HMA OVERLAY, STRUCTURAL. Let by Indiana DOT on August 5, 2026, Huntington, Wabash, Fort Wayne. 3 bids received; low bid $12,839,926 by Brooks Construction Company Inc.
- Owner
- Indiana DOT
- Letting
- 05 AUG 2026
- Pay items
- 57
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Brooks Construction Company Inc | $12,839,926 | Low |
| 2 | Phend & Brown Inc | $12,945,550 | +1.0% |
| 3 | E & B Paving LLC | $13,402,444 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Brooks Construction Company Inc | 2. Phend & Brown Inc | 3. E & B Paving LLC |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $150,000 | $235,000 | $151,313 |
| 0002 | Railroad flagging budget (107-12976) | DOL | 15,500 | $1.00 | $1.00 | $1.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $640,000 | $550,000 | $675,481 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $50,000 | $45,000 | $132,500 |
| 0012 | Excavation, common (203-02000) | CYS | 11,620 | $48.00 | $38.00 | $30.00 |
| 0013 | Subgrade treatment, type II (207-08264) | SYS | 1,653 | $25.00 | $49.00 | $50.00 |
| 0014 | Subgrade treatment, type IC (207-09935) | SYS | 11,381 | $31.00 | $40.00 | $30.00 |
| 0015 | Flowable backfill, non- removable (213-09269) | CYS | 12 | $275.00 | $190.00 | $157.00 |
| 0016 | Geotextile for pavement, type 2A (214-12238) | SYS | 4,000 | $5.00 | $4.50 | $2.00 |
| 0017 | Compacted aggregate, no. 5 (301-12232) | CYS | 638 | $75.00 | $45.00 | $50.00 |
| 0018 | Compacted aggregate, no. 53 (301-12234) | CYS | 959 | $62.00 | $45.00 | $50.00 |
| 0019 | Compacted aggregate, no. 53 (303-01180) | TON | 20,485 | $30.00 | $20.00 | $21.00 |
| 0020 | HMA patching, full depth, type B (304-12623) | TON | 1,607 | $165.00 | $150.00 | $70.00 |
| 0021 | Milling, asphalt, 1 in. (306-08033) | SYS | 191,308 | $1.30 | $1.35 | $1.30 |
| 0022 | Milling, scarification (306-08042) | SYS | 192,542 | $0.95 | $1.05 | $1.08 |
| 0023 | Milling, transition (306-08043) | SYS | 361 | $4.75 | $15.00 | $2.51 |
| 0024 | Milling, approach (306-08432) | SYS | 2,586 | $4.50 | $9.00 | $12.00 |
| 0025 | Milling, asphalt, 6 in. (306-10127) | SYS | 163,720 | $4.80 | $3.15 | $7.45 |
| 0026 | Corrective aggregate, FDR (307-12253) | TON | 6,379 | $18.00 | $23.00 | $48.22 |
| 0027 | Full depth reclamation (307-12254) | SYS | 191,308 | $5.25 | $6.50 | $6.00 |
| 0028 | Stabilizing material, portland cement (307-12256) | TON | 6,027 | $222.00 | $222.00 | $222.00 |
| 0029 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 15,158 | $81.00 | $98.00 | $90.00 |
| 0030 | QC/QA-HMA, 2, 58S, intermediate, 9.5 MM (401-000019) | TON | 15,446 | $81.00 | $94.00 | $90.00 |
| 0031 | Joint adhesive (401-11526) | LFT | 80,199 | $0.25 | $0.35 | $0.30 |
| 0032 | Inertial profiler, HMA (401-12169) | LS | 1 | $13,000 | $18,000 | $25,000 |
| 0033 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 80,199 | $2.35 | $2.28 | $2.50 |
| 0034 | Asphalt for tack coat (406-05520) | TON | 133 | $600.00 | $650.00 | $600.00 |
| 0035 | Cracks in asphalt pavement, fill (408-12028) | TON | 1 | $2,000.00 | $650.00 | $500.00 |
| 0036 | Cold central plant recycling (417-12211) | SYS | 192,542 | $10.50 | $8.50 | $9.45 |
| 0037 | Corrective aggregate, CCPR (417-12212) | TON | 200 | $25.00 | $16.00 | $10.82 |
| 0038 | Stabilizing material, asphalt emulsion, CCPR (417-12213) | TON | 997 | $876.00 | $850.00 | $790.00 |
| 0039 | PCCP patching, partial depth , 7 in. (506-06334) | SYS | 72 | $240.00 | $250.00 | $300.00 |
| 0040 | Milled HMA corrugations, conventional , modified (606-12399) | LFT | 6,058 | $3.00 | $1.35 | $1.30 |
| 0041 | HMA for approaches, type B (610-07487) | TON | 1,385 | $130.00 | $245.00 | $375.00 |
| 0042 | Mailbox assembly, reset, single (611-08232) | EACH | 59 | $275.00 | $425.00 | $275.00 |
| 0043 | Mailbox assembly, reset, double (611-08233) | EACH | 7 | $550.00 | $500.00 | $550.00 |
| 0044 | Monument, section corner (615-06527) | EACH | 78 | $685.00 | $700.00 | $685.00 |
| 0045 | Field office, type D (628-12683) | MOS | 12 | $4,500.00 | $5,500.00 | $4,500.00 |
| 0046 | Road closure sign assembly (801-04308) | EACH | 12 | $245.00 | $258.00 | $258.00 |
| 0047 | Detour route marker assembly (801-06625) | EACH | 33 | $230.00 | $136.00 | $136.00 |
| 0048 | Construction sign, type A (801-06640) | EACH | 16 | $260.00 | $198.00 | $198.00 |
| 0049 | Maintaining traffic (801-06775) | LS | 1 | $240,127 | $300,000 | $60,000 |
| 0050 | Barricade, type III-B (801-07119) | LFT | 240 | $19.00 | $15.01 | $15.01 |
| 0051 | Construction signs mobile (801-92448) | DAY | 570 | $1.00 | $10.00 | $10.00 |
| 0052 | Transverse marking, paint, stop line, white, 24 in. (808-06726) | LFT | 113 | $9.00 | $10.11 | $10.11 |
| 0053 | Retro-reflectivity testing (808-09381) | LS | 1 | $3,200.00 | $3,500.00 | $3,500.00 |
| 0054 | Line, paint, broken, yellow, 6 in. (808-12764) | LFT | 11,245 | $0.20 | $0.28 | $0.28 |
| 0055 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 144,247 | $0.19 | $0.28 | $0.28 |
| 0056 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 76,689 | $0.19 | $0.28 | $0.28 |
| 0057 | Pavement message marking, paint, RXR (808-75140) | EACH | 2 | $250.00 | $611.00 | $611.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of August 5, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.