INDOT contract R-39624-A bid tabulation
BIKE AND PEDESTRIAN FACILITIES. Let by Indiana DOT on January 14, 2026, Lake, LaPorte. 4 bids received; low bid $1,693,812 by Rieth-Riley Construction Co., Inc..
- Owner
- Indiana DOT
- Letting
- 14 JAN 2026
- Pay items
- 101
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rieth-Riley Construction Co., Inc. | $1,693,812 | Low |
| 2 | Milestone Contractors LP | $1,928,072 | +14% |
| 3 | Dyer Construction Co Inc | $2,197,967 | +30% |
| 4 | Gariup Construction Co Inc | $2,427,500 | +43% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rieth-Riley Construction Co., Inc. | 2. Milestone Contractors LP | 3. Dyer Construction Co Inc | 4. Gariup Construction Co Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $75,000 | $28,000 | $55,546 | $40,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $164,000 | $89,400 | $345,418 | $213,614 |
| 0010 | Tree, 6 in., remove (201-02245) | EACH | 1 | $90.00 | $50.00 | $40.00 | $60.00 |
| 0011 | Tree, 10 in., remove (201-02250) | EACH | 4 | $110.00 | $100.00 | $80.00 | $120.00 |
| 0012 | Tree, 18 in., remove (201-02255) | EACH | 207 | $200.00 | $200.00 | $165.00 | $220.00 |
| 0013 | Tree, 30 in., remove (201-02260) | EACH | 12 | $600.00 | $800.00 | $300.00 | $890.00 |
| 0014 | Clearing right-of-way (201-52370) | LS | 1 | $60,000 | $41,000 | $66,621 | $40,000 |
| 0015 | Regulated materials, remove, type Y (202-07553) | CYS | 50 | $81.00 | $81.00 | $81.00 | $180.00 |
| 0016 | Regulated materials, transport, type Y (202-07554) | CYS | 50 | $40.50 | $40.50 | $40.50 | $85.00 |
| 0017 | Regulated materials, dispose, type Y (202-07555) | CYS | 50 | $64.10 | $64.10 | $64.10 | $105.00 |
| 0018 | Regulated materials, dispose, type Z (202-09243) | CYS | 50 | $1,470.00 | $1,470.00 | $1,470.00 | $1,700.00 |
| 0019 | Regulated materials, remove, type Z (202-09244) | CYS | 50 | $81.00 | $81.00 | $81.00 | $100.00 |
| 0020 | Regulated materials, transport, type Z (202-09245) | CYS | 50 | $110.00 | $110.00 | $110.00 | $130.00 |
| 0021 | Concrete, remove (202-93615) | SYS | 75 | $50.00 | $45.00 | $21.18 | $50.00 |
| 0022 | Fence and posts, remove (202-96430) | LS | 1 | $10,000 | $3,000.00 | $7,500.00 | $10,000 |
| 0023 | Excavation, common (203-02000) | CYS | 4,241 | $15.00 | $50.00 | $37.82 | $62.00 |
| 0024 | Excavation, unclassified (203-02020) | CYS | 500 | $35.00 | $51.00 | $52.52 | $75.00 |
| 0025 | Stormwater management budget (205-12108) | DOL | 20,840 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0026 | Stormwater management implementation (205-12616) | LS | 1 | $30,000 | $3,215.00 | $37,463 | $30,000 |
| 0027 | SWQCP preparation (205-12618) | LS | 1 | $3,440.00 | $2,000.00 | $3,440.00 | $2,500.00 |
| 0028 | Subgrade treatment, type II (207-08264) | SYS | 100 | $44.00 | $40.00 | $21.60 | $30.00 |
| 0029 | Subgrade treatment, type IC (207-09935) | SYS | 7,028 | $31.00 | $44.00 | $33.72 | $45.00 |
| 0030 | B borrow (211-02050) | CYS | 2,430 | $10.00 | $55.00 | $54.24 | $60.00 |
| 0031 | Structure backfill, type 1 (211-09264) | CYS | 10 | $80.00 | $80.00 | $42.39 | $100.00 |
| 0032 | Geotextile for pavement, type 2B (214-12239) | SYS | 7,050 | $2.50 | $3.50 | $3.80 | $4.50 |
| 0033 | Compacted aggregate, no. 53 (301-12234) | CYS | 2,050 | $20.00 | $55.00 | $75.98 | $80.00 |
| 0034 | HMA patching, partial depth, type B (304-12624) | TON | 5 | $894.00 | $450.00 | $825.00 | $925.00 |
| 0035 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 67 | $200.00 | $166.00 | $207.00 | $230.00 |
| 0036 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 112 | $200.00 | $135.00 | $140.00 | $160.00 |
| 0037 | QC/QA-HMA, 4, 58S, base, 25.0 MM (401-000048) | TON | 366 | $150.00 | $110.00 | $103.00 | $115.00 |
| 0038 | Asphalt for tack coat (406-05520) | TON | 1.14 | $3,100.00 | $2,000.00 | $5,200.00 | $5,800.00 |
| 0039 | Guardrail terminal system, W-beam, curved, type 1 (601-01700) | EACH | 1 | $3,088.00 | $3,088.00 | $3,000.00 | $3,500.00 |
| 0040 | Guardrail, remove (601-02241) | LFT | 210 | $5.00 | $5.00 | $13.48 | $5.60 |
| 0041 | Hand dig guardrail post holes (601-09238) | EACH | 21 | $101.00 | $101.00 | $340.00 | $115.00 |
| 0042 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 1,427 | $27.00 | $27.00 | $34.50 | $30.00 |
| 0043 | Guardrail end treatment, type OS (601-94689) | EACH | 2 | $3,207.00 | $3,207.00 | $2,675.00 | $3,600.00 |
| 0044 | Fence gate, chain link, 72 in. X 12 FT (603-08648) | EACH | 2 | $2,500.00 | $2,000.00 | $3,155.00 | $2,250.00 |
| 0045 | Fence, chain link, 72 in. (603-92636) | LFT | 389 | $50.00 | $63.00 | $49.75 | $70.00 |
| 0046 | HMA for sidewalk (604-05528) | TON | 800 | $130.00 | $117.50 | $108.00 | $120.00 |
| 0047 | Sidewalk, concrete (604-06070) | SYS | 1,330 | $75.00 | $57.00 | $56.30 | $70.00 |
| 0048 | Curb ramp, concrete (604-08086) | SYS | 45 | $130.00 | $275.00 | $40.50 | $180.00 |
| 0049 | Detectable warning surfaces (604-12083) | SYS | 12 | $312.00 | $150.00 | $225.00 | $400.00 |
| 0050 | Curb and gutter, concrete (605-06140) | LFT | 42 | $106.00 | $62.00 | $62.10 | $60.00 |
| 0051 | HMA for approaches, type B (610-07487) | TON | 57 | $189.00 | $180.00 | $196.00 | $220.00 |
| 0052 | Riprap, revetment (616-06405) | TON | 6 | $300.00 | $300.00 | $140.63 | $300.00 |
| 0053 | Geotextile for riprap, type 2A (616-12248) | SYS | 22 | $25.00 | $25.00 | $38.47 | $30.00 |
| 0054 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $575.00 | $750.00 | $575.00 | $840.00 |
| 0055 | Seeding wetland (621-02356) | LBS | 4 | $765.00 | $220.00 | $765.00 | $250.00 |
| 0056 | Fertilizer for permanent seeding (621-06545) | TON | 1 | $1,595.00 | $1,100.00 | $1,595.00 | $1,250.00 |
| 0057 | Seed mixture, type U (621-06554) | LBS | 330 | $10.70 | $6.60 | $10.70 | $7.40 |
| 0058 | Mulching material (621-06565) | TON | 5 | $985.00 | $580.00 | $985.00 | $650.00 |
| 0059 | Water (621-06567) | KGAL | 170 | $15.00 | $125.00 | $15.00 | $140.00 |
| 0060 | Field office, type C (628-09403) | MOS | 18 | $2,000.00 | $2,800.00 | $4,407.59 | $6,000.00 |
| 0061 | Computer system equipment (628-11976) | EACH | 1 | $400.00 | $850.00 | $1,927.21 | $5,000.00 |
| 0062 | Topsoil processing and distribution (629-000149) | SYS | 10,600 | $6.50 | $9.00 | $9.94 | $13.00 |
| 0063 | Topsoil amendment budget (629-000150) | DOL | 21,200 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0064 | Safety metal end section, 4:1, diameter 36 in. (715-02397) | EACH | 1 | $10,000 | $10,000 | $5,762.20 | $5,000.00 |
| 0065 | Pipe, type 3, circular, diameter 36 in. (715-05177) | LFT | 24 | $300.00 | $300.00 | $340.93 | $550.00 |
| 0066 | Video inspection for pipe (715-09064) | LFT | 24 | $135.45 | $120.00 | $135.45 | $100.00 |
| 0067 | Pipe end section, diameter 36 in. (715-46040) | EACH | 1 | $7,500.00 | $7,500.00 | $3,588.65 | $2,800.00 |
| 0068 | Construction sign, type A (801-06640) | EACH | 14 | $225.00 | $225.00 | $225.00 | $260.00 |
| 0069 | Construction sign, type B (801-06645) | EACH | 6 | $175.00 | $175.00 | $175.00 | $200.00 |
| 0070 | Flashing arrow sign (801-06710) | DAY | 21 | $20.00 | $20.00 | $20.00 | $25.00 |
| 0071 | Maintaining traffic (801-06775) | LS | 1 | $65,000 | $35,000 | $33,678 | $30,000 |
| 0072 | Barricade, type III-B (801-07119) | LFT | 100 | $15.00 | $15.00 | $15.00 | $17.00 |
| 0073 | Temporary traffic barrier, type 2 (801-08401) | LFT | 60 | $30.00 | $120.00 | $75.00 | $130.00 |
| 0074 | Temporary curb ramp (801-11990) | EACH | 1 | $3,450.00 | $2,000.00 | $2,000.00 | $2,300.00 |
| 0075 | Temporary pedestrian channelizer (801-12862) | LFT | 50 | $37.50 | $37.50 | $37.50 | $42.00 |
| 0076 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 287 | $32.27 | $32.27 | $30.00 | $34.00 |
| 0077 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 105 | $33.97 | $33.97 | $29.00 | $33.00 |
| 0078 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 61 | $35.11 | $35.11 | $31.00 | $35.00 |
| 0079 | Controller cabinet foundation, type P1, modified (805-01479) | EACH | 1 | $2,006.22 | $2,006.22 | $1,500.00 | $1,700.00 |
| 0080 | Handhole, signal, type 1 (805-01842) | EACH | 3 | $2,409.08 | $2,409.08 | $2,100.00 | $2,400.00 |
| 0081 | Conduit, steel, galvanized, 2 in. (805-01844) | LFT | 200 | $43.85 | $43.85 | $46.00 | $52.00 |
| 0082 | Pedestrian signal head, countdown, 18 in. (805-02150) | EACH | 1 | $1,432.25 | $1,432.25 | $1,200.00 | $1,340.00 |
| 0083 | Controller and cabinet, type P1 (805-02445) | EACH | 1 | $17,634 | $17,634 | $17,500 | $19,000 |
| 0084 | Signal pole, pedestal, 12 FT (805-04133) | EACH | 2 | $1,489.40 | $1,489.40 | $1,200.00 | $1,340.00 |
| 0085 | Signal cantilever structure, single arm 25 FT (805-11375) | EACH | 1 | $18,431 | $18,431 | $19,900 | $22,000 |
| 0086 | Signal cantilever structure, single arm 30 FT (805-11376) | EACH | 1 | $19,133 | $19,133 | $21,900 | $24,500 |
| 0087 | Signal cantilever structure, drilled shaft foundation, type A (805-11383) | EACH | 2 | $9,039.32 | $9,039.32 | $9,200.00 | $10,300 |
| 0088 | Pedestrian hybrid beacon (805-11496) | EACH | 6 | $1,569.70 | $1,569.70 | $1,424.00 | $1,590.00 |
| 0089 | Pedestrian push button, APS (805-11817) | EACH | 2 | $1,510.25 | $1,510.25 | $1,150.00 | $1,280.00 |
| 0090 | Uninterruptible power supply (805-12016) | EACH | 1 | $7,297.45 | $7,297.45 | $8,100.00 | $9,100.00 |
| 0091 | Signal pole, pedestal, 5 FT (805-12650) | EACH | 1 | $1,129.40 | $1,129.40 | $900.00 | $1,000.00 |
| 0092 | Signal service (805-78445) | EACH | 1 | $2,789.41 | $2,789.41 | $4,100.00 | $4,600.00 |
| 0093 | Signal cable, service, copper, 3C/8 gauge (805-78467) | LFT | 75 | $5.41 | $5.41 | $8.00 | $9.00 |
| 0094 | Signal cable, control, copper, 3C/14 gauge (805-78480) | LFT | 100 | $4.08 | $4.08 | $2.00 | $2.30 |
| 0095 | Signal cable, control, copper, 5C/14 gauge (805-78485) | LFT | 575 | $5.31 | $5.31 | $3.00 | $3.30 |
| 0096 | Signal cable, control, copper, 7C/14 gauge (805-78490) | LFT | 120 | $5.71 | $5.71 | $5.00 | $5.60 |
| 0097 | Signal pole, timber, 5, 35 FT (805-97042) | EACH | 1 | $1,932.25 | $1,932.25 | $1,600.00 | $1,780.00 |
| 0098 | Transverse marking, thermoplastic, crosswalk line, white, 24 in. (808-03439) | LFT | 160 | $7.00 | $7.00 | $7.00 | $8.00 |
| 0099 | Transverse marking, paint, stop line, white, 24 in. (808-06726) | LFT | 15 | $7.00 | $7.00 | $7.00 | $8.00 |
| 0100 | Line, thermoplastic, solid, white, 12 in. (808-75215) | LFT | 230 | $4.00 | $4.00 | $4.00 | $4.50 |
| 0101 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 80 | $6.00 | $6.00 | $6.00 | $5.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.