INDOT contract R-43608-A bid tabulation
BIKE AND PEDESTRIAN FACILITIES. Let by Indiana DOT on January 14, 2026, Perry, Vincennes. 4 bids received; low bid $1,338,759 by River Town Construction LLC.
- Owner
- Indiana DOT
- Letting
- 14 JAN 2026
- Pay items
- 97
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | River Town Construction LLC | $1,338,759 | Low |
| 2 | Jbi Construction Inc | $1,380,847 | +3.0% |
| 3 | Blankenberger Brothers Inc | $1,646,800 | +23% |
| 4 | E & B Paving LLC | $1,703,166 | +27% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. River Town Construction LLC | 2. Jbi Construction Inc | 3. Blankenberger Brothers Inc | 4. E & B Paving LLC |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $50,000 | $39,580 | $50,000 | $95,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $66,000 | $69,000 | $82,300 | $84,000 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $116,500 | $65,000 | $49,400 | $50,000 |
| 0012 | Excavation, common (203-02000) | CYS | 1,985 | $30.00 | $36.00 | $34.50 | $95.00 |
| 0013 | Borrow (203-02070) | CYS | 50 | $40.00 | $41.00 | $55.70 | $46.00 |
| 0014 | Stormwater management budget (205-12108) | DOL | 42,408.80 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0015 | Stormwater management implementation (205-12616) | LS | 1 | $6,500.00 | $35,000 | $30,000 | $10,000 |
| 0016 | SWQCP preparation (205-12618) | LS | 1 | $3,500.00 | $1,800.00 | $15,000 | $2,750.00 |
| 0017 | Subgrade treatment, type II (207-08264) | SYS | 3,781 | $22.00 | $30.00 | $34.45 | $24.30 |
| 0018 | Structure backfill, type 2 (211-09265) | CYS | 17 | $85.00 | $83.00 | $51.60 | $95.00 |
| 0019 | Geogrid, type IB (214-11796) | SYS | 2,244 | $2.75 | $1.10 | $1.85 | $0.79 |
| 0020 | Compacted aggregate, no. 53 (301-12234) | CYS | 337 | $55.00 | $131.50 | $100.00 | $104.77 |
| 0021 | Dense graded subbase (302-07455) | CYS | 376 | $145.00 | $98.75 | $145.40 | $97.44 |
| 0022 | Compacted aggregate, no. 53 (303-01180) | TON | 16 | $185.00 | $68.00 | $84.00 | $122.32 |
| 0023 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 133 | $15.00 | $18.75 | $26.60 | $14.60 |
| 0024 | Joint adhesive (401-11526) | LFT | 1,820 | $0.50 | $0.50 | $0.50 | $0.50 |
| 0025 | Asphalt for tack coat (406-05520) | TON | 1 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0026 | Fence, chain link, PVC coated, 48 in. , black (603-98225) | LFT | 70 | $140.00 | $77.03 | $77.03 | $164.00 |
| 0027 | Sidewalk, concrete (604-06070) | SYS | 1,617 | $64.00 | $56.00 | $79.10 | $78.59 |
| 0028 | Curb ramp, concrete (604-08086) | SYS | 52 | $125.00 | $145.00 | $223.30 | $156.85 |
| 0029 | Curb ramp, concrete 9 in (604-08086) | SYS | 142 | $160.00 | $165.00 | $292.75 | $195.24 |
| 0030 | Detectable warning surfaces (604-12083) | SYS | 4 | $205.00 | $294.00 | $395.00 | $210.00 |
| 0031 | Detectable warning surfaces , brick (604-12083) | SYS | 23 | $205.00 | $264.00 | $556.50 | $210.00 |
| 0032 | Curb, integral concrete, modified (605-06105) | LFT | 270 | $30.00 | $41.00 | $38.00 | $28.00 |
| 0033 | Curb, concrete (605-06120) | LFT | 717 | $28.00 | $42.00 | $45.50 | $18.00 |
| 0034 | Curb, concrete, type B , sloping (605-06121) | LFT | 44 | $38.00 | $50.00 | $60.10 | $32.00 |
| 0035 | Curb and gutter, concrete (605-06140) | LFT | 1,172 | $45.00 | $47.00 | $45.00 | $39.00 |
| 0036 | HMA for approaches, type B (610-07487) | TON | 371 | $161.00 | $161.00 | $161.00 | $161.00 |
| 0037 | PCCP for approaches, 6 in. (610-08446) | SYS | 146 | $85.00 | $63.00 | $90.00 | $79.00 |
| 0038 | PCCP for approaches, 9 in. (610-09108) | SYS | 2,098 | $76.00 | $85.00 | $95.25 | $72.00 |
| 0039 | Mobilization and demobilization for seeding (621-01004) | EACH | 8 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0040 | Seed mixture, type R (621-06553) | LBS | 237.80 | $20.00 | $20.00 | $20.00 | $20.00 |
| 0041 | Mulching material (621-06565) | TON | 2.30 | $850.00 | $850.00 | $850.00 | $850.00 |
| 0042 | Water (621-06567) | KGAL | 22.50 | $0.01 | $1.00 | $1.00 | $0.01 |
| 0043 | Computer system equipment (628-11976) | EACH | 1 | $500.00 | $430.00 | $1,000.00 | $700.00 |
| 0044 | Field office, type D (628-12683) | MOS | 12 | $1,000.00 | $2,675.00 | $1,850.00 | $2,861.32 |
| 0045 | Topsoil processing and distribution (629-000149) | SYS | 5,959 | $9.95 | $8.25 | $8.50 | $11.06 |
| 0046 | Topsoil amendment budget (629-000150) | DOL | 11,916 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0047 | Reinforcing bars, epoxy coated (703-06029) | LBS | 2,597 | $4.00 | $2.00 | $3.00 | $3.00 |
| 0048 | Pipe, type 2, circular, diameter 15 in. (715-05032) | LFT | 6 | $82.00 | $245.00 | $420.00 | $215.00 |
| 0049 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 84 | $52.00 | $89.00 | $200.00 | $275.00 |
| 0050 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 12 | $96.00 | $105.00 | $295.00 | $245.00 |
| 0051 | Video inspection for pipe (715-09064) | LFT | 117 | $27.50 | $27.80 | $25.00 | $27.80 |
| 0052 | Pipe end section, diameter 12 in. (715-46000) | EACH | 1 | $700.00 | $1,000.00 | $1,600.00 | $2,500.00 |
| 0053 | Pipe PVC, 4 in. (715-92037) | LFT | 7 | $20.00 | $45.00 | $221.90 | $123.10 |
| 0054 | Pipe, PVC, 15 in. (715-96960) | LFT | 8 | $84.00 | $131.00 | $294.75 | $190.03 |
| 0055 | Casting, inlet, adjust to grade (720-12797) | EACH | 7 | $225.00 | $465.00 | $1,600.00 | $997.60 |
| 0056 | Casting, manhole, adjust to grade (720-12798) | EACH | 8 | $250.00 | $465.00 | $1,300.00 | $997.60 |
| 0057 | Inlet, cap (720-44296) | EACH | 2 | $1,400.00 | $450.00 | $1,200.00 | $1,900.00 |
| 0058 | Inlet, type E7 (720-45030) | EACH | 1 | $4,400.00 | $2,500.00 | $3,500.00 | $4,800.00 |
| 0059 | Inlet, type HA5 (720-45042) | EACH | 8 | $4,200.00 | $3,350.00 | $3,800.00 | $5,000.00 |
| 0060 | Inlet, type J10 (720-45045) | EACH | 2 | $4,200.00 | $3,250.00 | $4,000.00 | $4,850.00 |
| 0061 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 9,920 | $2.20 | $2.45 | $2.45 | $2.45 |
| 0062 | Temporary transverse pavement marking, removable, 6 in. (801-06217) | LFT | 628 | $3.35 | $3.15 | $3.15 | $3.15 |
| 0063 | Construction sign, type A (801-06640) | EACH | 22 | $165.00 | $165.00 | $165.00 | $165.00 |
| 0064 | Construction sign, type B (801-06645) | EACH | 13 | $98.00 | $98.00 | $98.00 | $98.00 |
| 0065 | Maintaining traffic (801-06775) | LS | 1 | $70,000 | $60,415 | $159,271 | $198,000 |
| 0066 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 1 | $10,374 | $14,300 | $10,374 | $14,300 |
| 0067 | Barricade, type III-B (801-07119) | LFT | 102 | $14.00 | $14.00 | $14.00 | $14.00 |
| 0068 | Temporary traffic barrier, type 2 (801-08401) | LFT | 307 | $33.00 | $31.00 | $50.00 | $50.45 |
| 0069 | Temporary curb ramp (801-11990) | EACH | 2 | $5,000.00 | $1,180.00 | $1,350.00 | $825.22 |
| 0070 | Temporary pedestrian channelizer (801-12862) | LFT | 348 | $23.00 | $35.00 | $35.50 | $37.25 |
| 0071 | Sign, panel, relocate (802-02475) | EACH | 2 | $250.00 | $160.00 | $160.00 | $160.00 |
| 0072 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 156 | $25.00 | $31.00 | $31.00 | $31.00 |
| 0073 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 50 | $25.00 | $28.00 | $28.00 | $28.00 |
| 0074 | Sign, double-faced, sheet, with legend, 0.100 in. thickness (802-09839) | SFT | 24 | $45.00 | $45.00 | $45.00 | $45.00 |
| 0075 | Handhole, signal, type 1 (805-01842) | EACH | 1 | $1,500.00 | $2,250.00 | $2,250.00 | $2,250.00 |
| 0076 | Pedestrian signal head, countdown, 18 in. (805-02150) | EACH | 4 | $1,000.00 | $800.00 | $800.00 | $800.00 |
| 0077 | Signal pole foundation, 24 in. X 24 in. X 36 in. (805-02645) | EACH | 4 | $1,000.00 | $1,800.00 | $1,800.00 | $1,800.00 |
| 0078 | Conduit, HDPE, 2 in. schedule 80 (805-11815) | LFT | 140 | $25.00 | $65.00 | $65.00 | $65.00 |
| 0079 | Pedestrian push button, APS (805-11817) | EACH | 4 | $1,250.00 | $1,200.00 | $1,200.00 | $1,200.00 |
| 0080 | Signal cable, roadway loop, copper, 1C/14 gauge (805-78470) | LFT | 220 | $0.65 | $2.50 | $2.50 | $2.50 |
| 0081 | Signal cable, control, copper, 3C/14 gauge (805-78480) | LFT | 770 | $1.65 | $2.50 | $2.50 | $2.50 |
| 0082 | Signal cable, control, copper, 5C/14 gauge (805-78485) | LFT | 810 | $2.15 | $2.80 | $2.80 | $2.80 |
| 0083 | Saw cut for roadway loop detector and sealant (805-78795) | LFT | 90 | $10.00 | $22.00 | $22.00 | $22.00 |
| 0084 | Signal pole, pedestal, 10 FT (805-90005) | EACH | 4 | $1,000.00 | $1,200.00 | $1,200.00 | $1,200.00 |
| 0085 | Line, thermoplastic, solid, white, 4 in. (808-06703) | LFT | 44 | $9.95 | $9.95 | $9.95 | $9.95 |
| 0086 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 95 | $2.95 | $2.95 | $2.95 | $2.95 |
| 0087 | Line, paint, solid, yellow, 4 in. (808-06714) | LFT | 1,524 | $0.80 | $0.80 | $0.80 | $0.80 |
| 0088 | Pavement message marking, paint, lane indication arrow (808-06723) | EACH | 2 | $130.00 | $130.00 | $130.00 | $130.00 |
| 0089 | Transverse marking, paint, stop line, white, 24 in. (808-06726) | LFT | 60 | $14.95 | $14.95 | $14.95 | $14.95 |
| 0090 | Grooving for pavement markings (808-12032) | LFT | 244 | $3.95 | $3.95 | $3.95 | $3.95 |
| 0091 | Transverse marking, paint, crosswalk line, white, 6 in. (808-75100) | LFT | 284 | $2.95 | $2.95 | $2.95 | $2.95 |
| 0092 | Line, thermoplastic, solid, yellow, 4 in. (808-75245) | LFT | 200 | $2.95 | $2.95 | $2.95 | $2.95 |
| 0093 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 138 | $6.95 | $6.95 | $6.95 | $6.95 |
| 0094 | Transverse marking, thermoplastic, crosswalk line, white, 6 in. (808-75300) | LFT | 621 | $2.95 | $2.95 | $2.95 | $2.95 |
| 0095 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 2 | $200.00 | $200.00 | $200.00 | $200.00 |
| 0096 | Temporary traffic signal installation, maintain (801-06539) | LS | 1 | $5,000.00 | $9,800.00 | $9,800.00 | $9,800.00 |
| 0097 | Flashing arrow sign (801-06710) | DAY | 180 | $15.00 | $15.00 | $15.00 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.