INDOT contract R-43812-A bid tabulation
SMALL STRUCTURE PIPE LINING AND REPLACEMENT. Let by Indiana DOT on December 10, 2025, Allen, Fort Wayne. 4 bids received; low bid $1,860,000 by Morphey Construction Inc..
- Owner
- Indiana DOT
- Letting
- 10 DEC 2025
- Pay items
- 84
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Morphey Construction Inc. | $1,860,000 | Low |
| 2 | Brooks Construction Company Inc | $1,960,986 | +5.0% |
| 3 | E & B Paving LLC | $2,184,179 | +17% |
| 4 | Infrastructure Systems Inc | $2,387,687 | +28% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Morphey Construction Inc. | 2. Brooks Construction Company Inc | 3. E & B Paving LLC | 4. Infrastructure Systems Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $15,000 | $15,000 | $15,000 | $20,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $93,000 | $95,000 | $109,000 | $200,000 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $15,000 | $19,000 | $21,000 | $25,000 |
| 0012 | Present structure, remove, structure no. 10 (202-51330) | LS | 1 | $15,000 | $35,000 | $102,710 | $45,000 |
| 0013 | Fence, chain link, remove (202-91840) | LFT | 202 | $5.00 | $9.00 | $13.56 | $20.00 |
| 0014 | Pipe, remove (202-96133) | LFT | 89 | $35.00 | $23.00 | $43.49 | $20.00 |
| 0015 | Excavation, common (203-02000) | CYS | 305 | $55.00 | $65.00 | $55.00 | $110.00 |
| 0016 | Borrow (203-02070) | CYS | 5 | $100.00 | $100.00 | $170.00 | $100.00 |
| 0017 | Excavation, waterway (203-51223) | CYS | 150 | $120.00 | $80.00 | $110.00 | $275.00 |
| 0018 | Pump around (205-11626) | EACH | 4 | $5,000.00 | $12,000 | $18,000 | $7,500.00 |
| 0019 | Stormwater management budget (205-12108) | DOL | 38,040 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0020 | Stormwater management implementation (205-12616) | LS | 1 | $5,000.00 | $10,000 | $25,000 | $10,000 |
| 0021 | Excavation, wet (206-51220) | CYS | 10 | $130.00 | $115.00 | $110.00 | $275.00 |
| 0022 | Subgrade treatment, type IC (207-09935) | SYS | 264 | $60.00 | $40.00 | $35.00 | $45.00 |
| 0023 | Structure backfill, type 2 (211-09265) | CYS | 118 | $100.00 | $75.00 | $115.00 | $80.00 |
| 0024 | Geotextile for pavement, type 2B (214-12239) | SYS | 178 | $5.00 | $4.70 | $5.00 | $6.00 |
| 0025 | Compacted aggregate, no. 8 (301-12233) | CYS | 18 | $150.00 | $89.00 | $84.00 | $100.00 |
| 0026 | Compacted aggregate, no. 53 (303-01180) | TON | 27 | $70.00 | $60.00 | $100.00 | $60.00 |
| 0027 | Widening with HMA, type B (304-07493) | TON | 28 | $300.00 | $140.00 | $400.00 | $150.00 |
| 0028 | Milling, transition (306-08043) | SYS | 196 | $30.00 | $30.00 | $39.00 | $35.00 |
| 0029 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 29 | $135.00 | $135.00 | $400.00 | $150.00 |
| 0030 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 22 | $145.00 | $145.00 | $478.00 | $150.00 |
| 0031 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 55 | $125.00 | $125.00 | $220.00 | $140.00 |
| 0032 | Joint adhesive (401-11526) | LFT | 700 | $1.00 | $0.70 | $0.35 | $1.00 |
| 0033 | Asphalt for tack coat (406-05521) | SYS | 814 | $1.00 | $0.40 | $0.15 | $1.00 |
| 0034 | Guardrail, remove (601-02241) | LFT | 425 | $3.00 | $7.00 | $7.22 | $12.00 |
| 0035 | Fence, chain link, 48 in. (603-06045) | LFT | 256 | $48.00 | $48.00 | $48.00 | $45.00 |
| 0036 | Milled HMA corrugations, conventional (606-12399) | LFT | 390 | $18.57 | $18.00 | $26.61 | $25.00 |
| 0037 | Right-of-way marker (615-06490) | EACH | 10 | $188.00 | $188.00 | $188.00 | $600.00 |
| 0038 | Monument, type B (615-06505) | EACH | 2 | $1,800.00 | $1,800.00 | $1,800.00 | $1,500.00 |
| 0039 | Riprap, relaid (616-01763) | SYS | 272 | $140.00 | $31.00 | $23.00 | $50.00 |
| 0040 | Riprap, class 1 (616-05688) | TON | 318 | $160.00 | $150.00 | $86.00 | $175.00 |
| 0041 | Riprap, class 2 (616-05689) | TON | 223 | $160.00 | $120.00 | $86.00 | $175.00 |
| 0042 | Riprap, revetment (616-06405) | TON | 167 | $160.00 | $55.00 | $83.00 | $100.00 |
| 0043 | Riprap, uniform (616-06451) | TON | 81 | $150.00 | $105.00 | $77.00 | $175.00 |
| 0044 | Geotextile for riprap, type 1A (616-12246) | SYS | 547 | $5.00 | $5.00 | $1.71 | $6.00 |
| 0045 | Geotextile for riprap, type 2A (616-12248) | SYS | 349 | $5.00 | $5.00 | $1.72 | $6.00 |
| 0046 | Mobilization and demobilization for seeding (621-01004) | EACH | 4 | $500.00 | $500.00 | $500.00 | $550.00 |
| 0047 | Mulched seeding, type R (621-06559) | SYS | 3,483 | $9.00 | $2.48 | $3.25 | $3.00 |
| 0048 | Mulched seeding, type U (621-06560) | SYS | 1,561 | $9.00 | $3.65 | $4.00 | $4.00 |
| 0049 | Water (621-06567) | KGAL | 1 | $1.00 | $10.00 | $10.00 | $10.00 |
| 0050 | Sodding (621-06574) | SYS | 42 | $120.00 | $43.75 | $80.00 | $45.00 |
| 0051 | Field office, type D (628-12683) | MOS | 12 | $3,000.00 | $4,400.00 | $4,400.00 | $4,400.00 |
| 0052 | Field drilled hole in concrete (702-51863) | EACH | 40 | $50.00 | $3.00 | $70.00 | $25.00 |
| 0053 | Concrete, A (702-90915) | CYS | 9 | $2,000.00 | $1,900.00 | $1,402.00 | $3,300.00 |
| 0054 | Reinforcing bars (703-06028) | LBS | 109 | $10.00 | $29.00 | $7.67 | $5.00 |
| 0055 | Embedded galvanic anode (703-08247) | EACH | 60 | $40.00 | $39.00 | $39.00 | $45.00 |
| 0056 | Patching concrete structures (710-09158) | SFT | 25 | $200.00 | $174.00 | $174.00 | $200.00 |
| 0057 | Waterproofing membrane, type 2 (714-000086) | SFT | 2,016 | $4.00 | $5.00 | $3.00 | $7.00 |
| 0058 | Structure, reinforced concrete, box sections, 5 FT X 5 FT (714-11190) | LFT | 112 | $770.00 | $650.00 | $900.00 | $1,000.00 |
| 0059 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 12 | $100.00 | $110.00 | $127.00 | $85.00 |
| 0060 | Pipe, type 3, circular, diameter 12 in. (715-05168) | LFT | 33 | $100.00 | $80.00 | $115.00 | $100.00 |
| 0061 | Perpetuation, existing pipe (725-10245) | EACH | 1 | $1,000.00 | $50.00 | $15,500 | $1,500.00 |
| 0062 | Pipe liner, cured-in- place, min. area 21.9 SFT (725-11741) | LFT | 152 | $1,220.00 | $1,219.27 | $1,638.78 | $1,700.00 |
| 0063 | Liner pipe, thermoplastic, deformed, 36.4-38.5 SFT (725-11762) | LFT | 230 | $2,100.00 | $1,780.00 | $2,057.24 | $2,707.00 |
| 0064 | Pipe liner, cured-in- place, min. area 26.8 SFT (725-12052) | LFT | 352 | $890.00 | $890.54 | $1,071.69 | $1,207.00 |
| 0065 | Temporary pavement message marking, lane indication arrow (801-01504) | EACH | 8 | $100.00 | $169.00 | $250.00 | $110.00 |
| 0066 | Road closure sign assembly (801-04308) | EACH | 6 | $125.00 | $244.00 | $300.00 | $140.00 |
| 0067 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 1,445 | $2.00 | $2.04 | $2.50 | $3.00 |
| 0068 | Temporary transverse pavement marking, 24 in. (801-06216) | LFT | 21 | $12.00 | $11.94 | $20.00 | $15.00 |
| 0069 | Detour route marker assembly (801-06625) | EACH | 60 | $75.00 | $147.00 | $175.00 | $100.00 |
| 0070 | Construction sign, type A (801-06640) | EACH | 53 | $175.00 | $196.00 | $225.00 | $200.00 |
| 0071 | Construction sign, type B (801-06645) | EACH | 15 | $50.00 | $102.00 | $150.00 | $55.00 |
| 0072 | Maintaining traffic (801-06775) | LS | 1 | $29,294 | $256,415 | $108,000 | $15,000 |
| 0073 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 6 | $5,000.00 | $4,925.00 | $4,925.00 | $6,000.00 |
| 0074 | Barricade, type III-A (801-07118) | LFT | 84 | $12.00 | $15.04 | $18.00 | $14.00 |
| 0075 | Barricade, type III-B (801-07119) | LFT | 228 | $12.00 | $15.04 | $18.00 | $14.00 |
| 0076 | Temporary traffic barrier, type 2 (801-08401) | LFT | 600 | $40.00 | $32.50 | $32.50 | $35.00 |
| 0077 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 1,200 | $40.00 | $32.50 | $32.50 | $35.00 |
| 0078 | Temporary pavement marking, removable, 12 in. (801-09087) | LFT | 628 | $4.00 | $6.34 | $5.00 | $5.00 |
| 0079 | Truck mounted attenuator (801-12042) | DAY | 2 | $500.00 | $450.00 | $2,475.76 | $550.00 |
| 0080 | Law enforcement officer (801-12324) | HRS | 16 | $60.00 | $60.00 | $60.00 | $60.00 |
| 0081 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 8 | $400.00 | $913.00 | $375.00 | $425.00 |
| 0082 | Line, paint, broken, yellow, 6 in. (808-12764) | LFT | 33 | $5.00 | $2.61 | $1.00 | $6.00 |
| 0083 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 260 | $2.00 | $1.44 | $1.00 | $3.00 |
| 0084 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 2 | $10.00 | $25.00 | $130.00 | $28.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of December 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.