INDOT contract B-44932-A bid tabulation
SCOUR PROTECTION. Let by Indiana DOT on August 5, 2026, Allen, Kosciusko, Whitley, Fort Wayne. 5 bids received; low bid $734,677 by Pioneer Associates Inc.
- Owner
- Indiana DOT
- Letting
- 05 AUG 2026
- Pay items
- 33
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pioneer Associates Inc | $734,677 | Low |
| 2 | Yarberry Companies Inc | $809,390 | +10% |
| 3 | Morphey Construction Inc. | $830,830 | +13% |
| 4 | E & B Paving LLC | $853,700 | +16% |
| 5 | Milestone Contractors LP | $973,637 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pioneer Associates Inc | 2. Yarberry Companies Inc | 3. Morphey Construction Inc. | 4. E & B Paving LLC | 5. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $5,800.00 | $25,000 | $7,500.00 | $5,000.00 | $16,000 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 10 | $1,200.00 | $500.00 | $450.00 | $1,000.00 | $1,600.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $82,500 | $53,000 | $47,500 | $60,000 | $48,682 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $33,500 | $40,000 | $40,000 | $20,000 | $20,000 |
| 0011 | Debris, remove, structure no. 3 (201-90788) | LS | 1 | $8,000.00 | $10,000 | $10,000 | $5,000.00 | $5,000.00 |
| 0012 | Pump around (205-11626) | EACH | 1 | $27,000 | $20,000 | $35,000 | $53,000 | $45,000 |
| 0013 | Stormwater management budget (205-12108) | DOL | 42,423 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0014 | Stormwater management implementation (205-12616) | LS | 1 | $3,400.00 | $20,000 | $5,000.00 | $15,000 | $10,000 |
| 0015 | Cofferdam (206-51235) | LS | 1 | $45,000 | $70,000 | $150,000 | $40,000 | $137,758 |
| 0016 | Compacted aggregate, no. 53 (303-01180) | TON | 18 | $120.00 | $150.00 | $110.00 | $250.00 | $550.00 |
| 0017 | Grout for riprap (616-02281) | CYS | 17 | $800.00 | $400.00 | $675.00 | $1,500.00 | $510.00 |
| 0018 | Riprap, class 2 (616-05689) | TON | 332 | $210.00 | $205.00 | $150.00 | $175.00 | $270.00 |
| 0019 | Riprap, revetment (616-06405) | TON | 1,566 | $125.00 | $160.00 | $160.00 | $85.00 | $180.00 |
| 0020 | Geotextile for riprap, type 1A (616-12246) | SYS | 314 | $5.00 | $15.00 | $4.00 | $3.00 | $8.00 |
| 0021 | Geotextile for riprap, type 2A (616-12248) | SYS | 1,818 | $5.00 | $15.00 | $4.00 | $3.00 | $8.00 |
| 0022 | Disposal of cleaning waste, hazardous, bridge no. 3 (619-12459) | LS | 1 | $500.00 | $1,000.00 | $2,000.00 | $500.00 | $500.00 |
| 0023 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $600.00 | $750.00 | $550.00 | $550.00 | $600.00 |
| 0024 | Erosion control blanket (621-02770) | SYS | 335 | $3.00 | $10.00 | $20.00 | $3.95 | $2.85 |
| 0025 | Seed mixture, type U (621-06554) | LBS | 11 | $25.00 | $45.00 | $150.00 | $20.70 | $25.00 |
| 0026 | Mulched seeding, type R (621-06559) | SYS | 1,152 | $3.00 | $2.00 | $13.00 | $4.60 | $2.90 |
| 0027 | Clean and epoxy coat existing piles (701-93790) | LS | 1 | $42,500 | $24,000 | $33,000 | $147,800 | $21,000 |
| 0028 | Concrete, A, substructure (702-51005) | CYS | 5.60 | $7,000.00 | $8,500.00 | $5,555.00 | $20,000 | $4,100.00 |
| 0029 | Reinforcing bars, epoxy coated (703-06029) | LBS | 1,214 | $8.00 | $8.00 | $2.50 | $20.00 | $8.00 |
| 0030 | Stud shear connectors (711-96800) | EACH | 168 | $20.00 | $75.00 | $25.00 | $20.00 | $30.00 |
| 0031 | Construction sign, type A (801-06640) | EACH | 18 | $175.00 | $225.00 | $168.00 | $175.00 | $250.00 |
| 0032 | Maintaining traffic (801-06775) | LS | 1 | $77,500 | $55,000 | $64,815 | $75,075 | $155,000 |
| 0033 | Sign, ground mounted, reset (802-91122) | EACH | 2 | $350.00 | $750.00 | $200.00 | $500.00 | $270.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of August 5, 2026. Compiled by Mirage Metrics.