INDOT contract B-44587-A bid tabulation
DEBRIS REMOVAL FROM CHANNEL. Let by Indiana DOT on February 12, 2025, Allen, Grant, Fort Wayne. 4 bids received; low bid $165,551 by Pioneer Associates Inc.
- Owner
- Indiana DOT
- Letting
- 12 FEB 2025
- Pay items
- 30
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pioneer Associates Inc | $165,551 | Low |
| 2 | Milestone Contractors LP | $187,026 | +13% |
| 3 | Yardberry Landscape Company | $210,407 | +27% |
| 4 | Morphey Construction Inc. | $252,571 | +53% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pioneer Associates Inc | 2. Milestone Contractors LP | 3. Yardberry Landscape Company | 4. Morphey Construction Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $5,850.00 | $3,000.00 | $10,000 | $5,000.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Mobilization and demobilization (110-01001) | LS | 1 | $31,500 | $9,351.30 | $10,000 | $15,000 |
| 0009 | Debris, remove, structure no. 1 (201-90788) | LS | 1 | $11,500 | $7,500.00 | $40,000 | $35,000 |
| 0010 | Debris, remove, structure no. 2 (201-90788) | LS | 1 | $12,500 | $70,000 | $40,000 | $35,000 |
| 0011 | Excavation, common (203-02000) | CYS | 20 | $130.00 | $138.00 | $300.00 | $250.00 |
| 0012 | Excavation, unclassified (203-02020) | CYS | 100 | $230.00 | $83.00 | $250.00 | $250.00 |
| 0013 | Stormwater management budget (205-12108) | DOL | 6,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0014 | Stormwater management implementation (205-12616) | LS | 1 | $2,100.00 | $3,000.00 | $8,000.00 | $2,000.00 |
| 0015 | Cofferdam (206-51235) | LS | 1 | $15,500 | $53,758 | $20,000 | $60,000 |
| 0016 | Guardrail, reset (601-06035) | LFT | 25 | $20.00 | $125.00 | $100.00 | $225.00 |
| 0017 | Erosion control blanket (621-02770) | SYS | 242 | $4.10 | $4.10 | $8.00 | $15.00 |
| 0018 | Seed mixture, floodplain (621-12612) | LBS | 1.50 | $463.00 | $463.00 | $1,200.00 | $1,000.00 |
| 0019 | Temporary pavement message marking, lane indication arrow (801-01504) | EACH | 1 | $123.00 | $200.00 | $225.00 | $200.00 |
| 0020 | Temporary pavement message marking, "only" (801-01505) | EACH | 1 | $148.00 | $250.00 | $275.00 | $250.00 |
| 0021 | Temporary pavement marking, removable, 5 in. (801-06208) | LFT | 25 | $1.50 | $2.00 | $4.00 | $2.00 |
| 0022 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 650 | $1.60 | $2.00 | $4.00 | $2.00 |
| 0023 | Temporary pavement marking, removable, 8 in. (801-06469) | LFT | 40 | $3.10 | $4.00 | $6.00 | $4.00 |
| 0024 | Construction sign, type A (801-06640) | EACH | 26 | $225.00 | $200.00 | $250.00 | $200.00 |
| 0025 | Construction sign, type B (801-06645) | EACH | 2 | $103.00 | $100.00 | $175.00 | $100.00 |
| 0026 | Flashing arrow sign (801-06710) | DAY | 5 | $16.00 | $50.00 | $65.00 | $50.00 |
| 0027 | Maintaining traffic (801-06775) | LS | 1 | $39,500 | $7,500.00 | $25,000 | $40,000 |
| 0028 | Truck mounted attenuator (801-12042) | DAY | 5 | $550.00 | $445.88 | $350.00 | $1,000.00 |
| 0029 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 2 | $1,100.00 | $400.00 | $500.00 | $400.00 |
| 0030 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $750.00 | $400.00 | $800.00 | $400.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 12, 2025. Compiled by Mirage Metrics.