BRIDGE REPLACEMENT. Let by Indiana DOT on February 12, 2025, Starke, LaPorte. 3 bids received; low bid $1,307,351 by Rieth-Riley Construction Co., Inc..
- Owner
- Indiana DOT
- Letting
- 12 FEB 2025
- Pay items
- 75
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rieth-Riley Construction Co., Inc. | $1,307,351 | Low |
| 2 | Superior Construction Co Inc | $1,652,942 | +26% |
| 3 | Milestone Contractors LP | $2,081,564 | +59% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rieth-Riley Construction Co., Inc. | 2. Superior Construction Co Inc | 3. Milestone Contractors LP |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $9,700.00 | $50,000 | $16,400 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $89,810 | $81,700 | $95,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $9,100.00 | $49,000 | $17,600 |
| 0011 | Paved side ditch, remove (202-02272) | LFT | 25 | $50.00 | $25.00 | $40.00 |
| 0012 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $39,100 | $280,054 | $82,000 |
| 0013 | Excavation, common (203-02000) | CYS | 370 | $37.00 | $40.00 | $110.00 |
| 0014 | Pump around (205-11626) | EACH | 1 | $54,390 | $15,000 | $382,000 |
| 0015 | Stormwater management budget (205-12108) | DOL | 10,695 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $12,835 | $13,000 | $6,500.00 |
| 0017 | Excavation, wet (206-51220) | CYS | 20 | $114.00 | $125.00 | $130.00 |
| 0018 | Cofferdam (206-51235) | LS | 1 | $8,360.00 | $50,000 | $106,000 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 458 | $74.00 | $28.00 | $60.00 |
| 0020 | Structure backfill, type 5 (211-09268) | CYS | 165 | $137.00 | $290.00 | $275.00 |
| 0021 | Geogrid, type IB (214-11796) | SYS | 453 | $2.00 | $11.00 | $3.00 |
| 0022 | Geotextile for pavement, type 2B (214-12239) | SYS | 95 | $22.00 | $15.00 | $42.00 |
| 0023 | Compacted aggregate, no. 5 (301-12232) | CYS | 9 | $490.00 | $275.00 | $980.00 |
| 0024 | Compacted aggregate, no. 53 (301-12234) | CYS | 9 | $490.00 | $275.00 | $930.00 |
| 0025 | Compacted aggregate, no. 73 (303-07449) | TON | 591 | $55.00 | $50.00 | $50.00 |
| 0026 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 271 | $40.00 | $12.00 | $22.00 |
| 0027 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 73 | $196.00 | $180.00 | $180.00 |
| 0028 | QC/QA-HMA, 3, 58S, intermediate, 9.5 MM (401-000020) | TON | 85 | $175.00 | $133.00 | $133.00 |
| 0029 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 272 | $138.00 | $107.00 | $107.00 |
| 0030 | Joint adhesive, surface (401-10258) | LFT | 600 | $2.60 | $1.00 | $1.00 |
| 0031 | Joint adhesive, intermediate (401-10259) | LFT | 500 | $3.15 | $1.00 | $1.00 |
| 0032 | Liquid asphalt sealant (401-11785) | LFT | 600 | $1.30 | $1.00 | $1.00 |
| 0033 | Asphalt for tack coat (406-05520) | TON | 2 | $1,300.00 | $1,200.00 | $1,200.00 |
| 0034 | Cracks and joints in asphalt pavement, rout and seal (408-07478) | TON | 1 | $1,500.00 | $2,400.00 | $2,500.00 |
| 0035 | Guardrail transition, type TGB (601-01522) | EACH | 1 | $2,900.00 | $2,900.00 | $2,900.00 |
| 0036 | Guardrail terminal system, W-beam curved, type 1 (601-01700) | EACH | 1 | $2,500.00 | $2,500.00 | $2,500.00 |
| 0037 | Guardrail, remove (601-02241) | LFT | 551 | $3.00 | $3.00 | $3.00 |
| 0038 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 82 | $20.00 | $20.00 | $20.00 |
| 0039 | Guardrail height transition, MGS (601-12289) | EACH | 3 | $950.00 | $950.00 | $950.00 |
| 0040 | Guardrail transition, MGS with curb (601-12291) | EACH | 3 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0041 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $2,900.00 | $2,900.00 | $2,900.00 |
| 0042 | Curb and gutter, concrete (605-06140) | LFT | 141 | $100.00 | $95.00 | $80.00 |
| 0043 | Paved side ditch, type A (607-06335) | LFT | 25 | $235.00 | $220.00 | $175.00 |
| 0044 | Right-of-way marker (615-06490) | EACH | 8 | $145.00 | $145.00 | $145.00 |
| 0045 | Monument, type B (615-06505) | EACH | 2 | $866.00 | $866.00 | $866.00 |
| 0046 | Riprap, revetment (616-06405) | TON | 126 | $155.00 | $100.00 | $140.00 |
| 0047 | Geotextile for riprap, type 1A (616-12246) | SYS | 165 | $7.00 | $9.00 | $11.50 |
| 0048 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $375.00 | $1,200.00 | $375.00 |
| 0049 | Mulched seeding, type R (621-06559) | SYS | 1,619 | $2.55 | $1.25 | $2.55 |
| 0050 | Topsoil (621-06570) | CYS | 179 | $125.00 | $100.00 | $95.00 |
| 0051 | Field office, type C (628-09403) | MOS | 6 | $2,500.00 | $1,700.00 | $2,500.00 |
| 0052 | Computer system equipment (628-11976) | EACH | 2 | $270.00 | $500.00 | $1,000.00 |
| 0053 | Concrete, A, substructure (702-51005) | CYS | 23 | $5,030.00 | $0.01 | $5,600.00 |
| 0054 | Reinforcing bars, epoxy coated (703-06029) | LBS | 4,100 | $3.00 | $1.60 | $2.05 |
| 0055 | Reinforced concrete moment slab, 12 in. (706-08496) | SYS | 140 | $350.00 | $211.00 | $288.00 |
| 0056 | Railing, concrete type FC (706-09960) | LFT | 64 | $200.00 | $250.00 | $235.00 |
| 0057 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $3,500.00 | $2,500.00 | $4,700.00 |
| 0058 | Surface seal (709-51821) | LS | 1 | $3,200.00 | $0.01 | $1.00 |
| 0059 | Waterproofing membrane type 3 (714-000087) | SFT | 2,040 | $4.00 | $8.00 | $13.40 |
| 0060 | Structure, reinforced concrete, three-sided (723-11208) | LFT | 47 | $11,100 | $15,000 | $16,290 |
| 0061 | Road closure sign assembly (801-04308) | EACH | 6 | $219.00 | $219.00 | $219.00 |
| 0062 | Detour route marker assembly (801-06625) | EACH | 29 | $131.00 | $131.00 | $131.00 |
| 0063 | Construction sign, type A (801-06640) | EACH | 16 | $163.00 | $163.00 | $163.00 |
| 0064 | Maintaining traffic (801-06775) | LS | 1 | $2,860.00 | $25,000 | $5,000.00 |
| 0065 | Barricade, type III-A (801-07118) | LFT | 48 | $13.88 | $13.88 | $13.88 |
| 0066 | Barricade, type III-B (801-07119) | LFT | 68 | $13.88 | $13.88 | $13.88 |
| 0067 | Reference post (802-04893) | EACH | 2 | $450.00 | $450.00 | $450.00 |
| 0068 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 69 | $26.00 | $26.00 | $26.00 |
| 0069 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 20 | $59.00 | $59.00 | $59.00 |
| 0070 | Sign, ground mounted, reset (802-91122) | EACH | 4 | $102.00 | $102.00 | $102.00 |
| 0071 | Line, paint, broken, yellow, 6 in. (808-12764) | LFT | 50 | $1.15 | $1.15 | $1.15 |
| 0072 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 400 | $1.03 | $1.03 | $1.03 |
| 0073 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 200 | $1.03 | $1.03 | $1.03 |
| 0074 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 5 | $21.00 | $21.00 | $25.00 |
| 0075 | Snowplowable raised pavement marker (808-75998) | EACH | 5 | $85.00 | $85.00 | $85.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.