INDOT contract B-44985-B bid tabulation
BRIDGE REPLACEMENT AND SLIDE CORRECTION. Let by Indiana DOT on May 7, 2025, Perry, Spencer, Vincennes. 5 bids received; low bid $5,133,000 by Mac Construction & Excavating Inc.
- Owner
- Indiana DOT
- Letting
- 07 MAY 2025
- Pay items
- 117
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Mac Construction & Excavating Inc | $5,133,000 | Low |
| 2 | Ragle, Inc. | $5,586,872 | +9.0% |
| 3 | Lutgring Brothers Inc | $5,590,000 | +9.0% |
| 4 | E & B Paving LLC | $5,649,660 | +10% |
| 5 | Force Construction Co Inc | $5,936,792 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Mac Construction & Excavating Inc | 2. Ragle, Inc. | 3. Lutgring Brothers Inc | 4. E & B Paving LLC | 5. Force Construction Co Inc |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $50,000 | $22,500 | $49,000 | $96,189 | $55,040 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $240,000 | $278,000 | $243,586 | $282,000 | $295,000 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $303,237 | $165,000 | $75,000 | $130,000 | $67,530 |
| 0012 | Gabions, remove (202-01073) | CYS | 28 | $70.00 | $60.00 | $75.00 | $112.00 | $183.00 |
| 0013 | Paved side ditch, remove (202-02272) | LFT | 106 | $35.00 | $16.50 | $3.00 | $23.28 | $20.00 |
| 0014 | Well , inclinometer, abandon (202-04890) | EACH | 1 | $5,000.00 | $8,000.00 | $5,000.00 | $10,215 | $5,192.00 |
| 0015 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $150,000 | $125,000 | $280,000 | $126,394 | $58,270 |
| 0016 | Present structure, remove, structure no. 2 (202-51330) | LS | 1 | $100,000 | $100,000 | $15,000 | $20,072 | $35,040 |
| 0017 | Retaining wall, remove , portions (202-90747) | LFT | 29 | $500.00 | $125.00 | $500.00 | $152.00 | $935.00 |
| 0018 | Excavation, common (203-02000) | CYS | 940 | $35.00 | $45.00 | $75.00 | $77.00 | $57.00 |
| 0019 | Excavation, rock (203-02010) | CYS | 20 | $500.00 | $160.00 | $300.00 | $300.00 | $183.00 |
| 0020 | Excavation, unclassified (203-02020) | CYS | 9,442 | $27.00 | $36.50 | $25.00 | $34.00 | $52.00 |
| 0021 | Borrow (203-02070) | CYS | 655 | $68.00 | $10.00 | $10.00 | $55.00 | $51.00 |
| 0022 | Pump around (205-11626) | EACH | 1 | $50,000 | $44,500 | $30,000 | $20,000 | $28,350 |
| 0023 | Stormwater management budget (205-12108) | DOL | 49,570 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0024 | Stormwater management implementation (205-12616) | LS | 1 | $100,000 | $35,000 | $25,000 | $66,000 | $16,880 |
| 0025 | Excavation, foundation, unclassified (206-51230) | CYS | 190 | $155.00 | $35.00 | $70.00 | $200.00 | $67.00 |
| 0026 | Cofferdam (206-51235) | LS | 1 | $50,000 | $74,500 | $55,000 | $40,000 | $219,990 |
| 0027 | Subgrade treatment, type II (207-08264) | SYS | 112 | $40.00 | $45.00 | $25.00 | $50.00 | $57.00 |
| 0028 | Subgrade treatment, type IC (207-09935) | SYS | 4,766 | $32.00 | $40.00 | $35.00 | $50.00 | $39.00 |
| 0029 | Structure backfill, type 1 (211-09264) | CYS | 7 | $300.00 | $125.00 | $90.00 | $100.00 | $193.00 |
| 0030 | Structure backfill, type 2 (211-09265) | CYS | 4,500 | $62.00 | $75.00 | $90.00 | $100.00 | $96.00 |
| 0031 | Geotextile for pavement, type 2B (214-12239) | SYS | 2,628 | $6.00 | $4.35 | $4.50 | $3.11 | $4.70 |
| 0032 | Compacted aggregate, no. 2 (301-12231) | CYS | 1,230 | $78.00 | $68.50 | $80.00 | $83.00 | $74.00 |
| 0033 | Compacted aggregate, no. 8 (301-12233) | CYS | 683 | $87.00 | $62.50 | $80.00 | $84.00 | $71.00 |
| 0034 | Compacted aggregate, no. 53 (301-12234) | CYS | 19 | $125.00 | $110.00 | $100.00 | $250.00 | $122.00 |
| 0035 | Compacted aggregate, no. 53 (303-01180) | TON | 362 | $45.00 | $57.50 | $55.00 | $83.43 | $54.00 |
| 0036 | HMA patching, partial depth, type B (304-12624) | TON | 195 | $238.00 | $146.00 | $180.00 | $200.66 | $187.00 |
| 0037 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 1,212 | $13.25 | $13.00 | $16.00 | $19.90 | $13.00 |
| 0038 | Milling, transition (306-08043) | SYS | 245 | $24.00 | $20.00 | $22.00 | $28.93 | $20.00 |
| 0039 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 233 | $200.00 | $249.00 | $248.00 | $248.00 | $258.00 |
| 0040 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 195 | $220.00 | $214.00 | $200.55 | $200.55 | $208.00 |
| 0041 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 290 | $162.00 | $154.00 | $154.00 | $154.00 | $160.00 |
| 0042 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 212 | $233.00 | $164.00 | $164.00 | $164.00 | $170.00 |
| 0043 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 1,039 | $108.00 | $135.00 | $135.00 | $135.00 | $140.00 |
| 0044 | QC/QA-HMA, 3, 58S, base, 19.0 MM (401-000053) | TON | 330 | $107.00 | $133.00 | $133.00 | $133.00 | $138.00 |
| 0045 | Joint adhesive, surface (401-10258) | LFT | 3,199 | $0.40 | $0.01 | $0.01 | $0.01 | $0.01 |
| 0046 | Joint adhesive, intermediate (401-10259) | LFT | 2,202 | $0.50 | $0.01 | $0.01 | $0.01 | $0.01 |
| 0047 | HMA for temporary pavement, type C (402-10086) | TON | 534 | $123.00 | $200.00 | $160.55 | $160.55 | $167.00 |
| 0048 | Asphalt for tack coat (406-05521) | SYS | 12,604 | $0.01 | $0.01 | $0.01 | $0.01 | $1.00 |
| 0049 | Guardrail terminal system, W-beam curved, type 1 (601-01700) | EACH | 1 | $3,100.00 | $3,400.00 | $3,400.00 | $3,400.00 | $3,531.00 |
| 0050 | Guardrail terminal system, W-beam curved, type 2 (601-01701) | EACH | 1 | $3,000.00 | $3,400.00 | $3,400.00 | $3,400.00 | $3,531.00 |
| 0051 | Guardrail, remove (601-02241) | LFT | 966 | $9.50 | $6.00 | $6.00 | $6.00 | $6.20 |
| 0052 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 715 | $22.00 | $21.00 | $21.00 | $21.00 | $22.00 |
| 0053 | Guardrail height transition, MGS (601-12289) | EACH | 7 | $917.00 | $1,300.00 | $1,300.00 | $1,300.00 | $1,350.00 |
| 0054 | Guardrail end treatment, type OS (601-94689) | EACH | 1 | $3,200.00 | $3,675.00 | $3,675.00 | $3,675.00 | $3,816.00 |
| 0055 | HMA for approaches, type B (610-07487) | TON | 25 | $300.00 | $437.00 | $437.00 | $437.00 | $454.00 |
| 0056 | Right-of-way marker (615-06490) | EACH | 11 | $200.00 | $180.00 | $275.00 | $180.00 | $187.00 |
| 0057 | Monument, type B (615-06505) | EACH | 6 | $1,100.00 | $1,075.00 | $1,500.00 | $1,075.00 | $1,116.00 |
| 0058 | Riprap, class 1 (616-05688) | TON | 1,068 | $56.00 | $95.00 | $90.00 | $119.64 | $82.00 |
| 0059 | Riprap, revetment (616-06405) | TON | 11,668 | $37.00 | $50.50 | $45.00 | $41.92 | $45.00 |
| 0060 | Geomembrane (616-09395) | SYS | 2,461 | $11.00 | $7.00 | $15.00 | $37.34 | $36.00 |
| 0061 | Geotextile for riprap, type 1A (616-12246) | SYS | 2,225 | $2.00 | $3.25 | $4.00 | $2.49 | $3.00 |
| 0062 | Geotextile for riprap, type 2B (616-12249) | SYS | 4,704 | $2.50 | $5.50 | $4.00 | $3.24 | $3.50 |
| 0063 | Mobilization and demobilization for seeding (621-01004) | EACH | 5 | $1,050.00 | $300.00 | $1,050.00 | $1,050.00 | $312.00 |
| 0064 | Mulched seeding, type R (621-06559) | SYS | 1,099 | $3.98 | $5.00 | $3.98 | $3.98 | $5.20 |
| 0065 | Mulched seeding, type U (621-06560) | SYS | 3,600 | $2.40 | $5.00 | $2.40 | $3.98 | $5.20 |
| 0066 | Computer system equipment (628-11976) | EACH | 2 | $1,800.00 | $750.00 | $1,000.00 | $750.00 | $889.00 |
| 0067 | Field office, type D (628-12683) | MOS | 20 | $2,900.00 | $2,200.00 | $2,450.00 | $3,741.97 | $4,222.00 |
| 0068 | Temporary shoring (702-04325) | LS | 1 | $150,000 | $150,000 | $150,000 | $216,876 | $154,300 |
| 0069 | Concrete, C, substructure (702-92857) | CYS | 25 | $1,600.00 | $1,350.00 | $1,355.00 | $429.94 | $1,831.00 |
| 0070 | Waterproofing membrane type 2 (714-000086) | SFT | 2,861 | $15.03 | $3.50 | $7.00 | $11.11 | $2.60 |
| 0071 | Structure, reinforced concrete, box sections, 22 FT X 9 FT (714-12964) | LFT | 147 | $3,600.00 | $4,150.00 | $3,950.00 | $4,000.00 | $3,281.00 |
| 0072 | Pipe, type 4, circular, diameter 12 in. (715-05052) | LFT | 474 | $39.00 | $26.50 | $18.00 | $18.00 | $81.00 |
| 0073 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 57 | $115.00 | $48.00 | $26.00 | $136.00 | $87.00 |
| 0074 | Pipe, type 3, circular, diameter 12 in. (715-05168) | LFT | 75 | $125.00 | $80.00 | $130.00 | $108.00 | $108.00 |
| 0075 | Video inspection for pipe (715-09064) | LFT | 44 | $75.00 | $70.00 | $1.00 | $73.90 | $104.00 |
| 0076 | Pipe end section, diameter 12 in. (715-46000) | EACH | 1 | $1,100.00 | $950.00 | $1,700.00 | $1,436.88 | $1,269.00 |
| 0077 | Catch basin, type E7 (720-45235) | EACH | 2 | $3,700.00 | $5,500.00 | $6,000.00 | $3,771.00 | $2,550.00 |
| 0078 | Manhole, type C4, drop (720-98625) | EACH | 1 | $6,200.00 | $7,600.00 | $6,000.00 | $5,600.00 | $7,579.00 |
| 0079 | Automatic drainage gate, diameter 12 in. (721-43000) | EACH | 1 | $4,250.00 | $3,000.00 | $2,400.00 | $3,000.00 | $2,793.00 |
| 0080 | Structure, reinforced concrete three-sided (723-12965) | LFT | 42 | $16,220 | $26,250 | $30,500 | $21,000 | $20,020 |
| 0081 | Construction sign, type C (801-03290) | EACH | 2 | $370.00 | $370.00 | $195.00 | $195.00 | $384.00 |
| 0082 | Road closure sign assembly (801-04308) | EACH | 9 | $303.00 | $303.00 | $295.00 | $295.00 | $315.00 |
| 0083 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 4,563 | $1.96 | $1.96 | $2.50 | $2.50 | $2.00 |
| 0084 | Temporary pavement message marking, removable, lane indication arrow (801-06211) | EACH | 7 | $217.00 | $217.00 | $95.00 | $95.00 | $225.00 |
| 0085 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 96 | $11.46 | $11.46 | $14.95 | $14.95 | $12.00 |
| 0086 | Detour route marker assembly (801-06625) | EACH | 57 | $190.00 | $190.00 | $89.00 | $89.00 | $197.00 |
| 0087 | Construction sign, type A (801-06640) | EACH | 45 | $240.00 | $240.00 | $165.00 | $165.00 | $249.00 |
| 0088 | Construction sign, type B (801-06645) | EACH | 12 | $98.00 | $98.00 | $89.00 | $89.00 | $102.00 |
| 0089 | Flashing arrow sign (801-06710) | DAY | 84 | $25.00 | $25.00 | $12.00 | $12.00 | $26.00 |
| 0090 | Maintaining traffic (801-06775) | LS | 1 | $200,000 | $85,000 | $75,000 | $69,602 | $445,000 |
| 0091 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $12,450 | $6,500.00 | $6,500.00 | $6,500.00 | $6,750.00 |
| 0092 | Barricade, type III-A (801-07118) | LFT | 156 | $14.00 | $14.00 | $12.00 | $12.00 | $15.00 |
| 0093 | Barricade, type III-B (801-07119) | LFT | 168 | $15.00 | $15.00 | $12.00 | $12.00 | $16.00 |
| 0094 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 564 | $35.00 | $60.00 | $78.00 | $136.48 | $76.00 |
| 0095 | Portable changeable message sign (801-11642) | EACH | 1 | $10,814 | $10,814 | $6,500.00 | $6,500.00 | $11,230 |
| 0096 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 2 | $338.00 | $338.00 | $795.00 | $795.00 | $351.00 |
| 0097 | Sign, sheet, relocate (802-07060) | EACH | 1 | $340.00 | $300.00 | $300.00 | $300.00 | $623.00 |
| 0098 | Conduit, PVC, 2 in. schedule 40 (805-08214) | LFT | 277 | $58.00 | $20.00 | $58.00 | $58.00 | $60.00 |
| 0099 | Conduit, HDPE, 2 in. schedule 80 (805-11815) | LFT | 28 | $58.00 | $20.00 | $58.00 | $58.00 | $60.00 |
| 0100 | Signal cable, roadway loop, copper, 1C/14 gauge (805-78470) | LFT | 229 | $2.00 | $0.70 | $2.00 | $2.00 | $2.10 |
| 0101 | Signal cable, detector lead-in, copper, 2C/16 gauge (805-78510) | LFT | 648 | $2.80 | $1.25 | $2.80 | $2.80 | $2.90 |
| 0102 | Signal detector housing (805-78785) | EACH | 1 | $4,200.00 | $1,300.00 | $4,200.00 | $4,200.00 | $4,362.00 |
| 0103 | Saw cut for roadway loop detector and sealant (805-78795) | LFT | 85 | $15.00 | $13.25 | $15.00 | $15.00 | $16.00 |
| 0104 | Line, remove (808-06716) | LFT | 1,800 | $1.38 | $1.38 | $0.98 | $0.98 | $1.40 |
| 0105 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 850 | $5.00 | $5.00 | $1.95 | $1.95 | $6.10 |
| 0106 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 850 | $5.00 | $5.00 | $1.95 | $1.95 | $6.10 |
| 0107 | Grooving for pavement markings (808-12032) | LFT | 2,799 | $3.39 | $3.39 | $0.98 | $0.98 | $3.50 |
| 0108 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 840 | $1.94 | $1.94 | $0.40 | $0.40 | $2.00 |
| 0109 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 1,645 | $2.61 | $2.61 | $1.25 | $1.25 | $2.70 |
| 0110 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 840 | $1.94 | $1.94 | $0.40 | $0.40 | $2.00 |
| 0111 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 1,154 | $2.61 | $2.61 | $1.25 | $1.25 | $2.70 |
| 0112 | Transverse marking, thermoplastic, crosshatch line, yellow, 8 in. (808-75274) | LFT | 138 | $3.48 | $3.48 | $2.95 | $2.95 | $3.60 |
| 0113 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 50 | $10.42 | $10.42 | $7.95 | $7.95 | $11.00 |
| 0114 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 3 | $219.00 | $219.00 | $135.00 | $135.00 | $227.00 |
| 0115 | Pavement message marking, thermoplastic, "only" (808-75325) | EACH | 3 | $295.00 | $295.00 | $195.00 | $195.00 | $306.00 |
| 0116 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 34 | $10.00 | $17.32 | $20.00 | $37.08 | $260.00 |
| 0117 | Snowplowable raised pavement marker (808-75998) | EACH | 32 | $412.50 | $100.00 | $130.00 | $130.00 | $341.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of May 7, 2025. Compiled by Mirage Metrics.