INDOT contract B-45490-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on December 10, 2025, Boone, Crawfordsville. 5 bids received; low bid $790,600 by Duncan Robertson Inc.
- Owner
- Indiana DOT
- Letting
- 10 DEC 2025
- Pay items
- 79
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Duncan Robertson Inc | $790,600 | Low |
| 2 | Pontem Contractors Inc | $862,694 | +9.0% |
| 3 | Milestone Contractors LP | $887,750 | +12% |
| 4 | His Constructors Inc | $990,141 | +25% |
| 5 | Beaty Construction Inc | $999,998 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Duncan Robertson Inc | 2. Pontem Contractors Inc | 3. Milestone Contractors LP | 4. His Constructors Inc | 5. Beaty Construction Inc |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $10,000 | $14,175 | $15,000 | $25,000 | $22,500 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $40,000 | $42,500 | $44,300 | $49,507 | $87,292 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $8,000.00 | $8,500.00 | $8,860.00 | $9,901.42 | $32,500 |
| 0011 | Present structure, remove, structure no. 06-00162 (202-51330) | LS | 1 | $55,000 | $125,071 | $44,200 | $50,000 | $91,240 |
| 0012 | Excavation, common (203-02000) | CYS | 430 | $25.00 | $51.99 | $92.00 | $46.00 | $49.00 |
| 0013 | Excavation, waterway (203-51223) | CYS | 170 | $65.00 | $58.78 | $73.00 | $54.00 | $59.00 |
| 0014 | Pump around (205-11626) | EACH | 1 | $8,000.00 | $24,744 | $1.00 | $40,000 | $74,500 |
| 0015 | Stormwater management budget (205-12108) | DOL | 12,655.31 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $12,500 | $2,961.21 | $1,550.00 | $3,500.00 | $8,000.00 |
| 0017 | Excavation, foundation, unclassified (206-51230) | CYS | 65 | $75.00 | $62.13 | $59.00 | $64.00 | $255.00 |
| 0018 | Subgrade treatment, type IC (207-09935) | SYS | 1,362 | $45.00 | $37.95 | $52.00 | $35.00 | $38.84 |
| 0019 | Aggregate for end bent backfill (211-06467) | CYS | 68 | $125.00 | $75.23 | $184.00 | $142.00 | $293.04 |
| 0020 | Geotextile for pavement, type 2B (214-12239) | SYS | 232 | $5.50 | $6.70 | $9.50 | $6.00 | $8.41 |
| 0021 | Subbase for PCCP (302-06464) | CYS | 48 | $150.00 | $167.93 | $160.00 | $175.00 | $139.25 |
| 0022 | Compacted aggregate, no. 53 (303-01180) | TON | 116 | $65.00 | $47.55 | $58.00 | $54.00 | $74.88 |
| 0023 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 96 | $158.00 | $151.20 | $170.40 | $144.00 | $144.00 |
| 0024 | QC/QA-HMA, 2, 58S, intermediate, 12.5 MM (401-000028) | TON | 127 | $136.00 | $130.20 | $148.00 | $124.00 | $124.00 |
| 0025 | QC/QA-HMA, 2, 58S, base, 19.0 MM (401-000052) | TON | 191 | $123.00 | $117.60 | $120.10 | $112.00 | $112.00 |
| 0026 | Joint adhesive (401-11526) | LFT | 909 | $2.20 | $2.10 | $1.00 | $2.00 | $2.00 |
| 0027 | Asphalt for tack coat (406-05521) | SYS | 1,153 | $0.23 | $0.22 | $0.30 | $0.21 | $0.27 |
| 0028 | Guardrail transition, type TGB (601-01522) | EACH | 4 | $3,368.00 | $2,756.25 | $2,625.00 | $2,625.00 | $3,210.06 |
| 0029 | Guardrail end treatment, type I (601-06037) | EACH | 4 | $1,457.00 | $1,391.25 | $1,325.00 | $1,325.00 | $1,715.72 |
| 0030 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 231.25 | $22.00 | $21.00 | $20.00 | $20.00 | $27.67 |
| 0031 | Barrier delineator (602-06729) | EACH | 6 | $30.00 | $132.55 | $78.83 | $23.61 | $30.29 |
| 0032 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 194 | $250.00 | $183.50 | $255.00 | $250.00 | $173.59 |
| 0033 | Riprap, revetment (616-06405) | TON | 156 | $55.00 | $43.72 | $145.00 | $69.00 | $81.42 |
| 0034 | Geotextile for riprap, type 1A (616-12246) | SYS | 282 | $3.50 | $4.33 | $2.00 | $6.00 | $4.36 |
| 0035 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $880.00 | $420.00 | $400.00 | $400.00 | $400.00 |
| 0036 | Erosion control blanket (621-02770) | SYS | 1,339 | $1.92 | $1.79 | $1.70 | $1.70 | $1.70 |
| 0037 | Fertilizer for permanent seeding (621-06545) | TON | 1 | $880.00 | $1,380.75 | $1,315.00 | $1,315.00 | $1,315.00 |
| 0038 | Seed mixture, type R (621-06553) | LBS | 57 | $11.00 | $11.13 | $10.60 | $10.60 | $10.60 |
| 0039 | Water (621-06567) | KGAL | 1 | $1.10 | $10.50 | $10.00 | $10.00 | $10.00 |
| 0040 | Sodding (621-06574) | SYS | 18 | $110.00 | $106.58 | $79.50 | $79.50 | $85.56 |
| 0041 | Field office, type C (628-09403) | MOS | 8 | $2,500.00 | $3,384.91 | $3,800.00 | $4,286.84 | $4,000.00 |
| 0042 | Cellular telephone, type A (628-11729) | EACH | 1 | $1,000.00 | $1,092.45 | $1,500.00 | $1,569.67 | $250.00 |
| 0043 | Cellular telephone, additional data (628-11731) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0044 | Cellular telephone, additional minutes (628-11732) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0045 | Cellular telephone service, 1000 min. (628-11782) | MOS | 8 | $100.00 | $34.14 | $170.00 | $204.74 | $100.00 |
| 0046 | Computer system equipment (628-11976) | EACH | 1 | $1,000.00 | $611.77 | $300.00 | $491.37 | $850.00 |
| 0047 | Computer system (628-11977) | EACH | 1 | $1,000.00 | $1,376.48 | $900.00 | $2,129.28 | $1,000.00 |
| 0048 | Test pile, indicator, production (701-09558) | LFT | 85 | $75.00 | $64.40 | $138.00 | $136.00 | $51.31 |
| 0049 | Test pile, indicator, restrike (701-09560) | EACH | 2 | $1,500.00 | $936.98 | $2,200.00 | $2,500.00 | $4,000.00 |
| 0050 | Pile, steel pipe, 0.312 in., diameter 14 in. (701-09663) | LFT | 390 | $75.00 | $66.82 | $140.00 | $78.00 | $105.00 |
| 0051 | Conical pile tip, 14 in. (701-09679) | EACH | 14 | $650.00 | $147.48 | $450.00 | $400.00 | $478.59 |
| 0052 | Concrete, B, footings (702-51015) | CYS | 15 | $650.00 | $718.30 | $1,145.00 | $2,250.00 | $647.30 |
| 0053 | Concrete, C, substructure (702-92857) | CYS | 83.20 | $850.00 | $820.43 | $1,210.00 | $1,500.00 | $925.14 |
| 0054 | Reinforcing bars, epoxy coated (703-06029) | LBS | 45,768 | $1.75 | $1.42 | $1.70 | $1.60 | $1.47 |
| 0055 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 30 | $65.00 | $41.18 | $60.00 | $56.00 | $56.52 |
| 0056 | Concrete, C, superstructure (704-51002) | CYS | 59.80 | $1,650.00 | $1,687.05 | $1,430.00 | $2,750.00 | $1,503.00 |
| 0057 | Railing, concrete type FC (706-09960) | LFT | 62 | $160.00 | $431.54 | $265.00 | $300.00 | $200.00 |
| 0058 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $2,500.00 | $5,730.56 | $4,900.00 | $4,000.00 | $1,284.86 |
| 0059 | Surface seal (709-51821) | LS | 1 | $1,500.00 | $5,250.00 | $1,000.00 | $2,500.00 | $1.00 |
| 0060 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 20 | $10.00 | $16.97 | $2.80 | $34.00 | $11.50 |
| 0061 | Pipe, type 4, circular, diameter 8 in. (715-05049) | LFT | 20 | $12.00 | $20.48 | $6.00 | $37.00 | $11.50 |
| 0062 | Pipe, type 4, circular, diameter 12 in. (715-05052) | LFT | 20 | $17.00 | $26.75 | $9.00 | $43.00 | $19.00 |
| 0063 | Pipe, type 4, circular, diameter 4 in. (715-05203) | LFT | 20 | $8.00 | $15.56 | $2.00 | $32.00 | $10.00 |
| 0064 | Pipe, type 4, circular, diameter 15 in. (715-05208) | LFT | 20 | $22.00 | $30.83 | $13.00 | $46.00 | $21.00 |
| 0065 | Pipe, type 4, circular, diameter 18 in. (715-05209) | LFT | 20 | $30.00 | $38.35 | $16.00 | $53.00 | $29.00 |
| 0066 | Pipe, type 4, circular, diameter 24 in. (715-05212) | LFT | 20 | $50.00 | $54.65 | $27.00 | $68.00 | $41.50 |
| 0067 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 128 | $15.00 | $10.93 | $7.00 | $18.00 | $10.00 |
| 0068 | Geotextile for underdrains, type 2A (718-12307) | SYS | 82 | $3.50 | $2.05 | $5.50 | $11.00 | $15.66 |
| 0069 | Longitudinal grooving (722-12732) | SYS | 294 | $15.00 | $23.65 | $10.00 | $9.00 | $9.41 |
| 0070 | Road closure sign assembly (801-04308) | EACH | 4 | $352.00 | $336.00 | $320.00 | $320.00 | $320.00 |
| 0071 | Detour route marker assembly (801-06625) | EACH | 6 | $177.00 | $169.05 | $161.00 | $161.00 | $125.00 |
| 0072 | Construction sign, type A (801-06640) | EACH | 4 | $250.00 | $238.35 | $227.00 | $227.00 | $185.00 |
| 0073 | Maintaining traffic (801-06775) | LS | 1 | $12,500 | $8,268.07 | $1,955.11 | $5,419.32 | $27,500 |
| 0074 | Barricade, type III-A (801-07118) | LFT | 48 | $16.00 | $15.75 | $15.00 | $15.00 | $16.00 |
| 0075 | Barricade, type III-B (801-07119) | LFT | 40 | $20.00 | $18.90 | $18.00 | $18.00 | $16.00 |
| 0076 | Sign, sheet, with legend (802-03821) | EACH | 4 | $132.00 | $126.00 | $120.00 | $120.00 | $131.73 |
| 0077 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 32 | $31.00 | $29.40 | $28.00 | $28.00 | $34.31 |
| 0078 | Line, paint, broken, yellow, 4 in. (808-06712) | LFT | 130 | $3.40 | $3.29 | $3.13 | $3.13 | $1.00 |
| 0079 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 1,040 | $0.92 | $0.87 | $0.83 | $0.83 | $0.70 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of December 10, 2025. Compiled by Mirage Metrics.