0038 | QC/QA-HMA, 4, 58E, surface, 9.5 MM (401-000009) | TON | 465 | $150.00 | $305.00 | $280.00 |
| 0039 | QC/QA-HMA, 4, 58E, intermediate, 19.0 MM (401-000045) | TON | 234 | $150.00 | $240.00 | $270.00 |
| 0040 | QC/QA-HMA, 4, 58S, base, 25.0 MM (401-000048) | TON | 898 | $150.00 | $154.00 | $190.00 |
| 0041 | Joint adhesive (401-11526) | LFT | 1,370 | $1.00 | $2.90 | $1.00 |
| 0042 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 9,442 | $10.00 | $8.25 | $8.70 |
| 0043 | HMA wedge and level, type D (402-07787) | TON | 38 | $150.00 | $390.00 | $240.00 |
| 0044 | HMA for temporary pavement, type D (402-10087) | TON | 3,661 | $150.00 | $113.00 | $166.00 |
| 0045 | Asphalt for tack coat (406-05520) | TON | 9 | $600.00 | $682.71 | $900.00 |
| 0046 | Terminal joint, type HMA (503-12477) | LFT | 208 | $425.00 | $435.00 | $530.00 |
| 0047 | Guardrail, remove (601-02241) | LFT | 563 | $16.50 | $16.50 | $16.50 |
| 0048 | Guardrail, reset (601-06035) | LFT | 103 | $30.00 | $30.00 | $30.00 |
| 0049 | Guardrail, W-beam, cable terminal anchor (601-06855) | EACH | 1 | $1,250.00 | $1,250.00 | $1,250.00 |
| 0050 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 1,125 | $27.00 | $27.00 | $27.00 |
| 0051 | Guardrail, MGS W-beam, 6 FT 3 in. spacing , temporary (601-12281) | LFT | 325 | $23.00 | $23.00 | $23.00 |
| 0052 | Guardrail height transition, MGS (601-12289) | EACH | 2 | $1,075.00 | $1,075.00 | $1,075.00 |
| 0053 | Guardrail transition, MGS with curb (601-12291) | EACH | 1 | $3,575.00 | $3,575.00 | $3,575.00 |
| 0054 | Guardrail transition, MGS without curb (601-12292) | EACH | 4 | $3,500.00 | $3,500.00 | $3,500.00 |
| 0055 | Guardrail transition, MGS without curb , temporary (601-12292) | EACH | 2 | $4,000.00 | $4,000.00 | $4,000.00 |
| 0056 | Guardrail end treatment, type OS (601-94689) | EACH | 2 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0057 | Guardrail end treatment, type OS , temporary (601-94689) | EACH | 2 | $2,500.00 | $2,500.00 | $2,500.00 |
| 0058 | Curb, concrete (605-06120) | LFT | 80 | $85.00 | $74.50 | $120.00 |
| 0059 | Curb and gutter, concrete , curb turnout (605-06140) | LFT | 7 | $240.00 | $300.00 | $550.00 |
| 0060 | Milled HMA corrugations, conventional (606-12399) | LFT | 5,070 | $4.00 | $2.50 | $2.50 |
| 0061 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 916.30 | $200.00 | $234.00 | $173.00 |
| 0062 | Monument, type B (615-06505) | EACH | 4 | $1,500.00 | $1,500.00 | $1,500.00 |
| 0063 | Riprap, class 2 (616-05689) | TON | 93 | $105.00 | $95.50 | $150.00 |
| 0064 | Riprap, revetment (616-06405) | TON | 175 | $90.00 | $76.50 | $120.00 |
| 0065 | Riprap, grouted, 12 in. (616-06425) | SYS | 58 | $105.00 | $193.00 | $170.00 |
| 0066 | Riprap, uniform (616-06451) | TON | 15 | $80.00 | $154.00 | $130.00 |
| 0067 | Geotextile for riprap, type 1A (616-12246) | SYS | 449 | $3.00 | $8.85 | $4.00 |
| 0068 | Mobilization and demobilization for seeding (621-01004) | EACH | 8 | $500.00 | $200.00 | $200.00 |
| 0069 | Fertilizer for permanent seeding (621-06545) | TON | 1 | $5.00 | $800.00 | $800.00 |
| 0070 | Seed mixture, type R (621-06553) | LBS | 371 | $55.00 | $15.00 | $15.00 |
| 0071 | Mulched seeding, type R (621-06559) | SYS | 2,947 | $2.25 | $1.35 | $1.35 |
| 0072 | Mulching material (621-06565) | TON | 4 | $550.00 | $500.00 | $500.00 |
| 0073 | Water (621-06567) | KGAL | 1 | $0.10 | $0.01 | $0.01 |
| 0074 | Sodding (621-06574) | SYS | 9 | $215.00 | $150.00 | $150.00 |
| 0075 | Cable barrier system, type TL-4, reset (627-11647) | LFT | 1,725 | $13.50 | $20.40 | $28.00 |
| 0076 | Computer system equipment (628-11976) | EACH | 3 | $1,000.00 | $885.00 | $1,000.00 |
| 0077 | Field office, type D (628-12683) | MOS | 24 | $4,000.00 | $4,425.00 | $3,800.00 |
| 0078 | Topsoil processing and distribution (629-000149) | SYS | 6,656 | $16.00 | $5.85 | $12.80 |
| 0079 | Topsoil amendment budget (629-000150) | DOL | 13,312 | $1.00 | $1.00 | $1.00 |
| 0080 | Temporary shoring , bridge no. 1 (702-04325) | LS | 1 | $50,000 | $15,840 | $108,150 |
| 0081 | Temporary shoring , bridge no. 2 (702-04325) | LS | 1 | $50,000 | $15,840 | $108,150 |
| 0082 | Concrete, A, substructure (702-51005) | CYS | 10 | $2,600.00 | $2,725.00 | $3,322.00 |
| 0083 | Reinforcing bars, epoxy coated (703-06029) | LBS | 77,967 | $1.75 | $1.95 | $1.31 |
| 0084 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 503 | $45.00 | $41.20 | $46.00 |
| 0085 | Concrete, C, superstructure (704-51002) | CYS | 131.50 | $1,650.00 | $1,490.00 | $2,080.00 |
| 0086 | Railing, concrete type FT , modified (706-11601) | CYS | 20.40 | $1,250.00 | $3,215.00 | $3,875.00 |
| 0087 | Concrete bridge railing transition, type TFT (706-11621) | EACH | 6 | $5,800.00 | $8,085.00 | $13,850 |
| 0088 | Fiber wrap concrete casing system , bridge no. 1 (709-04647) | LS | 1 | $17,891 | $17,891 | $17,890 |
| 0089 | Fiber wrap concrete casing system , bridge no. 2 (709-04647) | LS | 1 | $20,198 | $20,198 | $20,200 |
| 0090 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $4,250.00 | $7,700.00 | $4,250.00 |
| 0091 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $4,250.00 | $7,700.00 | $4,250.00 |
| 0092 | Patching concrete structures (710-09158) | SFT | 145 | $195.00 | $195.00 | $195.00 |
| 0093 | Structural steel , bridge no. 1 (711-51038) | LS | 1 | $50,000 | $55,925 | $48,685 |
| 0094 | Structural steel , bridge no. 2 (711-51038) | LS | 1 | $50,000 | $16,350 | $48,685 |
| 0095 | Drilled hole (711-51864) | EACH | 120 | $90.00 | $90.00 | $90.00 |
| 0096 | Jacking and supporting beams , bridge no. 1 (711-51877) | LS | 1 | $60,000 | $44,250 | $32,675 |
| 0097 | Jacking and supporting beams , bridge no. 2 (711-51877) | LS | 1 | $60,000 | $48,150 | $36,700 |
| 0098 | Safety metal end section, 6:1, diameter 15 in. , temporary (715-02628) | EACH | 1 | $1,500.00 | $1,030.00 | $2,350.00 |
| 0099 | Safety metal end section, 6:1, diameter 12 in. , temporary (715-03321) | EACH | 1 | $1,500.00 | $915.00 | $2,075.00 |
| 0100 | Pipe, type 2, circular, diameter 15 in. (715-05032) | LFT | 221 | $230.00 | $300.00 | $150.00 |
| 0101 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 190 | $45.00 | $39.80 | $96.00 |
| 0102 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 308 | $12.00 | $36.00 | $118.00 |
| 0103 | Pipe, slotted drain, diameter 12 in. , 0.064 inches temporary (715-05422) | LFT | 40 | $190.00 | $430.00 | $670.00 |
| 0104 | Video inspection for pipe (715-09064) | LFT | 221 | $18.10 | $18.10 | $13.00 |
| 0105 | Pipe end section, diameter 15 in. (715-46005) | EACH | 1 | $1,500.00 | $2,000.00 | $1,920.00 |
| 0106 | Pipe end section, diameter 36 in. (715-46040) | EACH | 2 | $4,500.00 | $3,280.00 | $3,700.00 |
| 0107 | Pipe installation, trenchless, 36 in. (716-07635) | LFT | 489 | $1,150.00 | $1,300.00 | $970.00 |
| 0108 | Outlet protector, type 2 (718-06529) | EACH | 4 | $2,000.00 | $6,650.00 | $6,900.00 |
| 0109 | Geotextile for underdrains, type 1A (718-12305) | SYS | 725 | $1.50 | $3.50 | $2.50 |
| 0110 | Geotextile for underdrains, type 2A (718-12307) | SYS | 18 | $5.00 | $8.00 | $30.00 |
| 0111 | Casting, catch basin, adjust to grade (720-12796) | EACH | 2 | $1,800.00 | $1,775.00 | $1,270.00 |
| 0112 | Casting, inlet, adjust to grade (720-12797) | EACH | 4 | $1,800.00 | $1,775.00 | $1,715.00 |
| 0113 | Inlet, type E7 (720-45030) | EACH | 1 | $3,500.00 | $4,300.00 | $5,920.00 |
| 0114 | Inlet, type F7 (720-45035) | EACH | 1 | $3,500.00 | $4,400.00 | $6,020.00 |
| 0115 | Catch basin, type K10 (720-45250) | EACH | 1 | $15,000 | $8,750.00 | $11,470 |
| 0116 | Bridge deck overlay, rigid (722-000134) | SYS | 2,849 | $100.00 | $104.00 | $167.00 |
| 0117 | Hydrodemolition (722-01066) | SYS | 2,726 | $65.00 | $90.00 | $61.00 |
| 0118 | Bridge deck overlay budget (722-12380) | DOL | 64,460 | $1.00 | $1.00 | $1.00 |
| 0119 | Bridge deck, remove concrete surface (722-12464) | SYS | 2,726 | $18.00 | $9.90 | $11.00 |
| 0120 | Longitudinal grooving (722-12732) | SYS | 3,764 | $3.50 | $8.65 | $3.50 |
| 0121 | Bridge deck patching, full depth (722-51401) | SFT | 100 | $195.00 | $65.85 | $154.00 |
| 0122 | Overlay dam (722-51874) | SFT | 254 | $60.00 | $92.75 | $230.00 |
| 0123 | Bridge expansion joint, type PCF (724-12773) | LFT | 138 | $90.00 | $138.00 | $85.00 |
| 0124 | Bearing assembly, reset (726-11773) | EACH | 11 | $1,200.00 | $825.00 | $825.00 |
| 0125 | Bearing assembly, elastomeric (726-92406) | EACH | 40 | $3,200.00 | $3,550.00 | $4,135.00 |
| 0126 | Construction sign, type C (801-03290) | EACH | 11 | $250.00 | $625.00 | $650.00 |
| 0127 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 153,911 | $2.07 | $1.45 | $1.50 |
| 0128 | Temporary transverse pavement marking, 24 in. (801-06216) | LFT | 84 | $20.00 | $15.00 | $15.00 |
| 0129 | Temporary pavement marking, removable, 8 in. (801-06469) | LFT | 30,465 | $3.10 | $2.40 | $2.50 |
| 0130 | Detour route marker assembly (801-06625) | EACH | 20 | $169.00 | $250.00 | $250.00 |
| 0131 | Construction sign, type A (801-06640) | EACH | 106 | $301.00 | $325.00 | $325.00 |
| 0132 | Construction sign, type B (801-06645) | EACH | 11 | $103.00 | $125.00 | $125.00 |
| 0133 | Temporary raised pavement marker, grade 1 (801-06649) | EACH | 1,782 | $25.00 | $25.00 | $25.00 |
| 0134 | Flashing arrow sign (801-06710) | DAY | 14 | $67.00 | $100.00 | $100.00 |
| 0135 | Maintaining traffic (801-06775) | LS | 1 | $522,000 | $690,687 | $387,415 |
| 0136 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 7 | $8,928.57 | $10,000 | $10,833 |
| 0137 | Barricade, type III-A (801-07118) | LFT | 144 | $15.00 | $25.00 | $25.00 |
| 0138 | Temporary crossover drainage pipe (801-07606) | LFT | 140 | $120.00 | $110.00 | $95.00 |
| 0139 | Temporary traffic barrier, type 1 (801-08400) | LFT | 2,390 | $50.00 | $34.80 | $66.50 |
| 0140 | Temporary traffic barrier, type 2 (801-08401) | LFT | 6,030 | $50.00 | $53.70 | $94.00 |
| 0141 | Portable changeable message sign (801-11642) | EACH | 14 | $3,458.00 | $4,500.00 | $4,500.00 |
| 0142 | Truck mounted attenuator (801-12042) | DAY | 4 | $1,500.00 | $2,000.00 | $1,970.00 |
| 0143 | Portable signal , bridge no. 1 (801-12081) | LS | 1 | $30,000 | $32,000 | $38,915 |
| 0144 | Fixed temporary signal , bridge no. 1 (801-12082) | LS | 1 | $77,100 | $66,950 | $73,000 |
| 0145 | Law enforcement officer (801-12324) | HRS | 1,024 | $75.00 | $75.00 | $75.00 |
| 0146 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 20 | $384.00 | $575.00 | $575.00 |
| 0147 | Temporary worksite speed limit sign assembly, intermittent (801-12930) | EACH | 4 | $1,580.00 | $5,000.00 | $5,000.00 |
| 0148 | Temporary crossover, type B (801-52817) | EACH | 2 | $300,000 | $232,800 | $217,240 |
| 0149 | Temporary buzz strips (801-97643) | LFT | 2,592 | $20.74 | $16.50 | $16.50 |
| 0150 | Reference post (802-04893) | EACH | 4 | $250.00 | $300.00 | $1,011.06 |
| 0151 | Line, remove (808-06716) | LFT | 20,115 | $0.78 | $0.65 | $0.65 |
| 0152 | Line, multi-component, solid, white, 8 in. (808-10037) | LFT | 800 | $3.00 | $4.00 | $4.00 |
| 0153 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 5,910 | $2.00 | $2.00 | $2.00 |
| 0154 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 5,880 | $2.00 | $2.00 | $2.00 |
| 0155 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 40 | $2.00 | $8.00 | $8.00 |
| 0156 | Grooving for pavement markings (808-12032) | LFT | 18,650 | $0.78 | $0.96 | $0.96 |
| 0157 | Line, preformed plastic, dotted, white, 10 in. (808-12848) | LFT | 450 | $28.27 | $15.00 | $15.00 |
| 0158 | Line, preformed plastic, broken, white, 6 in. (808-75055) | LFT | 1,430 | $7.00 | $10.00 | $10.00 |
| 0159 | Line, preformed plastic, solid, white, 12 in. (808-75326) | LFT | 85 | $14.07 | $20.00 | $20.00 |
| 0160 | Prismatic reflector (808-75994) | EACH | 88 | $25.00 | $25.00 | $25.00 |
| 0161 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 50 | $50.00 | $50.00 | $74.73 |
| 0162 | Snowplowable raised pavement marker (808-75998) | EACH | 40 | $85.00 | $250.00 | $250.00 |
| 0163 | Geogrid, type IB (214-11796) | SYS | 1,333 | $3.50 | $3.75 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of August 5, 2026. Compiled by Mirage Metrics.